US57 Rehabilitation of Existing Roadway
0276-01-044 · let Aug 6, 2026 · Maverick, Laredo · Rehabilitation of Existing Road
$8,822,697Low bid: ANDERSON COLUMBIA CO., INC.-23.7% vs estimate $11,559,333
$169,199Left on the table1.9% gap to the second bid
3BiddersSpread 43% low to high
88Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ANDERSON COLUMBIA CO., INC. | $8,822,697 | -23.7% | $169,199 | 0 | 2-$557,600 | |
| 2 | HUNTER INDUSTRIES, LTD. | $8,991,896 | +1.9% | -22.2% | $3,613,959 | 0 | 4-$722,700 |
| 3 | CK NEWBERRY, LLC | $12,605,855 | +42.9% | 9.1% | 4+$1,289,382 | 1-$456,980 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
ANDERSON COLUMBIA CO., INC. vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $400,000.00 | $702,391.80 | $523,850.32 | $302,392 |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 10,346 TON | $124.00 | $134.94 | $156.93 | $113,185 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 23 EA | $5,400.00 | $8,400.00 | $7,875.52 | $69,000 |
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) | 30,171 CY | $65.00 | $63.08 | $88.59 | -$57,928 |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV | 65,243 SY | $9.00 | $8.13 | $9.39 | -$56,761 |
| 344-7005 SP MIXES SP-B SAC-B PG70-22 | 15,659 TON | $91.00 | $88.17 | $94.47 | -$44,315 |
| 250-7002 GEOGRID BASE REINFORCEMENT (TYPE 2) | 65,243 SY | $1.80 | $1.17 | $1.65 | -$41,103 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $11,000.00 | $3,613.85 | $9,253.78 | -$36,931 |
| 351-7035 FLEXIBLEPAVEMENTSTRUCTUREREPAIR(10.5") | 2,209 SY | $83.00 | $67.24 | $83.00 | -$34,814 |
| 3007-7001 BONDING COURSE | 24,644 GAL | $2.00 | $3.40 | $3.32 | $34,502 |
| 681-7001 TEMP TRAF SIGNALS | 1 EA | $40,000.00 | $13,600.20 | $62,461.14 | -$26,400 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $3,200.00 | $5,131.85 | $11,585.04 | $23,182 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 6,270 LF | $4.00 | $7.50 | $9.04 | $21,945 |
| 530-7010 DRIVEWAYS (ACP) | 1,347 SY | $54.00 | $41.00 | $54.96 | -$17,511 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 6,810 LF | $14.00 | $11.50 | $13.39 | -$17,025 |
| 480-7001 CLEAN EXIST CULVERTS | 6 EA | $4,000.00 | $1,250.00 | $1,712.97 | -$16,500 |
| 464-7009 RC PIPE (CL III)(36 IN) | 270 LF | $228.00 | $168.00 | $183.45 | -$16,200 |
| 462-7006 CONC BOX CULV (5 FT X 2 FT) | 6 LF | $4,100.00 | $1,720.00 | $479.64 | -$14,280 |
| 467-7100 SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1)(C) | 4 EA | $7,700.00 | $10,300.00 | $10,052.01 | $10,400 |
| 560-7012 RELOCATE EXISTING MAILBOX | 17 EA | $50.00 | $579.67 | $381.49 | $9,004 |
Positive: the low bidder was cheaper on that item. These 20 items account for $203,842 of the $169,199 gap.
ANDERSON COLUMBIA CO., INC.: unbalanced items
Placed 1HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 82 STA | $514.50 | $6,072.92 | 0.08x | -$455,791 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,810 LF | $20.00 | $40.65 | 0.49x | -$140,610 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $5,131.85 | $11,585.04 | 0.44x | -$77,438 |
| 681-7001 TEMP TRAF SIGNALS | 1 EA | $13,600.20 | $62,461.14 | 0.22x | -$48,861 |
CK NEWBERRY, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,250,000.00 | $523,850.32 | 2.39x | $726,150 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 6,810 LF | $75.00 | $40.65 | 1.85x | $233,940 |
| 110-7001 EXCAV (ROADWAY) | 19,546 CY | $21.00 | $11.68 | 1.80x | $182,126 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 6,810 LF | $35.00 | $13.39 | 2.61x | $147,167 |
| 100-7002 PREPARING ROW | 82 STA | $500.00 | $6,072.92 | 0.08x | -$456,980 |