FY2027 AAO Crack Seal
6499-75-001 · let Aug 18, 2026 · Jim Wells, Corpus Christi · Routine Maintenance Project - Sealed
$189,550Low bid: FYL ENTERPRISES, LLC+4.3% vs estimate $181,775
$89,210Left on the table47.1% gap to the second bid
3BiddersSpread 53% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FYL ENTERPRISES, LLC | $189,550 | 4.3% | $89,210 | 0 | 3-$549,419 | |
| 2 | CRACKSEAL OF TEXAS, LLC | $278,760 | +47.1% | 53.4% | $11,461 | 0 | 3-$506,413 |
| 3 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $290,221 | +53.1% | 59.7% | 0 | 3-$554,563 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FYL ENTERPRISES, LLC vs CRACKSEAL OF TEXAS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 239.4 LMI | $750.00 | $943.00 | $868.20 | $46,204 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $53,000.00 | $523,850.32 | $43,000 |
| 505-7003 TMA (MOBILE OPERATION) | 54 DAY | $0.0010 | $0.1000 | $229.60 | $5 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $0.0100 | $0.1000 | $11,585.04 | $0 |
Positive: the low bidder was cheaper on that item. These 4 items account for $89,210 of the $89,210 gap.