UA 90, SB AT BUFFALO BAYOU
0027-10-074 · let Aug 6, 2026 · Harris, Houston · Bridge Maintenance
$2,463,336Low bid: GARRET SHIELDS INFRASTRUCTURE+38.2% vs estimate $1,782,087
$144,401Left on the table5.9% gap to the second bid
4BiddersSpread 97% low to high
21Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | GARRET SHIELDS INFRASTRUCTURE | $2,463,336 | 38.2% | $144,401 | 1+$40,910 | 2-$363,361 | |
| 2 | CASTILLO ARANDA LLC | $2,607,737 | +5.9% | 46.3% | $937,127 | 2+$327,458 | 3-$563,501 |
| 3 | EARTH BUILDERS, L.P. | $3,544,864 | +43.9% | 98.9% | $1,300,337 | 4+$1,569,795 | 2-$296,840 |
| 4 | RAGLE CONSTRUCTION, INC. | $4,845,201 | +96.7% | 171.9% | 5+$2,074,350 | 1-$276,939 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
GARRET SHIELDS INFRASTRUCTURE vs CASTILLO ARANDA LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 1.8 STA | $5,000.00 | $144,500.00 | $6,072.92 | $251,100 |
| 4001-7006 INTRLCK ART CONC BKS W/CABLE (8.5" MIN) | 6,838 SF | $60.00 | $30.00 | $60.00 | -$205,140 |
| 496-7023 REMOVE STR (PILING) | 118 LF | $50.00 | $800.00 | $136.53 | $88,500 |
| 400-7010 CEM STABIL BKFL | 600 CY | $200.00 | $95.00 | $138.14 | -$63,000 |
| 407-7010 SHEET PILING (NZ 42) | 8,935 SF | $150.00 | $155.00 | $106.32 | $44,675 |
| 401-7001 FLOWABLE BACKFILL | 530 CY | $160.00 | $220.00 | $298.77 | $31,800 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,396 CY | $30.00 | $20.00 | $12.93 | -$23,960 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 415 CY | $200.00 | $220.00 | $184.74 | $8,300 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $205,000.00 | $523,850.32 | $5,000 |
| 505-7001 TMA (STATIONARY) | 30 DAY | $300.00 | $150.00 | $217.57 | -$4,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 30 DAY | $100.00 | $200.00 | $87.82 | $3,000 |
| 162-7002 BLOCK SODDING | 242 SY | $8.00 | $20.00 | $4.39 | $2,904 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 300 LF | $1.00 | $10.00 | $5.96 | $2,700 |
| 442-7017 MISC NON-BRIDGE (NBIS) | 12.6 LB | $50.00 | $220.00 | $47.98 | $2,142 |
| 506-7024 CONSTRUCTION EXITS (REMOVE) | 200 SY | $1.00 | $5.00 | $8.93 | $800 |
| 168-7001 VEGETATIVE WATERING | 6 TGL | $20.00 | $100.00 | $8.43 | $480 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 400 LF | $5.00 | $4.00 | $3.92 | -$400 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 400 LF | $1.00 | $1.00 | $1.02 | $0 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $5,000.00 | $11,585.04 | $0 |
| 403-7001 TEMPORARY SPL SHORING | 2,166 SF | $40.00 | $40.00 | $25.56 | $0 |
Positive: the low bidder was cheaper on that item. These 20 items account for $144,401 of the $144,401 gap.
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 1CASTILLO ARANDA LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 1.8 STA | $144,500.00 | $6,072.92 | 23.79x | $249,169 |
| 496-7023 REMOVE STR (PILING) | 118 LF | $800.00 | $136.53 | 5.86x | $78,289 |
| 500-7001 MOBILIZATION | 1 LS | $205,000.00 | $523,850.32 | 0.39x | -$318,850 |
| 4001-7006 INTRLCK ART CONC BKS W/CABLE (8.5" MIN) | 6,838 SF | $30.00 | $60.00 | 0.50x | -$205,140 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |
EARTH BUILDERS, L.P.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 407-7010 SHEET PILING (NZ 42) | 8,935 SF | $255.00 | $106.32 | 2.40x | $1,328,450 |
| 403-7001 TEMPORARY SPL SHORING | 2,166 SF | $65.00 | $25.56 | 2.54x | $85,426 |
| 100-7002 PREPARING ROW | 1.8 STA | $50,000.00 | $6,072.92 | 8.23x | $79,069 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,396 CY | $45.00 | $12.93 | 3.48x | $76,850 |
| 4001-7006 INTRLCK ART CONC BKS W/CABLE (8.5" MIN) | 6,838 SF | $25.00 | $60.00 | 0.42x | -$239,330 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,000.00 | $11,585.04 | 0.17x | -$57,510 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 402-7001 TRENCH EXCAVATION PROTECTION | 300 LF | $2,120.00 | $5.96 | 355.76x | $634,212 |
| 100-7002 PREPARING ROW | 1.8 STA | $270,000.00 | $6,072.92 | 44.46x | $475,069 |
| 403-7001 TEMPORARY SPL SHORING | 2,166 SF | $179.00 | $25.56 | 7.00x | $332,350 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,396 CY | $150.00 | $12.93 | 11.60x | $328,430 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $62,300.00 | $11,585.04 | 5.38x | $304,290 |
| 4001-7006 INTRLCK ART CONC BKS W/CABLE (8.5" MIN) | 6,838 SF | $19.50 | $60.00 | 0.33x | -$276,939 |