SAT_SH0016_1of2: 0613-01-070: SFT
0613-01-070 · let Apr 4, 2025 · Bexar, San Antonio · Safety Improvement Projects
$8,862,445Low bid: CK NEWBERRY, LLC-15.3% vs estimate $10,457,586
$278,831Left on the table3.1% gap to the second bid
6BiddersSpread 15% low to high
289Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CK NEWBERRY, LLC | $8,862,445 | -15.3% | $278,831 | 1+$112,408 | 0 | |
| 2 | DAN WILLIAMS COMPANY | $9,141,276 | +3.1% | -12.6% | $415,835 | 4+$1,074,289 | 1-$97,383 |
| 3 | HUNTER INDUSTRIES, LTD. | $9,557,110 | +7.8% | -8.6% | $58,246 | 5+$1,453,536 | 1-$111,085 |
| 4 | JORDAN FOSTER CONSTRUCTION, LLC | $9,615,356 | +8.5% | -8.1% | $275,615 | 7+$1,254,764 | 1-$103,383 |
| 5 | J. CARROLL WEAVER, INC. | $9,890,971 | +11.6% | -5.4% | $332,820 | 4+$1,080,583 | 1-$61,555 |
| 6 | STERLING DELAWARE HOLDING COMPANY | $10,223,792 | +15.4% | -2.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CK NEWBERRY, LLC vs DAN WILLIAMS COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 316-7224 AGGR (TY-PD, GR-4)(SAC-B) | 4,344 CY | $85.00 | $170.00 | $86.92 | $369,240 |
| 432-7004 RIPRAP (CONC)(CL A) | 331 CY | $700.00 | $335.00 | $469.09 | -$120,815 |
| 677-7001 ELIM EXT PM & MRKS (4") | 19,598 LF | $6.00 | $0.5000 | $0.2643 | -$107,789 |
| 247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS) | 14,129 CY | $68.00 | $75.00 | $41.72 | $98,903 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,579 CY | $18.00 | $23.25 | $18.71 | $92,290 |
| 505-7001 TMA (STATIONARY) | 524 DAY | $350.00 | $175.00 | $217.57 | -$91,700 |
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 180,690 GAL | $4.00 | $4.50 | $3.44 | $90,345 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $60,000.00 | $30,000.00 | $62,461.14 | -$90,000 |
| 536-7002 CONC MEDIAN | 7,818 SY | $65.00 | $54.00 | $92.13 | -$85,998 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $2,300.00 | $45,000.00 | $8,031.16 | $85,400 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 11,272 LF | $20.00 | $13.50 | $12.40 | -$73,268 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 95,935 SY | $1.50 | $2.20 | $1.95 | $67,155 |
| 500-7001 MOBILIZATION | 1 LS | $850,000.00 | $910,000.00 | $523,850.32 | $60,000 |
| 168-7001 VEGETATIVE WATERING | 1,487 TGL | $30.00 | $7.00 | $8.43 | -$34,201 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $15,000.00 | $17,000.00 | $11,585.04 | $34,000 |
| 310-7013 PRIME COAT(MC-30 OR AE-P) | 9,534 GAL | $7.00 | $4.00 | $4.73 | -$28,602 |
| 686-7020 INS TRF SIG PL AM (S)STR(TY D)LUM | 2 EA | $13,100.00 | $25,000.00 | $11,209.92 | $23,800 |
| 341-7001 D-GR HMA TY-B PG64-22 | 7,906 TON | $105.00 | $102.00 | $97.82 | -$23,718 |
| 496-7004 REMOV STR (SET) | 28 EA | $1,500.00 | $750.00 | $514.07 | -$21,000 |
| 480-7001 CLEAN EXIST CULVERTS | 8 EA | $5,000.00 | $2,500.00 | $1,712.97 | -$20,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $224,041 of the $278,831 gap.
CK NEWBERRY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7001 ELIM EXT PM & MRKS (4") | 19,598 LF | $6.00 | $0.2643 | 22.70x | $112,408 |
DAN WILLIAMS COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS) | 14,129 CY | $75.00 | $41.72 | 1.80x | $470,223 |
| 316-7224 AGGR (TY-PD, GR-4)(SAC-B) | 4,344 CY | $170.00 | $86.92 | 1.96x | $360,908 |
| 110-7001 EXCAV (ROADWAY) | 18,161 CY | $21.00 | $11.68 | 1.80x | $169,221 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $45,000.00 | $8,031.16 | 5.60x | $73,938 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $30,000.00 | $62,461.14 | 0.48x | -$97,383 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,579 CY | $49.90 | $18.71 | 2.67x | $548,236 |
| 247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS) | 14,129 CY | $74.53 | $41.72 | 1.79x | $463,582 |
| 110-7001 EXCAV (ROADWAY) | 18,161 CY | $26.90 | $11.68 | 2.30x | $276,370 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 11,272 LF | $22.27 | $12.40 | 1.80x | $111,214 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $35,097.32 | $8,031.16 | 4.37x | $54,132 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $25,432.84 | $62,461.14 | 0.41x | -$111,085 |
JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $961,535.62 | $523,850.32 | 1.84x | $437,685 |
| 316-7224 AGGR (TY-PD, GR-4)(SAC-B) | 4,344 CY | $173.00 | $86.92 | 1.99x | $373,940 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 95,935 SY | $3.50 | $1.95 | 1.80x | $149,006 |
| 505-7001 TMA (STATIONARY) | 524 DAY | $470.00 | $217.57 | 2.16x | $132,272 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $38,000.00 | $8,031.16 | 4.73x | $59,938 |
| 400-7010 CEM STABIL BKFL | 496 CY | $243.00 | $138.14 | 1.76x | $52,009 |
| 168-7001 VEGETATIVE WATERING | 1,487 TGL | $42.00 | $8.43 | 4.98x | $49,913 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $28,000.00 | $62,461.14 | 0.45x | -$103,383 |
J. CARROLL WEAVER, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7192 FL BS(CIP)(TY D, GR 1-2 OR 5)(FNAL POS) | 14,129 CY | $83.70 | $41.72 | 2.01x | $593,145 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 17,579 CY | $35.17 | $18.71 | 1.88x | $289,298 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 11,272 LF | $24.75 | $12.40 | 2.00x | $139,169 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 12 EA | $6,091.04 | $1,176.76 | 5.18x | $58,971 |
| 104-7003 REMOV CONC (MOWSTRIP) | 3,506 SY | $2.92 | $20.48 | 0.14x | -$61,555 |