FY 26 Crack Seal BAAO
6487-41-001 · let Aug 12, 2026 · Bastrop, Austin · Routine Maintenance Project - Sealed
$133,050Low bid: FYL ENTERPRISES, LLC+10.5% vs estimate $120,391
$109,557Left on the table82.3% gap to the second bid
3BiddersSpread 84% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FYL ENTERPRISES, LLC | $133,050 | 10.5% | $109,557 | 0 | 1-$3,045 | |
| 2 | CRACKSEAL OF TEXAS, LLC | $242,607 | +82.3% | 101.5% | $2,388 | 3+$120,208 | 0 |
| 3 | D & M CONTRACTORS, LLC | $244,994 | +84.1% | 103.5% | 1+$124,120 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FYL ENTERPRISES, LLC vs CRACKSEAL OF TEXAS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 136.46 LMI | $975.00 | $1,580.00 | $868.20 | $82,558 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 10 DAY | $0.0480 | $2,000.00 | $87.82 | $20,000 |
| 505-7001 TMA (STATIONARY) | 14 DAY | $0.0700 | $500.00 | $217.57 | $6,999 |
Positive: the low bidder was cheaper on that item. These 3 items account for $109,557 of the $109,557 gap.
FYL ENTERPRISES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 14 DAY | $0.0700 | $217.57 | 0.00x | -$3,045 |
CRACKSEAL OF TEXAS, LLC: unbalanced items
Placed 2D & M CONTRACTORS, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 136.46 LMI | $1,777.77 | $868.20 | 2.05x | $124,120 |