Districtwide Upgrade Rail 2027
0922-00-080 · let Aug 5, 2026 · Webb, Laredo · Bridge Maintenance
$2,041,432Low bid: LUCANIA CONTRACTORS LLC-5.8% vs estimate $2,168,274
$86,908Left on the table4.3% gap to the second bid
3BiddersSpread 21% low to high
30Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LUCANIA CONTRACTORS LLC | $2,041,432 | -5.8% | $86,908 | 5+$228,331 | 5-$721,226 | |
| 2 | ICOS MANAGEMENT, LLC | $2,128,340 | +4.3% | -1.8% | $348,205 | 8+$257,320 | 3-$700,661 |
| 3 | STX CIVIL | $2,476,545 | +21.3% | 14.2% | 5+$309,716 | 2-$400,961 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
LUCANIA CONTRACTORS LLC vs ICOS MANAGEMENT, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $206,000.00 | $83,000.00 | $523,850.32 | -$123,000 |
| 505-7001 TMA (STATIONARY) | 387 DAY | $1.00 | $210.00 | $217.57 | $80,883 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 3,870 LF | $20.00 | $36.75 | $9.41 | $64,823 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 2,424 HR | $0.0100 | $21.00 | $46.94 | $50,880 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 9,400 LF | $30.00 | $25.20 | $25.60 | -$45,120 |
| 480-7001 CLEAN EXIST CULVERTS | 21 EA | $6,300.00 | $4,200.00 | $1,712.97 | -$44,100 |
| 134-7002 BACKFILL (TY B) | 147 STA | $500.00 | $210.00 | $206.94 | -$42,630 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 531 CY | $600.00 | $672.00 | $616.83 | $38,232 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 8,825 LF | $6.00 | $2.10 | $2.84 | -$34,418 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 6 EA | $3,000.00 | $8,400.00 | $7,875.52 | $32,400 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 270 LF | $10.00 | $105.00 | $17.41 | $25,650 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $1,200.00 | $1.10 | $11,585.04 | -$20,381 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 6 EA | $1,000.00 | $4,200.00 | $941.31 | $19,200 |
| 451-7020 RETROFIT RAIL (TY T631) | 775 LF | $120.00 | $141.75 | $110.49 | $16,856 |
| 540-7018 MTL W - BEAM GD FEN (LOW FILL CULVERT) | 325 LF | $85.00 | $128.10 | $90.29 | $14,008 |
| 104-7005 REMOV CONC (MOWSTRIP) | 3,775 LF | $7.00 | $10.50 | $9.49 | $13,213 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 16 EA | $1,500.00 | $2,100.00 | $2,218.70 | $9,600 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 52 EA | $350.00 | $525.00 | $263.33 | $9,100 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 560 LF | $275.00 | $262.50 | $228.58 | -$7,000 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 264 EA | $50.00 | $73.50 | $26.51 | $6,204 |
Positive: the low bidder was cheaper on that item. These 20 items account for $64,399 of the $86,908 gap.
LUCANIA CONTRACTORS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 21 EA | $6,300.00 | $1,712.97 | 3.68x | $96,328 |
| 134-7002 BACKFILL (TY B) | 147 STA | $500.00 | $206.94 | 2.42x | $43,080 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 3,870 LF | $20.00 | $9.41 | 2.13x | $40,979 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 8,825 LF | $6.00 | $2.84 | 2.11x | $27,860 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 270 LF | $112.67 | $38.28 | 2.94x | $20,085 |
| 500-7001 MOBILIZATION | 1 LS | $206,000.00 | $523,850.32 | 0.39x | -$317,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $1,200.00 | $11,585.04 | 0.10x | -$176,546 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 2,424 HR | $0.0100 | $46.94 | 0.00x | -$113,764 |
| 505-7001 TMA (STATIONARY) | 387 DAY | $1.00 | $217.57 | 0.00x | -$83,813 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 6 EA | $3,000.00 | $7,875.52 | 0.38x | -$29,253 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 3,870 LF | $36.75 | $9.41 | 3.90x | $105,802 |
| 480-7001 CLEAN EXIST CULVERTS | 21 EA | $4,200.00 | $1,712.97 | 2.45x | $52,228 |
| 512-7088 PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL) | 270 LF | $105.00 | $17.41 | 6.03x | $23,650 |
| 545-7004 CRASH CUSH ATTEN (REMOVE) | 6 EA | $4,200.00 | $941.31 | 4.46x | $19,552 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 270 LF | $105.00 | $38.28 | 2.74x | $18,014 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 52 EA | $525.00 | $263.33 | 1.99x | $13,607 |
| 658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 264 EA | $73.50 | $26.51 | 2.77x | $12,405 |
| 540-7027 MTL BM GD FEN (LONG SPAN SYSTEM) | 16 EA | $1,575.00 | $821.07 | 1.92x | $12,063 |
| 500-7001 MOBILIZATION | 1 LS | $83,000.00 | $523,850.32 | 0.16x | -$440,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $1.10 | $11,585.04 | 0.00x | -$196,927 |
| 510-7001 ONE-WAY TRAF CONT (FLAGGER CONT) | 2,424 HR | $21.00 | $46.94 | 0.45x | -$62,884 |
STX CIVIL: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 3,870 LF | $60.00 | $9.41 | 6.38x | $195,779 |
| 480-7001 CLEAN EXIST CULVERTS | 21 EA | $3,800.00 | $1,712.97 | 2.22x | $43,828 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 270 LF | $150.00 | $38.28 | 3.92x | $30,164 |
| 540-7018 MTL W - BEAM GD FEN (LOW FILL CULVERT) | 325 LF | $165.00 | $90.29 | 1.83x | $24,282 |
| 540-7027 MTL BM GD FEN (LONG SPAN SYSTEM) | 16 EA | $1,800.00 | $821.07 | 2.19x | $15,663 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |
| 505-7001 TMA (STATIONARY) | 387 DAY | $70.00 | $217.57 | 0.32x | -$57,110 |