Parking Lot
6499-90-001 · let Aug 20, 2026 · Lamar, Paris · Routine Maintenance Project - Sealed
$262,821Low bid: HIGHWAY 19 CONSTRUCTION LLC-10.2% vs estimate $292,705
$6,993Left on the table2.7% gap to the second bid
2BiddersSpread 3% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HIGHWAY 19 CONSTRUCTION LLC | $262,821 | -10.2% | $6,993 | 2+$12,160 | 2-$523,605 | |
| 2 | RB CONTRACTING, LLC | $269,814 | +2.7% | -7.8% | 7+$54,448 | 2-$540,605 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
HIGHWAY 19 CONSTRUCTION LLC vs RB CONTRACTING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 529-7009 CONC CURB & GUTTER (TY II) | 281 LF | $55.00 | $120.00 | $32.57 | $18,265 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $1,000.00 | $11,585.04 | -$12,000 |
| 360-7001 CONC PVMT (CRCP) (7") | 1,264 SY | $109.00 | $100.00 | $92.73 | -$11,376 |
| 110-7001 EXCAV (ROADWAY) | 1,359 CY | $15.00 | $10.00 | $11.68 | -$6,795 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $15,000.00 | $523,850.32 | -$5,000 |
| 134-7006 BACKFILL (TY A) | 707 LF | $5.00 | $12.00 | $1.66 | $4,949 |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP) | 76 SY | $25.00 | $90.00 | $17.88 | $4,940 |
| 251-7025 REWORK BS MTL (TY B)(6")(ORD COMP) | 87 SY | $10.00 | $50.00 | $3.44 | $3,480 |
| 100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA) | 6 EA | $2,500.00 | $2,000.00 | $1,166.77 | -$3,000 |
| 168-7001 VEGETATIVE WATERING | 3 TGL | $100.00 | $1,000.00 | $8.43 | $2,700 |
| 666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL) | 430 LF | $10.00 | $16.00 | $0.3245 | $2,580 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 34 SY | $25.00 | $90.00 | $19.70 | $2,210 |
| 531-7002 CONC SIDEWALKS (5") | 95 SY | $85.00 | $100.00 | $68.80 | $1,425 |
| 530-7006 DRIVEWAYS (CONC) | 54 SY | $110.00 | $132.00 | $109.20 | $1,188 |
| 162-7002 BLOCK SODDING | 436 SY | $10.00 | $12.00 | $4.39 | $872 |
| 100-7003 PREP ROW (TREE REMOVE) (0"-12" DIA) | 1 EA | $200.00 | $1,000.00 | $506.92 | $800 |
| 194-7007 RDSIDE AMENITY (WHEEL STOP) | 14 EA | $300.00 | $250.00 | $221.81 | -$700 |
| 668-7133 PRE PM TY C(BL&WH)(ACC PRK)(W/BORDR)LG | 1 EA | $100.00 | $775.00 | $346.62 | $675 |
| 105-7004 RMV (4"-8") TRT/UNTRT BASE & ASPH PAV | 121 SY | $15.00 | $20.00 | $4.38 | $605 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 60 LF | $5.00 | $15.00 | $3.92 | $600 |
Positive: the low bidder was cheaper on that item. These 20 items account for $6,418 of the $6,993 gap.
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA) | 6 EA | $2,500.00 | $1,166.77 | 2.14x | $7,999 |
| 666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL) | 430 LF | $10.00 | $0.3245 | 30.82x | $4,160 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $523,850.32 | 0.04x | -$503,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
RB CONTRACTING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7009 CONC CURB & GUTTER (TY II) | 281 LF | $120.00 | $32.57 | 3.68x | $24,568 |
| 134-7006 BACKFILL (TY A) | 707 LF | $12.00 | $1.66 | 7.25x | $7,313 |
| 666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL) | 430 LF | $16.00 | $0.3245 | 49.31x | $6,740 |
| 104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP) | 76 SY | $90.00 | $17.88 | 5.03x | $5,481 |
| 251-7025 REWORK BS MTL (TY B)(6")(ORD COMP) | 87 SY | $50.00 | $3.44 | 14.54x | $4,051 |
| 162-7002 BLOCK SODDING | 436 SY | $12.00 | $4.39 | 2.73x | $3,319 |
| 168-7001 VEGETATIVE WATERING | 3 TGL | $1,000.00 | $8.43 | 118.57x | $2,975 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1,000.00 | $11,585.04 | 0.09x | -$31,755 |