Parking Lot

6499-90-001 · let Aug 20, 2026 · Lamar, Paris · Routine Maintenance Project - Sealed

$262,821Low bid: HIGHWAY 19 CONSTRUCTION LLC-10.2% vs estimate $292,705
$6,993Left on the table2.7% gap to the second bid
2BiddersSpread 3% low to high
24Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1HIGHWAY 19 CONSTRUCTION LLC $262,821-10.2% $6,993 2+$12,160 2-$523,605
2RB CONTRACTING, LLC $269,814+2.7%-7.8% 7+$54,448 2-$540,605

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

HIGHWAY 19 CONSTRUCTION LLC vs RB CONTRACTING, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
529-7009 CONC CURB & GUTTER (TY II)281 LF $55.00$120.00$32.57 $18,265
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $5,000.00$1,000.00$11,585.04 -$12,000
360-7001 CONC PVMT (CRCP) (7")1,264 SY $109.00$100.00$92.73 -$11,376
110-7001 EXCAV (ROADWAY)1,359 CY $15.00$10.00$11.68 -$6,795
500-7001 MOBILIZATION1 LS $20,000.00$15,000.00$523,850.32 -$5,000
134-7006 BACKFILL (TY A)707 LF $5.00$12.00$1.66 $4,949
104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP)76 SY $25.00$90.00$17.88 $4,940
251-7025 REWORK BS MTL (TY B)(6")(ORD COMP)87 SY $10.00$50.00$3.44 $3,480
100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA)6 EA $2,500.00$2,000.00$1,166.77 -$3,000
168-7001 VEGETATIVE WATERING3 TGL $100.00$1,000.00$8.43 $2,700
666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL)430 LF $10.00$16.00$0.3245 $2,580
104-7011 REMOV CONC (DRIVEWAYS)34 SY $25.00$90.00$19.70 $2,210
531-7002 CONC SIDEWALKS (5")95 SY $85.00$100.00$68.80 $1,425
530-7006 DRIVEWAYS (CONC)54 SY $110.00$132.00$109.20 $1,188
162-7002 BLOCK SODDING436 SY $10.00$12.00$4.39 $872
100-7003 PREP ROW (TREE REMOVE) (0"-12" DIA)1 EA $200.00$1,000.00$506.92 $800
194-7007 RDSIDE AMENITY (WHEEL STOP)14 EA $300.00$250.00$221.81 -$700
668-7133 PRE PM TY C(BL&WH)(ACC PRK)(W/BORDR)LG1 EA $100.00$775.00$346.62 $675
105-7004 RMV (4"-8") TRT/UNTRT BASE & ASPH PAV121 SY $15.00$20.00$4.38 $605
506-7039 TEMP SEDMT CONT FENCE (INSTALL)60 LF $5.00$15.00$3.92 $600

Positive: the low bidder was cheaper on that item. These 20 items account for $6,418 of the $6,993 gap.

HIGHWAY 19 CONSTRUCTION LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
100-7005 PREP ROW (TREE REMOVE) (24"-36" DIA)6 EA $2,500.00$1,166.772.14x$7,999
666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL)430 LF $10.00$0.324530.82x$4,160
500-7001 MOBILIZATION1 LS $20,000.00$523,850.320.04x-$503,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $5,000.00$11,585.040.43x-$19,755

RB CONTRACTING, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
529-7009 CONC CURB & GUTTER (TY II)281 LF $120.00$32.573.68x$24,568
134-7006 BACKFILL (TY A)707 LF $12.00$1.667.25x$7,313
666-7405 REFL PAV MRK TY I (W)4"(SLD)(100MIL)430 LF $16.00$0.324549.31x$6,740
104-7013 REMOV CONC (SIDEWALK, RAMP OR SUP)76 SY $90.00$17.885.03x$5,481
251-7025 REWORK BS MTL (TY B)(6")(ORD COMP)87 SY $50.00$3.4414.54x$4,051
162-7002 BLOCK SODDING436 SY $12.00$4.392.73x$3,319
168-7001 VEGETATIVE WATERING3 TGL $1,000.00$8.43118.57x$2,975
500-7001 MOBILIZATION1 LS $15,000.00$523,850.320.03x-$508,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $1,000.00$11,585.040.09x-$31,755