FY 26 Crack Seal NAAO
6487-43-001 · let Aug 12, 2026 · Travis, Austin · Routine Maintenance Project - Sealed
$100,511Low bid: FYL ENTERPRISES, LLC+10.1% vs estimate $91,316
$62,464Left on the table62.1% gap to the second bid
3BiddersSpread 182% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FYL ENTERPRISES, LLC | $100,511 | 10.1% | $62,464 | 0 | 1-$5,222 | |
| 2 | D & M CONTRACTORS, LLC | $162,974 | +62.1% | 78.5% | $120,676 | 0 | 1-$2,822 |
| 3 | CRACKSEAL OF TEXAS, LLC | $283,650 | +182.2% | 210.6% | 2+$184,090 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FYL ENTERPRISES, LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 108.66 LMI | $925.00 | $1,477.77 | $868.20 | $60,064 |
| 505-7001 TMA (STATIONARY) | 24 DAY | $0.0010 | $100.00 | $217.57 | $2,400 |
Positive: the low bidder was cheaper on that item. These 2 items account for $62,464 of the $62,464 gap.
FYL ENTERPRISES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 24 DAY | $0.0010 | $217.57 | 0.00x | -$5,222 |
D & M CONTRACTORS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 24 DAY | $100.00 | $217.57 | 0.46x | -$2,822 |