FY27 - Brazos HMA - 11
6511-05-001 · let Nov 17, 2026 · Brazos, Bryan · Material Maintenance Project
$378,400Low bid: KNIFE RIVER CORPORATION - SOUTH-20.5% vs estimate $476,000
$56,100Left on the table14.8% gap to the second bid
3BiddersSpread 23% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | KNIFE RIVER CORPORATION - SOUTH | $378,400 | -20.5% | $56,100 | 0 | 0 | |
| 2 | BRAZOS PAVING, INC. | $434,500 | +14.8% | -8.7% | $29,060 | 0 | 0 |
| 3 | AMERICAN MATERIALS, INC. | $463,560 | +22.5% | -2.6% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
KNIFE RIVER CORPORATION - SOUTH vs BRAZOS PAVING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 4,000 TON | $87.00 | $99.85 | $99.54 | $51,400 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 400 TON | $76.00 | $87.75 | $89.12 | $4,700 |
Positive: the low bidder was cheaper on that item. These 2 items account for $56,100 of the $56,100 gap.