6495-42-001STRIPING/GRAPHICS S. HARRIS
6495-42-001 · let Aug 11, 2026 · Harris, Houston · Routine Maintenance Project - Sealed
$637,744Low bid: TRP INFRASTRUCTURE SERVICES, LLC-15.2% vs estimate $752,114
$95,472Left on the table15.0% gap to the second bid
2BiddersSpread 15% low to high
58Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TRP INFRASTRUCTURE SERVICES, LLC | $637,744 | -15.2% | $95,472 | 1+$23,395 | 3-$34,685 | |
| 2 | STRIPE LINES, INC. | $733,216 | +15.0% | -2.5% | 1+$26,395 | 4-$28,410 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
TRP INFRASTRUCTURE SERVICES, LLC vs STRIPE LINES, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7239 RE PM TY III (W)(8")(SLD) | 86,993.75 LF | $1.00 | $1.45 | $1.06 | $39,147 |
| 677-7008 ELIM EXT PM & MRKS (24") | 13,881.25 LF | $2.90 | $1.60 | $2.87 | -$18,046 |
| 666-7244 RE PM TY III (W)(24")(SLD) | 11,896.25 LF | $8.50 | $10.00 | $7.96 | $17,844 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $150.00 | $229.60 | $14,900 |
| 666-7251 RE PM TY III (Y)(8")(SLD) | 30,607.5 LF | $1.00 | $1.45 | $1.22 | $13,773 |
| 677-7002 ELIM EXT PM & MRKS (6") | 118,117.5 LF | $0.3500 | $0.4500 | $0.2755 | $11,812 |
| 677-7004 ELIM EXT PM & MRKS (8") | 52,246.25 LF | $0.7500 | $0.5500 | $0.6468 | -$10,449 |
| 666-7237 RE PM TY III (W)(6")(BRK) | 31,222.5 LF | $0.7000 | $0.9900 | $0.7099 | $9,055 |
| 666-7262 RE PM TY III (BLK)(6")(SHADOW) | 31,222.5 LF | $0.7500 | $0.9900 | $0.7183 | $7,493 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 24,690 LF | $0.7000 | $0.9900 | $0.7409 | $7,160 |
| 672-7006 REFL PAV MRKR TY II-C-R | 2,546 EA | $4.50 | $7.00 | $4.19 | $6,365 |
| 666-7352 PAVEMENT SLER 24" | 9,688.75 LF | $1.50 | $0.8500 | $1.84 | -$6,298 |
| 666-7254 RE PM TY III (W)(ARROW) | 72 EA | $185.00 | $250.00 | $239.01 | $4,680 |
| 666-7042 REFL PAV MRK TY I (W)(ARROW)(100MIL) | 123 EA | $140.00 | $175.00 | $156.95 | $4,305 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 66 EA | $285.00 | $225.00 | $249.54 | -$3,960 |
| 678-7008 PAV SURF PREP FOR MRK (24") | 13,881.25 LF | $0.5000 | $0.2500 | $0.9416 | -$3,470 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 195 EA | $42.00 | $25.00 | $50.50 | -$3,315 |
| 666-7072 REFL PAV MRK TY I(W)(EXIT GORE)(100MIL) | 8 EA | $900.00 | $500.00 | $964.21 | -$3,200 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $4,500.00 | $5,000.00 | $600.85 | $3,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $500.00 | $2,000.00 | $844.81 | $3,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $93,797 of the $95,472 gap.
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $4,500.00 | $600.85 | 7.49x | $23,395 |
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 118,117.5 LF | $0.0100 | $0.0662 | 0.15x | -$6,638 |
| 678-7004 PAV SURF PREP FOR MRK (8") | 53,915 LF | $0.0200 | $0.1162 | 0.17x | -$5,187 |
STRIPE LINES, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $5,000.00 | $600.85 | 8.32x | $26,395 |
| 678-7008 PAV SURF PREP FOR MRK (24") | 13,881.25 LF | $0.2500 | $0.9416 | 0.27x | -$9,600 |
| 666-7352 PAVEMENT SLER 24" | 9,688.75 LF | $0.8500 | $1.84 | 0.46x | -$9,562 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 195 EA | $25.00 | $50.50 | 0.50x | -$4,972 |
| 678-7002 PAV SURF PREP FOR MRK (6") | 118,117.5 LF | $0.0300 | $0.0662 | 0.45x | -$4,276 |