Sweeping and Debris Removal 07 08.26
6498-31-001 · let Aug 12, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$922,919Low bid: SWEEPING CORPORATION OF AMERICA, LLC+24.6% vs estimate $740,632
$2,330Left on the table0.3% gap to the second bid
2BiddersSpread 0% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SWEEPING CORPORATION OF AMERICA, LLC | $922,919 | 24.6% | $2,330 | 3+$528,265 | 2-$188,292 | |
| 2 | DIGG COMMERCIAL, LLC | $925,249 | +0.3% | 24.9% | 4+$316,504 | 2-$85,308 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
SWEEPING CORPORATION OF AMERICA, LLC vs DIGG COMMERCIAL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 800 DAY | $1.00 | $595.00 | $229.60 | $475,200 |
| 735-7003 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) | 3,755.32 MI | $149.00 | $85.00 | $72.08 | -$240,340 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $20,000.00 | $500.00 | $600.85 | -$234,000 |
| 738-7001 CLEANING / SWEEPING (CENTER MEDIAN) | 374.46 MI | $119.00 | $75.00 | $187.45 | -$16,476 |
| 738-7025 CLEANING / SWEEPING (OUTSIDE MAIN LANE) | 353.04 MI | $119.00 | $75.00 | $197.36 | -$15,534 |
| 505-7001 TMA (STATIONARY) | 25 DAY | $1.00 | $500.00 | $217.57 | $12,475 |
| 738-7103 CLEANING / SWEEPING (AGGREGATE REMOVAL) | 49.15 MI | $100.00 | $250.00 | $191.75 | $7,373 |
| 738-7070 CLEANING / SWEEPING(ENTRANCE/EXIT RAMP) | 77.27 MI | $119.00 | $200.00 | $162.48 | $6,259 |
| 735-7037 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 87.14 MI | $149.00 | $200.00 | $73.08 | $4,444 |
| 738-7105 CLEANING / SWEEPING (HANDWORK) | 7,500 SY | $0.5000 | $1.00 | $0.1919 | $3,750 |
| 738-7049 CLEANING / SWEEPING (FRONTAGE ROAD) | 23.98 MI | $119.00 | $100.00 | $175.99 | -$456 |
| 738-7091 CLEANING / SWEEPING (DIRECT CONNECTOR) | 19.172 MI | $119.00 | $100.00 | $169.58 | -$364 |
Positive: the low bidder was cheaper on that item. These 12 items account for $2,330 of the $2,330 gap.
SWEEPING CORPORATION OF AMERICA, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 735-7003 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) | 3,755.32 MI | $149.00 | $72.08 | 2.07x | $288,859 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $20,000.00 | $600.85 | 33.29x | $232,790 |
| 735-7037 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 87.14 MI | $149.00 | $73.08 | 2.04x | $6,616 |
| 505-7003 TMA (MOBILE OPERATION) | 800 DAY | $1.00 | $229.60 | 0.00x | -$182,878 |
| 505-7001 TMA (STATIONARY) | 25 DAY | $1.00 | $217.57 | 0.00x | -$5,414 |
DIGG COMMERCIAL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 800 DAY | $595.00 | $229.60 | 2.59x | $292,322 |
| 735-7037 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 87.14 MI | $200.00 | $73.08 | 2.74x | $11,060 |
| 505-7001 TMA (STATIONARY) | 25 DAY | $500.00 | $217.57 | 2.30x | $7,061 |
| 738-7105 CLEANING / SWEEPING (HANDWORK) | 7,500 SY | $1.00 | $0.1919 | 5.21x | $6,061 |
| 738-7025 CLEANING / SWEEPING (OUTSIDE MAIN LANE) | 353.04 MI | $75.00 | $197.36 | 0.38x | -$43,200 |
| 738-7001 CLEANING / SWEEPING (CENTER MEDIAN) | 374.46 MI | $75.00 | $187.45 | 0.40x | -$42,108 |