US 87 HIR AMA CRK TO SL 335
0041-07-121 · let Aug 6, 2026 · Potter, Amarillo · Restoration
$30,085,056Low bid: J. LEE MILLIGAN, INC.-3.5% vs estimate $31,174,130
$879,739Left on the table2.9% gap to the second bid
3BiddersSpread 12% low to high
269Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | J. LEE MILLIGAN, INC. | $30,085,056 | -3.5% | $879,739 | 2+$2,956,164 | 1-$197,156 | |
| 2 | RK HALL, LLC | $30,964,796 | +2.9% | -0.7% | $2,689,749 | 3+$1,323,359 | 0 |
| 3 | GILVIN-TERRILL, LTD. | $33,654,544 | +11.9% | 8.0% | 5+$4,227,780 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
J. LEE MILLIGAN, INC. vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,305,620.00 | $1,000,000.00 | $523,850.32 | -$2,305,620 |
| 346-7010 STONE-MTRX-ASPH SMA-D SAC-A PG76-28 | 78,909 TON | $174.00 | $197.50 | $170.42 | $1,854,362 |
| 403-7001 TEMPORARY SPL SHORING | 9,828 SF | $5.50 | $78.23 | $25.56 | $714,790 |
| 314-7018 EMULS ASPH (EROSN CONT)(MULTI) | 45,050 GAL | $3.75 | $7.75 | $4.75 | $180,200 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $25,000.00 | $36,936.89 | $11,585.04 | $155,180 |
| 247-7133 FL BS (CMP IN PLC)(TY A OR B GR 4)(12") | 13,252 SY | $31.25 | $41.50 | $33.10 | $135,833 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 15,606 SY | $45.85 | $54.01 | $35.01 | $127,345 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 47,254 SY | $6.10 | $3.41 | $3.11 | -$127,113 |
| 134-7001 BACKFILL (TY A) | 886 STA | $365.00 | $251.39 | $224.26 | -$100,658 |
| 423-7001 RETAINING WALL (MSE) | 6,955 SF | $92.25 | $106.52 | $74.07 | $99,248 |
| 636-7006 REPLACE EXISTING ALUMINUM SIGNS(TY O) | 4,816 SF | $53.45 | $40.32 | $34.38 | -$63,234 |
| 346-7028 TACK COAT | 173,238 GAL | $6.05 | $6.41 | $5.05 | $62,366 |
| 105-7012 RMV (12"-16") TRT/UNTRT BASE & ASPH PAV | 6,980 SY | $10.00 | $18.88 | $8.45 | $61,982 |
| 505-7001 TMA (STATIONARY) | 300 DAY | $320.00 | $524.31 | $217.57 | $61,293 |
| 427-7002 CONCRETE PAINT FINISH | 36,816 SF | $0.5500 | $2.10 | $0.9252 | $57,065 |
| 432-7001 RIPRAP (CONC)(4 IN) | 1,062 CY | $685.00 | $735.00 | $573.24 | $53,100 |
| 647-7001 INSTALL LRSS (STRUCT STEEL) | 24,026 LB | $10.10 | $8.09 | $7.97 | -$48,292 |
| 644-7026 IN SM RD SN SUP&AM TYS80(1)SA(P-BM) | 15 EA | $1,470.00 | $4,237.46 | $1,106.55 | $41,512 |
| 354-7052 PLANE ASPH CONC PAV(3") | 23,894 SY | $5.05 | $3.41 | $2.92 | -$39,186 |
| 358-7003 HIR (SURFACE)(2.5") | 256,294 SY | $8.35 | $8.21 | $8.35 | -$35,881 |
Positive: the low bidder was cheaper on that item. These 20 items account for $884,290 of the $879,739 gap.
J. LEE MILLIGAN, INC.: unbalanced items
Placed 1RK HALL, LLC: unbalanced items
Placed 2GILVIN-TERRILL, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,300,000.00 | $523,850.32 | 6.30x | $2,776,150 |
| 423-7001 RETAINING WALL (MSE) | 6,955 SF | $150.00 | $74.07 | 2.03x | $528,081 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $50,000.00 | $11,585.04 | 4.32x | $499,394 |
| 403-7001 TEMPORARY SPL SHORING | 9,828 SF | $50.00 | $25.56 | 1.96x | $240,190 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 47,254 SY | $7.00 | $3.11 | 2.25x | $183,965 |