LRA Kinney
6474-49-001 · let Nov 21, 2024 · Kinney, Laredo · Material Maintenance Project - Sealed
$856,000Low bid: VULCAN CONSTRUCTION MATERIALS, LLC-0.5% vs estimate $860,100
$76,800Left on the table9.0% gap to the second bid
2BiddersSpread 9% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $856,000 | -0.5% | $76,800 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $932,800 | +9.0% | 8.5% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7093 LRA (TY II GR CS) (DEL) (ST1) | 7,800 TON | $85.82 | $93.50 | $104.61 | $59,904 |
| 8001-7009 LRA (TY I GR AA) (DEL) (ST1) | 2,200 TON | $84.82 | $92.50 | $112.79 | $16,896 |
Positive: the low bidder was cheaper on that item. These 2 items account for $76,800 of the $76,800 gap.