FM 1235 TAYLOR CO CR 306 TO CR 300
0663-03-031 · let Apr 3, 2025 · Taylor, Abilene · Widen Non-Freeway
$3,167,591Low bid: J. H. STRAIN & SONS, INC.-12.6% vs estimate $3,625,750
$191,832Left on the table6.1% gap to the second bid
6BiddersSpread 38% low to high
72Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | J. H. STRAIN & SONS, INC. | $3,167,591 | -12.6% | $191,832 | 9+$410,905 | 1-$273,850 | |
| 2 | STX CIVIL | $3,359,423 | +6.1% | -7.3% | $30,706 | 15+$688,345 | 1-$72,435 |
| 3 | A. L. HELMCAMP, INC. | $3,390,128 | +7.0% | -6.5% | $195,105 | 10+$382,008 | 0 |
| 4 | BONTKE BROTHERS CONSTRUCTION COMPANY | $3,585,233 | +13.2% | -1.1% | $213,843 | 17+$1,014,564 | 2-$263,601 |
| 5 | CK NEWBERRY, LLC | $3,799,077 | +19.9% | 4.8% | $572,377 | 15+$618,466 | 0 |
| 6 | GREY SKY CONSTRUCTION LLC | $4,371,453 | +38.0% | 20.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
J. H. STRAIN & SONS, INC. vs STX CIVIL, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 467-7183 SET (TY I)(S= 8 FT)(HW= 5 FT)(3:1)(C) | 12 EA | $12,400.00 | $25,000.00 | $10,657.22 | $151,200 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $15,000.00 | $5,000.00 | $11,585.04 | -$110,000 |
| 403-7001 TEMPORARY SPL SHORING | 2,983 SF | $65.00 | $30.00 | $25.56 | -$104,405 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $300,000.00 | $523,850.32 | $50,000 |
| 344-7041 SP MIXES SP-D PG64-22 | 3,180 TON | $145.00 | $160.00 | $134.97 | $47,700 |
| 316-7007 ASPH (AC-20-5TR) | 22,551 GAL | $8.00 | $6.00 | $3.27 | -$45,102 |
| 110-7001 EXCAV (ROADWAY) | 2,895 CY | $15.00 | $30.00 | $11.68 | $43,425 |
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) | 3,503 CY | $62.00 | $50.00 | $88.59 | -$42,036 |
| 480-7001 CLEAN EXIST CULVERTS | 7 EA | $2,000.00 | $7,000.00 | $1,712.97 | $35,000 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 1,685 CY | $22.50 | $40.00 | $12.93 | $29,488 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 35,172 LF | $0.7200 | $1.50 | $0.6515 | $27,434 |
| 164-7007 BROADCAST SEED (TEMP_WARM_COOL) | 13,220 SY | $0.3300 | $2.00 | $0.2110 | $22,077 |
| 164-7010 DRILL SEED (PERM_RURAL_CLAY) | 13,220 SY | $0.3700 | $2.00 | $0.2111 | $21,549 |
| 466-7180 WINGWALL (PW - 1) (HW=10 FT) | 4 EA | $75,000.00 | $70,000.00 | $58,928.62 | -$20,000 |
| 316-7086 ASPH (AC-20-5TR OR CRS-2P) | 8,155 GAL | $8.00 | $6.00 | $4.40 | -$16,310 |
| 105-7055 RMV (4"-10") TRT/UNTRT BASE & ASPH PAV | 4,374 SY | $12.00 | $15.00 | $5.22 | $13,122 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 451 CY | $225.00 | $250.00 | $133.09 | $11,275 |
| 530-7015 DRIVEWAYS (BASE) | 337 SY | $35.00 | $65.00 | $27.85 | $10,110 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,315 SY | $52.50 | $45.00 | $35.01 | -$9,863 |
| 677-7002 ELIM EXT PM & MRKS (6") | 15,173 LF | $0.3500 | $1.00 | $0.2755 | $9,862 |
Positive: the low bidder was cheaper on that item. These 20 items account for $124,527 of the $191,832 gap.
J. H. STRAIN & SONS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 2,983 SF | $65.00 | $25.56 | 2.54x | $117,648 |
| 316-7007 ASPH (AC-20-5TR) | 22,551 GAL | $8.00 | $3.27 | 2.45x | $106,696 |
| 168-7001 VEGETATIVE WATERING | 1,281 TGL | $45.00 | $8.43 | 5.34x | $46,841 |
| 105-7055 RMV (4"-10") TRT/UNTRT BASE & ASPH PAV | 4,374 SY | $12.00 | $5.22 | 2.30x | $29,658 |
| 316-7086 ASPH (AC-20-5TR OR CRS-2P) | 8,155 GAL | $8.00 | $4.40 | 1.82x | $29,329 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 6,618 LF | $6.75 | $2.80 | 2.41x | $26,155 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 169 CY | $225.00 | $110.18 | 2.04x | $19,405 |
| 462-7030 CONC BOX CULV (9 FT X 8 FT) | 21 LF | $1,755.00 | $917.03 | 1.91x | $17,597 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,410 LF | $20.00 | $7.54 | 2.65x | $17,576 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
STX CIVIL: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 467-7183 SET (TY I)(S= 8 FT)(HW= 5 FT)(3:1)(C) | 12 EA | $25,000.00 | $10,657.22 | 2.35x | $172,113 |
| 316-7007 ASPH (AC-20-5TR) | 22,551 GAL | $6.00 | $3.27 | 1.84x | $61,594 |
| 168-7001 VEGETATIVE WATERING | 1,281 TGL | $50.00 | $8.43 | 5.93x | $53,246 |
| 110-7001 EXCAV (ROADWAY) | 2,895 CY | $30.00 | $11.68 | 2.57x | $53,030 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 451 CY | $250.00 | $133.09 | 1.88x | $52,726 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 1,685 CY | $40.00 | $12.93 | 3.09x | $45,620 |
| 105-7055 RMV (4"-10") TRT/UNTRT BASE & ASPH PAV | 4,374 SY | $15.00 | $5.22 | 2.87x | $42,780 |
| 480-7001 CLEAN EXIST CULVERTS | 7 EA | $7,000.00 | $1,712.97 | 4.09x | $37,009 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 35,172 LF | $1.50 | $0.6515 | 2.30x | $29,843 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 169 CY | $265.00 | $110.18 | 2.41x | $26,165 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $5,000.00 | $11,585.04 | 0.43x | -$72,435 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 451 CY | $300.00 | $133.09 | 2.25x | $75,276 |
| 403-7001 TEMPORARY SPL SHORING | 2,983 SF | $50.00 | $25.56 | 1.96x | $72,903 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,315 SY | $74.00 | $35.01 | 2.11x | $51,265 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 169 CY | $300.00 | $110.18 | 2.72x | $32,080 |
| 110-7001 EXCAV (ROADWAY) | 2,895 CY | $22.00 | $11.68 | 1.88x | $29,870 |
| 168-7001 VEGETATIVE WATERING | 1,281 TGL | $30.00 | $8.43 | 3.56x | $27,626 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,410 LF | $25.00 | $7.54 | 3.32x | $24,626 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 6,618 LF | $6.50 | $2.80 | 2.32x | $24,500 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 1,685 CY | $26.00 | $12.93 | 2.01x | $22,030 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 8 EA | $4,200.00 | $1,471.00 | 2.86x | $21,832 |
BONTKE BROTHERS CONSTRUCTION COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 168-7001 VEGETATIVE WATERING | 1,281 TGL | $150.00 | $8.43 | 17.79x | $181,346 |
| 450-7020 RAIL (TY T631) | 400 LF | $500.00 | $108.10 | 4.63x | $156,759 |
| 316-7007 ASPH (AC-20-5TR) | 22,551 GAL | $10.00 | $3.27 | 3.06x | $151,798 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,410 LF | $75.00 | $7.54 | 9.95x | $95,126 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 451 CY | $300.00 | $133.09 | 2.25x | $75,276 |
| 105-7055 RMV (4"-10") TRT/UNTRT BASE & ASPH PAV | 4,374 SY | $18.00 | $5.22 | 3.45x | $55,902 |
| 316-7086 ASPH (AC-20-5TR OR CRS-2P) | 8,155 GAL | $10.00 | $4.40 | 2.27x | $45,639 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 690 LF | $65.00 | $15.26 | 4.26x | $34,320 |
| 316-7208 AGGR (TY-PB, GR-3)(SAC-B) | 169 CY | $300.00 | $110.18 | 2.72x | $32,080 |
| 110-7001 EXCAV (ROADWAY) | 2,895 CY | $22.00 | $11.68 | 1.88x | $29,870 |
| 466-7180 WINGWALL (PW - 1) (HW=10 FT) | 4 EA | $10,000.00 | $58,928.62 | 0.17x | -$195,714 |
| 467-7183 SET (TY I)(S= 8 FT)(HW= 5 FT)(3:1)(C) | 12 EA | $5,000.00 | $10,657.22 | 0.47x | -$67,887 |
CK NEWBERRY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $25,000.00 | $11,585.04 | 2.16x | $147,565 |
| 105-7055 RMV (4"-10") TRT/UNTRT BASE & ASPH PAV | 4,374 SY | $20.00 | $5.22 | 3.83x | $64,650 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 1,410 LF | $50.00 | $7.54 | 6.64x | $59,876 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,315 SY | $75.00 | $35.01 | 2.14x | $52,580 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 35,172 LF | $1.75 | $0.6515 | 2.69x | $38,636 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 690 LF | $70.00 | $15.26 | 4.59x | $37,770 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 42 LF | $1,500.00 | $765.77 | 1.96x | $30,838 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 6,618 LF | $7.00 | $2.80 | 2.50x | $27,809 |
| 462-7030 CONC BOX CULV (9 FT X 8 FT) | 21 LF | $2,200.00 | $917.03 | 2.40x | $26,942 |
| 512-7037 PORT CTB (STKPL)(SGL SLP)(TY 1) | 690 LF | $50.00 | $12.38 | 4.04x | $25,959 |