IH 35W; N of Woodbine Dr to S of CR 530B
0014-03-103 · let Aug 5, 2026 · Johnson, Fort Worth · Bridge Replacement
$2,800,124Low bid: FOUTSCO PAVING COMPANY, LLC-29.9% vs estimate $3,991,946
$132,236Left on the table4.7% gap to the second bid
8BiddersSpread 32% low to high
52Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FOUTSCO PAVING COMPANY, LLC | $2,800,124 | -29.9% | $132,236 | 8+$481,047 | 2-$481,687 | |
| 2 | IBCTX, LLC | $2,932,360 | +4.7% | -26.5% | $163,538 | 5+$178,498 | 1-$22,105 |
| 3 | RAGLE CONSTRUCTION, INC. | $3,095,898 | +10.6% | -22.4% | $193,394 | 5+$498,838 | 2-$75,479 |
| 4 | ED BELL CONSTRUCTION COMPANY | $3,289,291 | +17.5% | -17.6% | $70,763 | 7+$358,501 | 2-$83,132 |
| 5 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $3,360,054 | +20.0% | -15.8% | $92,869 | 7+$223,500 | 2-$44,222 |
| 6 | BEAR CREEK CONTRACTING, LLC | $3,452,923 | +23.3% | -13.5% | $15,603 | ||
| 7 | ICOS MANAGEMENT, LLC | $3,468,526 | +23.9% | -13.1% | $218,687 | ||
| 8 | STX CIVIL | $3,687,213 | +31.7% | -7.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
FOUTSCO PAVING COMPANY, LLC vs IBCTX, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $45,000.00 | $7,000.00 | $11,585.04 | -$304,000 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $293,000.00 | $523,850.32 | $223,000 |
| 508-7001 CONSTRUCTING DETOURS | 5,603 SY | $86.00 | $103.00 | $83.58 | $95,251 |
| 466-7164 WINGWALL (FW - S) (HW=8 FT) | 2 EA | $58,000.00 | $25,000.00 | $37,015.62 | -$66,000 |
| 462-7027 CONC BOX CULV (9 FT X 5 FT) | 854 LF | $791.00 | $858.00 | $1,063.28 | $57,218 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $6,000.00 | $20,000.00 | $9,253.78 | $56,000 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $50,000.00 | $30,000.00 | $28,021.15 | -$40,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 1,266 CY | $135.00 | $165.00 | $190.61 | $37,980 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 9,680 SY | $2.50 | $6.00 | $1.43 | $33,880 |
| 466-7177 WINGWALL (PW - 1) (HW=7 FT) | 1 EA | $60,000.00 | $28,000.00 | $36,993.32 | -$32,000 |
| 466-7178 WINGWALL (PW - 1) (HW=8 FT) | 1 EA | $62,000.00 | $30,000.00 | $42,198.45 | -$32,000 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 9 EA | $2,500.00 | $6,000.00 | $100.44 | $31,500 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 250 CY | $133.00 | $30.00 | $16.96 | -$25,750 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 67 CY | $650.00 | $1,000.00 | $616.83 | $23,450 |
| 505-7001 TMA (STATIONARY) | 128 DAY | $0.1000 | $130.00 | $217.57 | $16,627 |
| 403-7001 TEMPORARY SPL SHORING | 900 SF | $17.00 | $1.00 | $25.56 | -$14,400 |
| 164-7002 BROADCAST SEED (PERM_RURAL_CLAY) | 9,680 SY | $0.1100 | $1.50 | $0.3117 | $13,455 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 2,000 LF | $0.1000 | $6.00 | $3.92 | $11,800 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 148 TON | $300.00 | $230.00 | $156.36 | -$10,360 |
| 105-7069 RMV (10"-14") TRT/UNTRT BASE & ASPH PAV | 1,422 CY | $13.00 | $20.00 | $13.00 | $9,954 |
Positive: the low bidder was cheaper on that item. These 20 items account for $85,605 of the $132,236 gap.
FOUTSCO PAVING COMPANY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $45,000.00 | $11,585.04 | 3.88x | $267,320 |
| 341-7001 D-GR HMA TY-B PG64-22 | 774 TON | $175.00 | $97.82 | 1.79x | $59,734 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $50,000.00 | $28,021.15 | 1.78x | $43,958 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 250 CY | $133.00 | $16.96 | 7.84x | $29,009 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,740 LF | $25.00 | $12.08 | 2.07x | $22,475 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 9 EA | $2,500.00 | $100.44 | 24.89x | $21,596 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 148 TON | $300.00 | $156.36 | 1.92x | $21,259 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,500 LF | $18.00 | $7.54 | 2.39x | $15,698 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $523,850.32 | 0.13x | -$453,850 |
| 505-7001 TMA (STATIONARY) | 128 DAY | $0.1000 | $217.57 | 0.00x | -$27,836 |
IBCTX, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 9 EA | $6,000.00 | $100.44 | 59.74x | $53,096 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 9,680 SY | $6.00 | $1.43 | 4.20x | $44,244 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $20,000.00 | $9,253.78 | 2.16x | $42,985 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,740 LF | $25.00 | $12.08 | 2.07x | $22,475 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,500 LF | $18.00 | $7.54 | 2.39x | $15,698 |
| 403-7001 TEMPORARY SPL SHORING | 900 SF | $1.00 | $25.56 | 0.04x | -$22,105 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 7 STA | $36,000.00 | $6,072.92 | 5.93x | $209,490 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $90,000.00 | $28,021.15 | 3.21x | $123,958 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $26,000.00 | $11,585.04 | 2.24x | $115,320 |
| 110-7001 EXCAV (ROADWAY) | 400 CY | $88.00 | $11.68 | 7.53x | $30,527 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 9 EA | $2,272.00 | $100.44 | 22.62x | $19,544 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,740 LF | $17.90 | $52.29 | 0.34x | -$59,837 |
| 105-7069 RMV (10"-14") TRT/UNTRT BASE & ASPH PAV | 1,422 CY | $2.00 | $13.00 | 0.15x | -$15,642 |
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 7 STA | $21,000.00 | $6,072.92 | 3.46x | $104,490 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $21,000.00 | $11,585.04 | 1.81x | $75,320 |
| 341-7001 D-GR HMA TY-B PG64-22 | 774 TON | $175.00 | $97.82 | 1.79x | $59,734 |
| 466-7178 WINGWALL (PW - 1) (HW=8 FT) | 1 EA | $84,000.00 | $42,198.45 | 1.99x | $41,802 |
| 466-7177 WINGWALL (PW - 1) (HW=7 FT) | 1 EA | $73,500.00 | $36,993.32 | 1.99x | $36,507 |
| 110-7002 EXCAV (CHANNEL) | 1,205 CY | $34.00 | $16.69 | 2.04x | $20,854 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 9 EA | $2,300.00 | $100.44 | 22.90x | $19,796 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,740 LF | $15.00 | $52.29 | 0.29x | -$64,883 |
| 505-7001 TMA (STATIONARY) | 128 DAY | $75.00 | $217.57 | 0.34x | -$18,249 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,740 LF | $101.00 | $52.29 | 1.93x | $84,757 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,500 LF | $36.00 | $7.54 | 4.78x | $42,698 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 250 CY | $107.00 | $16.96 | 6.31x | $22,509 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,740 LF | $24.00 | $12.08 | 1.99x | $20,735 |
| 168-7001 VEGETATIVE WATERING | 339 TGL | $63.00 | $8.43 | 7.47x | $18,498 |
| 110-7002 EXCAV (CHANNEL) | 1,205 CY | $31.00 | $16.69 | 1.86x | $17,239 |
| 105-7069 RMV (10"-14") TRT/UNTRT BASE & ASPH PAV | 1,422 CY | $25.00 | $13.00 | 1.92x | $17,064 |
| 100-7002 PREPARING ROW | 7 STA | $2,399.00 | $6,072.92 | 0.40x | -$25,717 |
| 403-7001 TEMPORARY SPL SHORING | 900 SF | $5.00 | $25.56 | 0.20x | -$18,505 |