Bid Tab X-ray: 6480-26-001

Mar 27, 2025 · Howard Sign up free
Set your company to personalize scores

2025 Howard County MOWING

6480-26-001 · let Mar 27, 2025 · Howard, Abilene · Routine Maintenance Project - Sealed

$467,354Low bid: ABESCAPE GROUP LLC-13.6% vs estimate $541,026
$63,478Left on the table13.6% gap to the second bid
2BiddersSpread 14% low to high
5Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1ABESCAPE GROUP LLC $467,354-13.6% $63,478 1+$10,622 2-$562,223
2GREG SCRUGGS $530,832+13.6%-1.9% 0 1-$523,850

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

ABESCAPE GROUP LLC vs GREG SCRUGGS, biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7020 STRIP MOWING1,233 AC $1.00$41.50$32.12 $49,937
734-7001 LITTER REMOVAL6,810 AC $20.00$22.00$15.14 $13,620
505-7003 TMA (MOBILE OPERATION)6 DAY $2,000.00$0.0010$229.60 -$12,000
730-7022 FULL - WIDTH MOWING7,948 AC $40.00$41.50$38.53 $11,922
500-7001 MOBILIZATION1 LS $1.00$0.0010$523,850.32 -$1

Positive: the low bidder was cheaper on that item. These 5 items account for $63,478 of the $63,478 gap.

ABESCAPE GROUP LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)6 DAY $2,000.00$229.608.71x$10,622
500-7001 MOBILIZATION1 LS $1.00$523,850.320.00x-$523,849
730-7020 STRIP MOWING1,233 AC $1.00$32.120.03x-$38,374

GREG SCRUGGS: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $0.0010$523,850.320.00x-$523,850