6511-71-001 HMCL Kingsville/Alice
6511-71-001 · let Nov 17, 2026 · Kleberg, Corpus Christi · Material Maintenance Project
$563,000Low bid: BRAUNTEX MATERIALS, INC.+9.3% vs estimate $515,000
$42,000Left on the table7.5% gap to the second bid
5BiddersSpread 26% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BRAUNTEX MATERIALS, INC. | $563,000 | 9.3% | $42,000 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $605,000 | +7.5% | 17.5% | $10,000 | 0 | 0 |
| 3 | CK NEWBERRY, LLC | $615,000 | +9.2% | 19.4% | $73,350 | 0 | 0 |
| 4 | ANDERSON COLUMBIA CO., INC. | $688,350 | +22.3% | 33.7% | $21,940 | 0 | 0 |
| 5 | COLORADO MATERIALS, LTD. | $710,290 | +26.2% | 37.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BRAUNTEX MATERIALS, INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8013-7020 HMCL ACP TYPE D (DEL)(SITE 4) | 3,000 TON | $115.00 | $121.00 | $101.29 | $18,000 |
| 8013-7018 HMCL ACP TYPE D (DEL)(SITE 2) | 1,000 TON | $107.00 | $121.00 | $92.98 | $14,000 |
| 8013-7017 HMCL ACP TYPE D (DEL)(SITE 1) | 500 TON | $107.00 | $121.00 | $93.03 | $7,000 |
| 8013-7019 HMCL ACP TYPE D (DEL)(SITE 3) | 500 TON | $115.00 | $121.00 | $86.52 | $3,000 |
Positive: the low bidder was cheaper on that item. These 4 items account for $42,000 of the $42,000 gap.