Concrete Spall Repair 07 11.26
6509-36-001 · let Nov 12, 2026 · Collin, Dallas · Routine Maintenance Project - Sealed
$615,350Low bid: STRUCTURAL INTEGRITY GROUP LLC-33.5% vs estimate $925,400
$111,650Left on the table18.1% gap to the second bid
6BiddersSpread 59% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRUCTURAL INTEGRITY GROUP LLC | $615,350 | -33.5% | $111,650 | 1+$74,470 | 3-$227,239 | |
| 2 | XIT PAVING AND CONSTRUCTION INC. | $727,000 | +18.1% | -21.4% | $16,150 | 0 | 3-$97,576 |
| 3 | GHB EQUIPMENT COMPANY, L.L.C. | $743,150 | +20.8% | -19.7% | $21,950 | 1+$365,848 | 3-$227,239 |
| 4 | O. TREVINO CONSTRUCTION, LLC | $765,100 | +24.3% | -17.3% | $45,650 | 1+$343,448 | 4-$187,019 |
| 5 | PREMIER CONTRACTORS LLC | $810,750 | +31.8% | -12.4% | $170,000 | 2+$429,318 | 3-$227,239 |
| 6 | DIGG COMMERCIAL, LLC | $980,750 | +59.4% | 6.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STRUCTURAL INTEGRITY GROUP LLC vs XIT PAVING AND CONSTRUCTION INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 600 DAY | $1.00 | $265.00 | $217.57 | $158,400 |
| 721-7002 BULKING AGGREGATE | 20,000 LB | $5.13 | $0.5000 | $1.41 | -$92,600 |
| 721-7001 FIBER REINFORCED POLYMER PATCHING MATLS | 80,000 LB | $6.40 | $6.75 | $4.41 | $28,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 120 EA | $1.00 | $100.00 | $600.85 | $11,880 |
| 500-7033 MOBILIZATION (EMERGENCY) | 30 EA | $1.00 | $200.00 | $844.81 | $5,970 |
Positive: the low bidder was cheaper on that item. These 5 items account for $111,650 of the $111,650 gap.
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 1XIT PAVING AND CONSTRUCTION INC.: unbalanced items
Placed 2GHB EQUIPMENT COMPANY, L.L.C.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 721-7001 FIBER REINFORCED POLYMER PATCHING MATLS | 80,000 LB | $8.98 | $4.41 | 2.04x | $365,848 |
| 505-7001 TMA (STATIONARY) | 600 DAY | $1.00 | $217.57 | 0.00x | -$129,943 |
| 500-7002 MOBILIZATION (CALLOUT) | 120 EA | $1.00 | $600.85 | 0.00x | -$71,982 |
| 500-7033 MOBILIZATION (EMERGENCY) | 30 EA | $1.00 | $844.81 | 0.00x | -$25,314 |
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 721-7001 FIBER REINFORCED POLYMER PATCHING MATLS | 80,000 LB | $8.70 | $4.41 | 1.97x | $343,448 |
| 505-7001 TMA (STATIONARY) | 600 DAY | $85.00 | $217.57 | 0.39x | -$79,543 |
| 500-7002 MOBILIZATION (CALLOUT) | 120 EA | $50.00 | $600.85 | 0.08x | -$66,102 |
| 500-7033 MOBILIZATION (EMERGENCY) | 30 EA | $50.00 | $844.81 | 0.06x | -$23,844 |
| 721-7002 BULKING AGGREGATE | 20,000 LB | $0.5300 | $1.41 | 0.38x | -$17,530 |
PREMIER CONTRACTORS LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 721-7001 FIBER REINFORCED POLYMER PATCHING MATLS | 80,000 LB | $9.50 | $4.41 | 2.16x | $407,448 |
| 721-7002 BULKING AGGREGATE | 20,000 LB | $2.50 | $1.41 | 1.78x | $21,870 |
| 505-7001 TMA (STATIONARY) | 600 DAY | $1.00 | $217.57 | 0.00x | -$129,943 |
| 500-7002 MOBILIZATION (CALLOUT) | 120 EA | $1.00 | $600.85 | 0.00x | -$71,982 |
| 500-7033 MOBILIZATION (EMERGENCY) | 30 EA | $1.00 | $844.81 | 0.00x | -$25,314 |