FM2275,FM1845-SH300,WDN
2158-01-020 · let Aug 6, 2026 · Gregg, Tyler · Widen Non-Freeway
$17,959,231Low bid: LONGVIEW BRIDGE AND ROAD, LTD.-7.7% vs estimate $19,466,265
$1,031,157Left on the table5.7% gap to the second bid
5BiddersSpread 32% low to high
185Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONGVIEW BRIDGE AND ROAD, LTD. | $17,959,231 | -7.7% | $1,031,157 | 0 | 2-$370,109 | |
| 2 | EAST TEXAS BRIDGE, INC. | $18,990,388 | +5.7% | -2.4% | $154,030 | 2+$773,816 | 1-$266,806 |
| 3 | HIGHWAY 19 CONSTRUCTION LLC | $19,144,418 | +6.6% | -1.7% | $939,614 | 3+$1,769,376 | 3-$1,157,539 |
| 4 | DRAKE COMPANIES LLC | $20,084,032 | +11.8% | 3.2% | $3,545,343 | 3+$1,457,878 | 2-$706,378 |
| 5 | REYNOLDS & KAY, LTD. | $23,629,375 | +31.6% | 21.4% | 4+$2,443,819 | 1-$585,971 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONGVIEW BRIDGE AND ROAD, LTD. vs EAST TEXAS BRIDGE, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $800,000.00 | $1,175,000.00 | $523,850.32 | $375,000 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 83,630 SY | $28.00 | $24.00 | $21.46 | -$334,520 |
| 465-7171 INLET (COMPL)(CCO)(3FT)(BOTH) | 47 EA | $4,960.00 | $9,000.00 | $5,829.11 | $189,880 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 8,520 LF | $54.00 | $75.00 | $43.56 | $178,920 |
| 531-7002 CONC SIDEWALKS (5") | 8,698 SY | $69.00 | $88.00 | $68.80 | $165,262 |
| 529-7009 CONC CURB & GUTTER (TY II) | 20,252 LF | $21.00 | $28.00 | $32.57 | $141,764 |
| 466-7105 HEADWALL (CH - PW - 0) (DIA= 36 IN) | 2 EA | $23,000.00 | $72,000.00 | $10,666.79 | $98,000 |
| 316-7258 AGGR (TY-PD OR PL, GR-4) | 1,523 CY | $212.00 | $155.00 | $194.90 | -$86,811 |
| 260-7002 LIME (QUICKLIME (DRY)) | 792 TON | $267.00 | $365.00 | $344.36 | $77,616 |
| 403-7001 TEMPORARY SPL SHORING | 7,740 SF | $20.00 | $30.00 | $25.56 | $77,400 |
| 508-7001 CONSTRUCTING DETOURS | 15,901 SY | $63.50 | $68.00 | $83.58 | $71,555 |
| 260-7007 LIME TRT (EXIST MATL)(8") | 44,028 SY | $2.00 | $3.50 | $4.35 | $66,042 |
| 344-7009 SP MIXES SP-C PG64-22 | 17,514 TON | $156.00 | $153.00 | $131.13 | -$52,542 |
| 530-7010 DRIVEWAYS (ACP) | 2,018 SY | $49.00 | $70.00 | $54.96 | $42,378 |
| 465-7003 MANH (COMPL)(PRM)(60IN) | 8 EA | $7,200.00 | $12,000.00 | $9,599.00 | $38,400 |
| 316-7068 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) | 70,342 GAL | $4.50 | $4.00 | $5.18 | -$35,171 |
| 100-7002 PREPARING ROW | 134 STA | $3,500.00 | $3,750.00 | $6,072.92 | $33,500 |
| 432-7031 RIPRAP (STONE COMMON)(DRY)(12 IN) | 1,164 CY | $210.00 | $235.00 | $152.41 | $29,100 |
| 512-7033 PORT CTB (MOVE)(LOW PROF)(TY 1) | 6,900 LF | $4.60 | $8.00 | $8.08 | $23,460 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 234 LF | $700.00 | $800.00 | $765.77 | $23,400 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,122,633 of the $1,031,157 gap.
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 1EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 2HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,950,000.00 | $523,850.32 | 3.72x | $1,426,150 |
| 403-7001 TEMPORARY SPL SHORING | 7,740 SF | $55.00 | $25.56 | 2.15x | $227,861 |
| 512-7045 PORT CTB (STKPL)(LOW PROF)(TY 1) | 8,520 LF | $25.00 | $11.46 | 2.18x | $115,365 |
| 100-7002 PREPARING ROW | 134 STA | $1,500.00 | $6,072.92 | 0.25x | -$612,771 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $1,500.00 | $11,585.04 | 0.13x | -$332,806 |
| 110-7001 EXCAV (ROADWAY) | 29,512 CY | $4.50 | $11.68 | 0.39x | -$211,961 |
DRAKE COMPANIES LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 8,520 LF | $85.00 | $43.56 | 1.95x | $353,062 |
| 466-7105 HEADWALL (CH - PW - 0) (DIA= 36 IN) | 2 EA | $75,000.00 | $10,666.79 | 7.03x | $128,666 |
| 100-7002 PREPARING ROW | 134 STA | $2,300.00 | $6,072.92 | 0.38x | -$505,571 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $5,500.00 | $11,585.04 | 0.47x | -$200,806 |
REYNOLDS & KAY, LTD.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,150,000.00 | $523,850.32 | 4.10x | $1,626,150 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 8,520 LF | $90.00 | $43.56 | 2.07x | $395,662 |
| 403-7001 TEMPORARY SPL SHORING | 7,740 SF | $57.00 | $25.56 | 2.23x | $243,341 |
| 466-7105 HEADWALL (CH - PW - 0) (DIA= 36 IN) | 2 EA | $100,000.00 | $10,666.79 | 9.37x | $178,666 |
| 100-7002 PREPARING ROW | 134 STA | $1,700.00 | $6,072.92 | 0.28x | -$585,971 |