Bid Tab X-ray: 6502-69-001

Aug 11, 2026 · Smith Sign up free
Set your company to personalize scores

FY 27 CRACKSEAL - HOT POUR - SOUTH

6502-69-001 · let Aug 11, 2026 · Smith, Tyler · Routine Maintenance Project

$592,020Low bid: D & M CONTRACTORS, LLC-6.4% vs estimate $632,576
$36,151Left on the table6.1% gap to the second bid
6BiddersSpread 83% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1D & M CONTRACTORS, LLC $592,020-6.4% $36,151 0 2-$512,058
2FYL ENTERPRISES, LLC $628,171+6.1%-0.7% $146,648 0 2-$462,217
3GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY $774,819+30.9%22.5% $145,706 0 2-$539,638
4SCOUT 5 CONSTRUCTION LLC $920,525+55.5%45.5% $45,499 0 2-$487,217
5GARRET SHIELDS INFRASTRUCTURE $966,024+63.2%52.7% $116,142 0 1-$448,850
6CRACKSEAL OF TEXAS, LLC $1,082,166+82.8%71.1%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

D & M CONTRACTORS, LLC vs FYL ENTERPRISES, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7001 MOBILIZATION1 LS $30,000.00$80,000.00$523,850.32 $50,000
712-7003 JT / CRCK SEAL (HOT - POURED RUBBER)577.016 LMI $972.00$950.00$936.68 -$12,694
7010-7002 MAINTENANCE SPEED LIMIT SIGNING10 DAY $100.00$0.5000$117.34 -$995
505-7003 TMA (MOBILE OPERATION)80 DAY $2.00$0.0100$229.60 -$159

Positive: the low bidder was cheaper on that item. These 4 items account for $36,151 of the $36,151 gap.

D & M CONTRACTORS, LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $30,000.00$523,850.320.06x-$493,850
505-7003 TMA (MOBILE OPERATION)80 DAY $2.00$229.600.01x-$18,208

FYL ENTERPRISES, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $80,000.00$523,850.320.15x-$443,850
505-7003 TMA (MOBILE OPERATION)80 DAY $0.0100$229.600.00x-$18,367

GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,500.00$523,850.320.00x-$521,350
505-7003 TMA (MOBILE OPERATION)80 DAY $1.00$229.600.00x-$18,288

SCOUT 5 CONSTRUCTION LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $55,000.00$523,850.320.10x-$468,850
505-7003 TMA (MOBILE OPERATION)80 DAY $0.0100$229.600.00x-$18,367

GARRET SHIELDS INFRASTRUCTURE: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $75,000.00$523,850.320.14x-$448,850