Crack Seal 01 0826
6500-43-001 · let Aug 12, 2026 · Navarro, Dallas · Routine Maintenance Project - Sealed
$258,716Low bid: SCOUT 5 CONSTRUCTION LLC-7.5% vs estimate $279,635
$1,143Left on the table0.4% gap to the second bid
5BiddersSpread 76% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOUT 5 CONSTRUCTION LLC | $258,716 | -7.5% | $1,143 | 0 | 3-$549,630 | |
| 2 | D & M CONTRACTORS, LLC | $259,859 | +0.4% | -7.1% | $45,442 | 0 | 3-$547,840 |
| 3 | FYL ENTERPRISES, LLC | $305,301 | +18.0% | 9.2% | $18,066 | 0 | 3-$523,330 |
| 4 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $323,366 | +25.0% | 15.6% | $131,161 | 0 | 3-$549,602 |
| 5 | CRACKSEAL OF TEXAS, LLC | $454,527 | +75.7% | 62.5% | 0 | 2-$475,020 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SCOUT 5 CONSTRUCTION LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,700.00 | $5,000.00 | $523,850.32 | $1,300 |
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 289.79 LMI | $880.00 | $877.77 | $868.20 | -$646 |
| 505-7001 TMA (STATIONARY) | 29 DAY | $0.0100 | $10.00 | $217.57 | $290 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $0.0100 | $100.00 | $11,585.04 | $200 |
Positive: the low bidder was cheaper on that item. These 4 items account for $1,143 of the $1,143 gap.