Bridge Maintenance (2025) - MAO & OAO
0906-00-284 · let Jan 7, 2025 · Ector, Odessa · Bridge Maintenance
$1,886,046Low bid: RELMCO, INC.+15.1% vs estimate $1,638,204
$274,725Left on the table14.6% gap to the second bid
6BiddersSpread 70% low to high
45Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RELMCO, INC. | $1,886,046 | 15.1% | $274,725 | 11+$309,507 | 2-$486,636 | |
| 2 | ICOS MANAGEMENT, LLC | $2,160,771 | +14.6% | 31.9% | $3,783 | 13+$1,045,063 | 4-$772,150 |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $2,164,554 | +14.8% | 32.1% | $602,233 | 14+$507,610 | 2-$456,636 |
| 4 | FNH CONSTRUCTION, LLC | $2,766,788 | +46.7% | 68.9% | $83,234 | 20+$1,039,883 | 1-$323,850 |
| 5 | DAN WILLIAMS COMPANY | $2,850,022 | +51.1% | 74.0% | $364,952 | 9+$707,088 | 0 |
| 6 | TI-ZACK CONCRETE, LLC | $3,214,974 | +70.5% | 96.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RELMCO, INC. vs ICOS MANAGEMENT, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 778-7002 CONCRETE RAIL REPAIR (MISC) | 1,741 LF | $175.00 | $495.00 | $113.22 | $557,120 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 21 MO | $5,500.00 | $1.00 | $11,585.04 | -$115,479 |
| 427-7007 BLAST FINISH | 13,105 SF | $4.00 | $12.00 | $0.5560 | $104,840 |
| 505-7001 TMA (STATIONARY) | 381 DAY | $250.00 | $1.00 | $217.57 | -$94,869 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 628 DAY | $100.00 | $1.00 | $87.82 | -$62,172 |
| 6069-7001 TEMP Q-DETECT (TY2) (1 SYS) | 134 DAY | $300.00 | $1.00 | $68.16 | -$40,066 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 1 EA | $35,000.00 | $1.00 | $9,253.78 | -$34,999 |
| 341-7022 D-GR HMA TY-C PG70-22 | 28.3 TON | $1,500.00 | $275.00 | $114.77 | -$34,668 |
| 500-7001 MOBILIZATION | 1 LS | $165,000.00 | $132,000.00 | $523,850.32 | -$33,000 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 1 EA | $15,000.00 | $38,500.00 | $7,875.52 | $23,500 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 900 LF | $40.00 | $66.00 | $52.29 | $23,400 |
| 666-7347 PAVEMENT SLER 6" | 10,792 LF | $0.8800 | $3.00 | $0.1841 | $22,879 |
| 454-7009 HEADER TYPE EXPANSION JOINT | 52 CF | $750.00 | $330.00 | $434.15 | -$21,840 |
| 677-7002 ELIM EXT PM & MRKS (6") | 10,792 LF | $1.10 | $3.00 | $0.2755 | $20,505 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 450 LF | $80.00 | $44.00 | $7.54 | -$16,200 |
| 432-7001 RIPRAP (CONC)(4 IN) | 60 CY | $900.00 | $660.00 | $573.24 | -$14,400 |
| 467-7004 SET (REPLACE PIPE RUNNER) | 5 EA | $4,500.00 | $1,650.00 | $1,561.57 | -$14,250 |
| 422-7013 APPROACH SLAB | 31 CY | $1,500.00 | $1,100.00 | $738.51 | -$12,400 |
| 104-7030 REMOV CONC (APPR SLAB) | 85 SY | $350.00 | $220.00 | $64.93 | -$11,050 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 1 EA | $1,500.00 | $11,000.00 | $1,471.00 | $9,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $256,351 of the $274,725 gap.
RELMCO, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 293 SF | $250.00 | $95.74 | 2.61x | $45,197 |
| 427-7007 BLAST FINISH | 13,105 SF | $4.00 | $0.5560 | 7.19x | $45,134 |
| 341-7022 D-GR HMA TY-C PG70-22 | 28.3 TON | $1,500.00 | $114.77 | 13.07x | $39,202 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 450 LF | $80.00 | $7.54 | 10.62x | $32,609 |
| 6069-7001 TEMP Q-DETECT (TY2) (1 SYS) | 134 DAY | $300.00 | $68.16 | 4.40x | $31,066 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 1 EA | $35,000.00 | $9,253.78 | 3.78x | $25,746 |
| 104-7030 REMOV CONC (APPR SLAB) | 85 SY | $350.00 | $64.93 | 5.39x | $24,231 |
| 422-7013 APPROACH SLAB | 31 CY | $1,500.00 | $738.51 | 2.03x | $23,606 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 25 EA | $1,200.00 | $475.41 | 2.52x | $18,115 |
| 467-7004 SET (REPLACE PIPE RUNNER) | 5 EA | $4,500.00 | $1,561.57 | 2.88x | $14,692 |
| 500-7001 MOBILIZATION | 1 LS | $165,000.00 | $523,850.32 | 0.31x | -$358,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 21 MO | $5,500.00 | $11,585.04 | 0.47x | -$127,786 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 778-7002 CONCRETE RAIL REPAIR (MISC) | 1,741 LF | $495.00 | $113.22 | 4.37x | $664,675 |
| 427-7007 BLAST FINISH | 13,105 SF | $12.00 | $0.5560 | 21.58x | $149,974 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 293 SF | $220.00 | $95.74 | 2.30x | $36,407 |
| 545-7018 CCA (INSTL)(N)(TL3)(WORK ZONE) | 1 EA | $38,500.00 | $7,875.52 | 4.89x | $30,624 |
| 666-7347 PAVEMENT SLER 6" | 10,792 LF | $3.00 | $0.1841 | 16.30x | $30,389 |
| 677-7002 ELIM EXT PM & MRKS (6") | 10,792 LF | $3.00 | $0.2755 | 10.89x | $29,403 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 450 LF | $44.00 | $7.54 | 5.84x | $16,409 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 7,299 LF | $3.00 | $0.8015 | 3.74x | $16,047 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 25 EA | $1,100.00 | $475.41 | 2.31x | $15,615 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 6,975 LF | $3.00 | $0.8371 | 3.58x | $15,086 |
| 500-7001 MOBILIZATION | 1 LS | $132,000.00 | $523,850.32 | 0.25x | -$391,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 21 MO | $1.00 | $11,585.04 | 0.00x | -$243,265 |
| 505-7001 TMA (STATIONARY) | 381 DAY | $1.00 | $217.57 | 0.00x | -$82,514 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 628 DAY | $1.00 | $87.82 | 0.01x | -$54,521 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 427-7007 BLAST FINISH | 13,105 SF | $6.00 | $0.5560 | 10.79x | $71,344 |
| 341-7022 D-GR HMA TY-C PG70-22 | 28.3 TON | $2,600.00 | $114.77 | 22.65x | $70,332 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 25 EA | $2,600.00 | $475.41 | 5.47x | $53,115 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 293 SF | $275.00 | $95.74 | 2.87x | $52,522 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 900 LF | $107.00 | $52.29 | 2.05x | $49,240 |
| 432-7001 RIPRAP (CONC)(4 IN) | 60 CY | $1,280.00 | $573.24 | 2.23x | $42,406 |
| 454-7009 HEADER TYPE EXPANSION JOINT | 52 CF | $1,100.00 | $434.15 | 2.53x | $34,624 |
| 401-7001 FLOWABLE BACKFILL | 60.333 CY | $811.00 | $298.77 | 2.71x | $30,905 |
| 422-7013 APPROACH SLAB | 31 CY | $1,445.00 | $738.51 | 1.96x | $21,901 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 160 LF | $210.00 | $76.83 | 2.73x | $21,307 |
| 500-7001 MOBILIZATION | 1 LS | $216,000.00 | $523,850.32 | 0.41x | -$307,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 21 MO | $4,500.00 | $11,585.04 | 0.39x | -$148,786 |
FNH CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 427-7007 BLAST FINISH | 13,105 SF | $15.00 | $0.5560 | 26.98x | $189,289 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 293 SF | $650.00 | $95.74 | 6.79x | $162,397 |
| 778-7002 CONCRETE RAIL REPAIR (MISC) | 1,741 LF | $200.00 | $113.22 | 1.77x | $151,080 |
| 467-7004 SET (REPLACE PIPE RUNNER) | 5 EA | $14,500.00 | $1,561.57 | 9.29x | $64,692 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 900 LF | $120.00 | $52.29 | 2.29x | $60,940 |
| 422-7013 APPROACH SLAB | 31 CY | $2,500.00 | $738.51 | 3.39x | $54,606 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 25 EA | $2,500.00 | $475.41 | 5.26x | $50,615 |
| 104-7030 REMOV CONC (APPR SLAB) | 85 SY | $500.00 | $64.93 | 7.70x | $36,981 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 160 LF | $300.00 | $76.83 | 3.90x | $35,707 |
| 666-7347 PAVEMENT SLER 6" | 10,792 LF | $3.00 | $0.1841 | 16.30x | $30,389 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
DAN WILLIAMS COMPANY: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 778-7002 CONCRETE RAIL REPAIR (MISC) | 1,741 LF | $315.00 | $113.22 | 2.78x | $351,295 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 293 SF | $425.00 | $95.74 | 4.44x | $96,472 |
| 341-7022 D-GR HMA TY-C PG70-22 | 28.3 TON | $3,000.00 | $114.77 | 26.14x | $81,652 |
| 454-7009 HEADER TYPE EXPANSION JOINT | 52 CF | $1,300.00 | $434.15 | 2.99x | $45,024 |
| 432-7001 RIPRAP (CONC)(4 IN) | 60 CY | $1,200.00 | $573.24 | 2.09x | $37,606 |
| 6069-7001 TEMP Q-DETECT (TY2) (1 SYS) | 134 DAY | $300.00 | $68.16 | 4.40x | $31,066 |
| 422-7013 APPROACH SLAB | 31 CY | $1,500.00 | $738.51 | 2.03x | $23,606 |
| 467-7004 SET (REPLACE PIPE RUNNER) | 5 EA | $6,000.00 | $1,561.57 | 3.84x | $22,192 |
| 401-7001 FLOWABLE BACKFILL | 60.333 CY | $600.00 | $298.77 | 2.01x | $18,174 |