On Call Ditch and Culvert FY27 GAO

6502-67-001 · let Aug 20, 2026 · Hunt, Paris · Routine Maintenance Project - Sealed

$380,291Low bid: TEXAS DRAINAGE INC.-42.2% vs estimate $658,000
$276,749Left on the table72.8% gap to the second bid
3BiddersSpread 94% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TEXAS DRAINAGE INC. $380,291-42.2% $276,749 0 3-$451,254
2ADVANCED BARRICADES OF AMERICA, LLC $657,040+72.8%-0.1% $80,160 1+$22,790 2-$425,296
3CATOCON, INC. $737,200+93.9%12.0% 1+$71,297 2-$429,643

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

TEXAS DRAINAGE INC. vs ADVANCED BARRICADES OF AMERICA, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
760-7001 DITCH CLEANING AND RESHAPING (FOOT)200,000 LF $1.68$2.82$1.96 $228,000
500-7002 MOBILIZATION (CALLOUT)12 EA $0.9900$2,500.00$600.85 $29,988
480-7001 CLEAN EXIST CULVERTS280 EA $158.00$225.00$1,712.97 $18,760
505-7001 TMA (STATIONARY)40 DAY $0.9900$1.00$217.57 $0

Positive: the low bidder was cheaper on that item. These 4 items account for $276,749 of the $276,749 gap.

TEXAS DRAINAGE INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
480-7001 CLEAN EXIST CULVERTS280 EA $158.00$1,712.970.09x-$435,393
505-7001 TMA (STATIONARY)40 DAY $0.9900$217.570.00x-$8,663
500-7002 MOBILIZATION (CALLOUT)12 EA $0.9900$600.850.00x-$7,198

ADVANCED BARRICADES OF AMERICA, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)12 EA $2,500.00$600.854.16x$22,790
480-7001 CLEAN EXIST CULVERTS280 EA $225.00$1,712.970.13x-$416,633
505-7001 TMA (STATIONARY)40 DAY $1.00$217.570.00x-$8,663

CATOCON, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)40 DAY $2,000.00$217.579.19x$71,297
480-7001 CLEAN EXIST CULVERTS280 EA $200.00$1,712.970.12x-$423,633
500-7002 MOBILIZATION (CALLOUT)12 EA $100.00$600.850.17x-$6,010