6502-72-001 Miscellaneous Concrete
6502-72-001 · let Aug 11, 2026 · Midland, Odessa · Routine Maintenance Project - Sealed
$1,037,872Low bid: SCOTT TUCKER CONSTRUCTION COMPANY, LLC+45.4% vs estimate $714,000
$185,562Left on the table17.9% gap to the second bid
2BiddersSpread 18% low to high
38Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $1,037,872 | 45.4% | $185,562 | 21+$470,064 | 1-$423,850 | |
| 2 | E.V.G. ENTERPRISE | $1,223,434 | +17.9% | 71.3% | 19+$654,097 | 1-$473,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
SCOTT TUCKER CONSTRUCTION COMPANY, LLC vs E.V.G. ENTERPRISE, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $12,529.00 | $120,000.00 | $1,712.97 | $214,942 |
| 344-7004 SP MIXES SP-B PG70-22 | 180 TON | $862.00 | $152.00 | $147.51 | -$127,800 |
| 432-7005 RIPRAP (CONC)(CL B) | 56 CY | $1,051.00 | $2,500.00 | $556.52 | $81,144 |
| 344-7051 SP MIXES SP-D PG70-22 | 90 TON | $888.00 | $159.00 | $139.43 | -$65,610 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $50,000.00 | $523,850.32 | -$50,000 |
| 529-7009 CONC CURB & GUTTER (TY II) | 620 LF | $63.00 | $113.00 | $32.57 | $31,000 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $665.00 | $1,000.00 | $217.57 | $30,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $14,664.00 | $20,000.00 | $11,585.04 | $26,680 |
| 496-7006 REMOV STR (HEADWALL) | 3 EA | $1,950.00 | $7,800.00 | $1,533.90 | $17,550 |
| 496-7005 REMOV STR (WINGWALL) | 6 EA | $2,244.00 | $4,850.00 | $1,898.40 | $15,636 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 400 SY | $59.00 | $25.00 | $6.84 | -$13,600 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $91.00 | $300.00 | $64.00 | $12,540 |
| 112-7003 SUBGR WIDEN (OC) | 800 SY | $52.00 | $66.00 | $22.87 | $11,200 |
| 132-7011 EMBANK (FNL)(OC)(TY D) | 80 CY | $185.00 | $45.00 | $32.39 | -$11,200 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $8,001.00 | $10,000.00 | $9,253.78 | $9,995 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 732 LF | $7.00 | $20.00 | $0.4757 | $9,516 |
| 531-7001 CONC SIDEWALKS (4") | 17 SY | $1,237.00 | $770.00 | $70.57 | -$7,939 |
| 467-7129 SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1)(C) | 4 EA | $12,554.00 | $14,470.00 | $10,383.10 | $7,664 |
| 150-7002 BLADING | 15 HR | $929.00 | $500.00 | $171.50 | -$6,435 |
| 104-7015 REMOV CONC (CURB RAMP) | 9 SY | $732.00 | $55.00 | $37.29 | -$6,093 |
Positive: the low bidder was cheaper on that item. These 20 items account for $179,340 of the $185,562 gap.
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7004 SP MIXES SP-B PG70-22 | 180 TON | $862.00 | $147.51 | 5.84x | $128,608 |
| 344-7051 SP MIXES SP-D PG70-22 | 90 TON | $888.00 | $139.43 | 6.37x | $67,371 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $665.00 | $217.57 | 3.06x | $40,269 |
| 432-7005 RIPRAP (CONC)(CL B) | 56 CY | $1,051.00 | $556.52 | 1.89x | $27,691 |
| 112-7003 SUBGR WIDEN (OC) | 800 SY | $52.00 | $22.87 | 2.27x | $23,304 |
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $12,529.00 | $1,712.97 | 7.31x | $21,632 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 400 SY | $59.00 | $6.84 | 8.63x | $20,865 |
| 531-7001 CONC SIDEWALKS (4") | 17 SY | $1,237.00 | $70.57 | 17.53x | $19,829 |
| 529-7009 CONC CURB & GUTTER (TY II) | 620 LF | $63.00 | $32.57 | 1.93x | $18,868 |
| 132-7011 EMBANK (FNL)(OC)(TY D) | 80 CY | $185.00 | $32.39 | 5.71x | $12,209 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
E.V.G. ENTERPRISE: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 2 EA | $120,000.00 | $1,712.97 | 70.05x | $236,574 |
| 432-7005 RIPRAP (CONC)(CL B) | 56 CY | $2,500.00 | $556.52 | 4.49x | $108,835 |
| 505-7001 TMA (STATIONARY) | 90 DAY | $1,000.00 | $217.57 | 4.60x | $70,419 |
| 529-7009 CONC CURB & GUTTER (TY II) | 620 LF | $113.00 | $32.57 | 3.47x | $49,868 |
| 112-7003 SUBGR WIDEN (OC) | 800 SY | $66.00 | $22.87 | 2.89x | $34,504 |
| 496-7006 REMOV STR (HEADWALL) | 3 EA | $7,800.00 | $1,533.90 | 5.09x | $18,798 |
| 496-7005 REMOV STR (WINGWALL) | 6 EA | $4,850.00 | $1,898.40 | 2.55x | $17,710 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 732 LF | $20.00 | $0.4757 | 42.04x | $14,292 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $300.00 | $64.00 | 4.69x | $14,160 |
| 104-7017 REMOV CONC (CURB & GUTTER) | 640 LF | $30.00 | $8.04 | 3.73x | $14,054 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |