LRA Maverick
6480-42-001 · let Mar 20, 2025 · Maverick, Laredo · Material Maintenance Project - Sealed
$838,150Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+6.6% vs estimate $786,000
$27,500Left on the table3.3% gap to the second bid
2BiddersSpread 3% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $838,150 | 6.6% | $27,500 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $865,650 | +3.3% | 10.1% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7107 LRA (TY II GR DS) (DEL) (ST1) | 7,000 TON | $93.35 | $96.85 | $125.06 | $24,500 |
| 8001-7009 LRA (TY I GR AA) (DEL) (ST1) | 2,000 TON | $92.35 | $93.85 | $112.79 | $3,000 |
Positive: the low bidder was cheaper on that item. These 2 items account for $27,500 of the $27,500 gap.