Bid Tab X-ray: 1685-05-140

Aug 5, 2026 · Harris Sign up free
Set your company to personalize scores

SH 6 - Memorial Dr to Westpark Dr

1685-05-140 · let Aug 5, 2026 · Harris, Houston · Safety Improvement Projects

$1,834,898Low bid: STRUCTURAL INTEGRITY GROUP LLC-16.7% vs estimate $2,203,493
$2,695Left on the table0.1% gap to the second bid
13BiddersSpread 58% low to high
13Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1STRUCTURAL INTEGRITY GROUP LLC $1,834,898-16.7% $2,695 0 1-$375,672
2ALBATROSS CONSTRUCTION LLC $1,837,593+0.1%-16.6% $13,447 0 2-$498,945
3DECO CONTRACTORS, INC. $1,851,040+0.9%-16.0% $3,807 0 2-$422,531
4SICE, INC. $1,854,848+1.1%-15.8% $15,484 0 4-$507,877
5ALLSTATE SIGNAL & CONSTRUCTION, LLC $1,870,331+1.9%-15.1% $82,296 1+$33,891 2-$539,531
6VACA UNDERGROUND UTILITIES INC $1,952,627+6.4%-11.4% $14,630
7THIRD COAST SERVICES LLC $1,967,257+7.2%-10.7% $31,175
8JASCO $1,998,432+8.9%-9.3% $14,320
9HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC $2,012,752+9.7%-8.7% $54,199
10CREACOM, INC. $2,066,951+12.6%-6.2% $90,867
11TRAF-TEX, INC. $2,157,818+17.6%-2.1% $81,157
12FLORIDA TRAFFIC CONTROL DEVICES, INC. $2,238,975+22.0%1.6% $664,290
13ROAD SOLUTIONS L.L.C. $2,903,265+58.2%31.8%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

STRUCTURAL INTEGRITY GROUP LLC vs ALBATROSS CONSTRUCTION LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
618-7055 CONDT (PVC) (SCH 80) (2") (BORE)6,666 LF $23.30$10.61$20.33 -$84,592
618-7054 CONDT (PVC) (SCH 80) (2")32,814 LF $6.15$8.63$12.03 $81,379
500-7001 MOBILIZATION1 LS $148,178.00$76,635.65$523,850.32 -$71,542
610-7198 IN RD IL (TY SA) 50T-10 (400W EQ) LED158 EA $4,470.00$4,747.93$5,165.17 $43,913
416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN)1,580 LF $151.00$175.97$270.84 $39,453
620-7010 ELEC CONDR (NO.6) INSULATED81,906 LF $1.67$1.98$2.58 $25,391
432-7007 RIPRAP (CONC) (CL B) (4 IN)56.5 CY $870.00$532.59$564.22 -$19,064
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $7,056.00$5,118.75$11,585.04 -$15,498
620-7009 ELEC CONDR (NO.6) BARE40,889 LF $1.38$1.62$2.23 $9,813
628-7055 ELC SRV TY A 240/480 060(SS)SS(E)GC(U)3 EA $6,620.00$9,755.20$7,162.06 $9,406
505-7001 TMA (STATIONARY)120 DAY $280.00$222.55$217.57 -$6,894
618-7078 CONDT (RM) (2")449 LF $44.15$30.74$49.01 -$6,021
624-7008 GROUND BOX TY D (162922)W/APRON10 EA $1,266.00$961.19$1,715.49 -$3,048

Positive: the low bidder was cheaper on that item. These 13 items account for $2,695 of the $2,695 gap.

STRUCTURAL INTEGRITY GROUP LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $148,178.00$523,850.320.28x-$375,672

ALBATROSS CONSTRUCTION LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $76,635.65$523,850.320.15x-$447,215
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $5,118.75$11,585.040.44x-$51,730

DECO CONTRACTORS, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $180,000.00$523,850.320.34x-$343,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $1,750.00$11,585.040.15x-$78,680

SICE, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $171,783.00$523,850.320.33x-$352,067
618-7055 CONDT (PVC) (SCH 80) (2") (BORE)6,666 LF $8.66$20.330.43x-$77,774
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $3,282.44$11,585.040.28x-$66,421
618-7078 CONDT (RM) (2")449 LF $23.14$49.010.47x-$11,615

ALLSTATE SIGNAL & CONSTRUCTION, LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)120 DAY $500.00$217.572.30x$33,891
500-7001 MOBILIZATION1 LS $65,000.00$523,850.320.12x-$458,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $1,500.00$11,585.040.13x-$80,680