FY 27 CRACKSEAL - HOT POUR - SOUTH
6502-69-001 · let Aug 11, 2026 · Smith, Tyler · Routine Maintenance Project
$592,020Low bid: D & M CONTRACTORS, LLC-6.4% vs estimate $632,576
$36,151Left on the table6.1% gap to the second bid
6BiddersSpread 83% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | D & M CONTRACTORS, LLC | $592,020 | -6.4% | $36,151 | 0 | 2-$512,058 | |
| 2 | FYL ENTERPRISES, LLC | $628,171 | +6.1% | -0.7% | $146,648 | 0 | 2-$462,217 |
| 3 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $774,819 | +30.9% | 22.5% | $145,706 | 0 | 2-$539,638 |
| 4 | SCOUT 5 CONSTRUCTION LLC | $920,525 | +55.5% | 45.5% | $45,499 | 0 | 2-$487,217 |
| 5 | GARRET SHIELDS INFRASTRUCTURE | $966,024 | +63.2% | 52.7% | $116,142 | 0 | 1-$448,850 |
| 6 | CRACKSEAL OF TEXAS, LLC | $1,082,166 | +82.8% | 71.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
D & M CONTRACTORS, LLC vs FYL ENTERPRISES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $80,000.00 | $523,850.32 | $50,000 |
| 712-7003 JT / CRCK SEAL (HOT - POURED RUBBER) | 577.016 LMI | $972.00 | $950.00 | $936.68 | -$12,694 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 10 DAY | $100.00 | $0.5000 | $117.34 | -$995 |
| 505-7003 TMA (MOBILE OPERATION) | 80 DAY | $2.00 | $0.0100 | $229.60 | -$159 |
Positive: the low bidder was cheaper on that item. These 4 items account for $36,151 of the $36,151 gap.
D & M CONTRACTORS, LLC: unbalanced items
Placed 1FYL ENTERPRISES, LLC: unbalanced items
Placed 2GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items
Placed 3SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 4GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |