Hot Mix FY2027
6506-44-001 · let Nov 12, 2026 · Collin, Dallas · Material Maintenance Project
$530,400Low bid: AUSTIN ASPHALT, INC.-6.4% vs estimate $566,650
$17,600Left on the table3.3% gap to the second bid
4BiddersSpread 29% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AUSTIN ASPHALT, INC. | $530,400 | -6.4% | $17,600 | 0 | 0 | |
| 2 | ROADXCHANGE MELISSA LLC | $548,000 | +3.3% | -3.3% | $34,770 | 0 | 0 |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $582,770 | +9.9% | 2.8% | $101,530 | 0 | 0 |
| 4 | TOUCHSTONE RESOURCES, LLC | $684,300 | +29.0% | 20.8% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
AUSTIN ASPHALT, INC. vs ROADXCHANGE MELISSA LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP) | 4,500 TON | $87.00 | $90.00 | $96.97 | $13,500 |
| 8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP) | 900 TON | $96.00 | $99.00 | $104.70 | $2,700 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 500 TON | $86.00 | $88.00 | $89.12 | $1,000 |
| 8011-7127 D-GR HMA TY C PG 70-22 (PICKUP) | 100 TON | $95.00 | $99.00 | $120.25 | $400 |
Positive: the low bidder was cheaper on that item. These 4 items account for $17,600 of the $17,600 gap.