IH 20; FM 1884 TO SH 171a
0314-07-070 · let Aug 6, 2026 · Parker, Fort Worth · Rehabilitation of Existing Road
$15,697,165Low bid: INDUS ROAD & BRIDGE, INC.-13.5% vs estimate $18,156,437
$261,713Left on the table1.7% gap to the second bid
7BiddersSpread 36% low to high
167Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INDUS ROAD & BRIDGE, INC. | $15,697,165 | -13.5% | $261,713 | 5+$1,996,543 | 1-$79,374 | |
| 2 | PRATER DIRT WORK LLC | $15,958,879 | +1.7% | -12.1% | $41,121 | 1+$976,150 | 0 |
| 3 | REYES TX, INC. | $16,000,000 | +1.9% | -11.9% | $839,039 | 4+$1,315,405 | 1-$699,013 |
| 4 | URBAN INFRACONSTRUCTION LLC | $16,839,039 | +7.3% | -7.3% | $1,315,837 | 3+$996,293 | 0 |
| 5 | ED BELL CONSTRUCTION COMPANY | $18,154,876 | +15.7% | 0.0% | $1,933,691 | 4+$2,216,507 | 2-$368,971 |
| 6 | JAY MILLS CONTRACTING, INCORPORATED | $20,088,567 | +28.0% | 10.6% | $1,211,535 | ||
| 7 | REBCON, LLC | $21,300,102 | +35.7% | 17.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
INDUS ROAD & BRIDGE, INC. vs PRATER DIRT WORK LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 61.2 STA | $17,518.61 | $5,000.00 | $6,072.92 | -$766,139 |
| 403-7001 TEMPORARY SPL SHORING | 30,444 SF | $16.00 | $34.00 | $25.56 | $547,992 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 21 MO | $8,000.00 | $19,000.00 | $11,585.04 | $231,000 |
| 423-7001 RETAINING WALL (MSE) | 49,918 SF | $72.00 | $68.67 | $74.07 | -$166,227 |
| 410-7001 SOIL NAIL ANCHORS | 17,153 LF | $38.00 | $28.35 | $30.07 | -$165,526 |
| 423-7023 RETAINING WALL (SOIL NAIL) (FASCIA) | 10,397 SF | $60.00 | $73.50 | $66.42 | $140,360 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 2,960 LF | $80.00 | $44.00 | $43.56 | -$106,560 |
| 341-7001 D-GR HMA TY-B PG64-22 | 3,428 TON | $119.00 | $150.00 | $97.82 | $106,268 |
| 508-7001 CONSTRUCTING DETOURS | 4,218 SY | $90.00 | $115.00 | $83.58 | $105,450 |
| 110-7001 EXCAV (ROADWAY) | 7,727 CY | $28.00 | $15.00 | $11.68 | -$100,451 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 8 EA | $20,000.00 | $8,000.00 | $9,253.78 | -$96,000 |
| 505-7001 TMA (STATIONARY) | 805 DAY | $280.00 | $165.00 | $217.57 | -$92,575 |
| 132-7012 EMBANK (FNL)(DC)(TY D) | 7,727 CY | $9.00 | $20.00 | $10.77 | $84,997 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 8,293 CY | $7.00 | $15.00 | $12.93 | $66,344 |
| 420-7017 CL C CONC (ABUT)(HPC)(EXTEND) | 34.6 CY | $1,250.00 | $3,100.00 | $3,544.03 | $64,010 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 6,150 LF | $12.00 | $22.00 | $12.08 | $61,500 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 39.5 CY | $1,262.00 | $2,500.00 | $1,492.16 | $48,901 |
| 450-7024 RAIL (TY SSTR) | 5,828 LF | $76.00 | $68.25 | $69.92 | -$45,167 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 653.9 LF | $256.00 | $320.00 | $217.69 | $41,850 |
| 422-7002 REINF CONC SLAB (HPC) | 4,854 SF | $31.00 | $38.75 | $26.91 | $37,594 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$2,380 of the $261,713 gap.
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |
| 100-7002 PREPARING ROW | 61.2 STA | $17,518.61 | $6,072.92 | 2.88x | $700,476 |
| 110-7001 EXCAV (ROADWAY) | 7,727 CY | $28.00 | $11.68 | 2.40x | $126,088 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 2,960 LF | $80.00 | $43.56 | 1.84x | $107,860 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 8 EA | $20,000.00 | $9,253.78 | 2.16x | $85,970 |
| 420-7017 CL C CONC (ABUT)(HPC)(EXTEND) | 34.6 CY | $1,250.00 | $3,544.03 | 0.35x | -$79,374 |
PRATER DIRT WORK LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |
REYES TX, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,456,177.26 | $523,850.32 | 2.78x | $932,327 |
| 422-7002 REINF CONC SLAB (HPC) | 4,854 SF | $64.00 | $26.91 | 2.38x | $180,040 |
| 110-7001 EXCAV (ROADWAY) | 7,727 CY | $25.00 | $11.68 | 2.14x | $102,907 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 8,293 CY | $25.00 | $12.93 | 1.93x | $100,131 |
| 403-7001 TEMPORARY SPL SHORING | 30,444 SF | $2.60 | $25.56 | 0.10x | -$699,013 |
URBAN INFRACONSTRUCTION LLC: unbalanced items
Placed 4ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,635,000.00 | $523,850.32 | 3.12x | $1,111,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 21 MO | $52,500.00 | $11,585.04 | 4.53x | $859,214 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 13,335 SY | $12.00 | $1.95 | 6.16x | $134,059 |
| 422-7002 REINF CONC SLAB (HPC) | 4,854 SF | $50.00 | $26.91 | 1.86x | $112,084 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 6,150 LF | $17.50 | $52.29 | 0.33x | -$213,951 |
| 505-7001 TMA (STATIONARY) | 805 DAY | $25.00 | $217.57 | 0.11x | -$155,020 |