Striping Denton County FY 26
6488-40-001 · let Aug 12, 2026 · Denton, Dallas · Routine Maintenance Project - Sealed
$384,014Low bid: STRIPE-A-ZONE, LLC+13.9% vs estimate $337,034
$138,164Left on the table36.0% gap to the second bid
2BiddersSpread 36% low to high
29Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPE-A-ZONE, LLC | $384,014 | 13.9% | $138,164 | 0 | 3-$556,805 | |
| 2 | TRP INFRASTRUCTURE SERVICES, LLC | $522,177 | +36.0% | 54.9% | 1+$47,514 | 3-$549,607 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
STRIPE-A-ZONE, LLC vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 677-7002 ELIM EXT PM & MRKS (6") | 211,643 LF | $0.3000 | $0.5000 | $0.2755 | $42,329 |
| 666-7254 RE PM TY III (W)(ARROW) | 305 EA | $200.00 | $300.00 | $239.01 | $30,500 |
| 666-7257 RE PM TY III (W)(WORD) | 121 EA | $230.00 | $325.00 | $274.97 | $11,495 |
| 666-7236 RE PM TY III (W)(6")(SLD) | 91,283 LF | $0.5800 | $0.7000 | $0.6919 | $10,954 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 88,421 LF | $0.5800 | $0.7000 | $0.7409 | $10,611 |
| 677-7004 ELIM EXT PM & MRKS (8") | 25,260 LF | $0.4000 | $0.7500 | $0.6468 | $8,841 |
| 500-7001 MOBILIZATION | 1 LS | $500.00 | $7,500.00 | $523,850.32 | $7,000 |
| 666-7242 RE PM TY III (W)(12")(SLD) | 2,700 LF | $2.00 | $4.50 | $2.62 | $6,750 |
| 666-7239 RE PM TY III (W)(8")(SLD) | 25,260 LF | $0.7500 | $1.00 | $1.06 | $6,315 |
| 666-7244 RE PM TY III (W)(24")(SLD) | 3,511 LF | $7.50 | $9.00 | $7.96 | $5,267 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 182 EA | $70.00 | $50.00 | $50.50 | -$3,640 |
| 666-7237 RE PM TY III (W)(6")(BRK) | 31,938 LF | $0.6000 | $0.7000 | $0.7099 | $3,194 |
| 677-7015 ELIM EXT PM & MRKS (WORD) | 121 EA | $70.00 | $55.00 | $53.95 | -$1,815 |
| 677-7006 ELIM EXT PM & MRKS (12") | 2,700 LF | $1.00 | $1.50 | $1.27 | $1,350 |
| 677-7008 ELIM EXT PM & MRKS (24") | 3,511 LF | $2.25 | $2.50 | $2.87 | $878 |
| 668-7109 PREFAB PM TY C (W)(SYMBOL) | 4 EA | $350.00 | $150.00 | $178.61 | -$800 |
| 672-7006 REFL PAV MRKR TY II-C-R | 418 EA | $6.75 | $5.00 | $4.19 | -$732 |
| 666-7255 RE PM TY III (W)(DBL ARROW) | 4 EA | $280.00 | $395.00 | $337.23 | $460 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 2 DAY | $250.00 | $60.00 | $87.82 | -$380 |
| 666-7066 REFL PAV MRK TY I (W)(WORD)(100MIL) | 4 EA | $235.00 | $165.00 | $184.78 | -$280 |
Positive: the low bidder was cheaper on that item. These 20 items account for $138,296 of the $138,164 gap.
STRIPE-A-ZONE, LLC: unbalanced items
Placed 1TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7002 ELIM EXT PM & MRKS (6") | 211,643 LF | $0.5000 | $0.2755 | 1.81x | $47,514 |
| 500-7001 MOBILIZATION | 1 LS | $7,500.00 | $523,850.32 | 0.01x | -$516,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $100.00 | $11,585.04 | 0.01x | -$22,970 |
| 505-7003 TMA (MOBILE OPERATION) | 45 DAY | $1.00 | $229.60 | 0.00x | -$10,287 |