086401069 FM 494 HIDALGO (WIDEN 2 TO 4)
0864-01-069 · let Apr 3, 2025 · Hidalgo, Pharr · Widen Non-Freeway
$15,739,166Low bid: REIM CONSTRUCTION, INC.-6.4% vs estimate $16,823,453
$398,990Left on the table2.5% gap to the second bid
3BiddersSpread 25% low to high
173Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | REIM CONSTRUCTION, INC. | $15,739,166 | -6.4% | $398,990 | 1+$776,150 | 8-$1,599,046 | |
| 2 | TEXAS CORDIA CONSTRUCTION, LLC | $16,138,156 | +2.5% | -4.1% | $3,458,729 | 1+$171,245 | 8-$2,127,263 |
| 3 | FOREMOST PAVING, INC. | $19,596,885 | +24.5% | 16.5% | 8+$2,609,447 | 3-$394,687 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
REIM CONSTRUCTION, INC. vs TEXAS CORDIA CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 423-7001 RETAINING WALL (MSE) | 17,033 SF | $72.50 | $100.00 | $74.07 | $468,408 |
| 500-7001 MOBILIZATION | 1 LS | $1,300,000.00 | $834,900.00 | $523,850.32 | -$465,100 |
| 450-7016 RAIL (TY T551) | 2,047 LF | $211.00 | $50.00 | $164.46 | -$329,567 |
| 400-7010 CEM STABIL BKFL | 7,186 CY | $97.50 | $60.00 | $138.14 | -$269,475 |
| 344-7008 SP MIXES SP-B SAC-B PG76-22 | 19,263 TON | $112.00 | $120.00 | $117.26 | $154,104 |
| 531-7001 CONC SIDEWALKS (4") | 12,433 SY | $41.00 | $50.00 | $70.57 | $111,897 |
| 250-7002 GEOGRID BASE REINFORCEMENT (TYPE 2) | 106,046 SY | $1.10 | $2.00 | $1.65 | $95,441 |
| 512-7089 PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1 | 3,720 LF | $8.65 | $30.00 | $32.87 | $79,422 |
| 400-7005 STRUCT EXCAV (SPECIAL) | 2,983 CY | $73.50 | $100.00 | $42.59 | $79,050 |
| 110-7001 EXCAV (ROADWAY) | 44,651 CY | $5.30 | $7.00 | $11.68 | $75,907 |
| 529-7024 CONC CURB & GUTTER (TY B) (MOUNTABLE) | 16,907 LF | $15.00 | $19.00 | $16.02 | $67,628 |
| 420-7061 CL C CONC (COLLAR) | 14 EA | $898.00 | $5,340.00 | $1,390.28 | $62,188 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 11,007 TON | $115.00 | $120.00 | $138.38 | $55,035 |
| 247-7277 FL BS (RDWY DEL)(TY E GR 4)(FNL POS) | 14,422 CY | $34.50 | $38.00 | $29.59 | $50,477 |
| 529-7022 CONC CURB (TY F3) | 865 LF | $163.00 | $210.00 | $179.62 | $40,655 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 20 MO | $2,380.00 | $500.00 | $11,585.04 | -$37,600 |
| 403-7001 TEMPORARY SPL SHORING | 3,906 SF | $20.75 | $30.00 | $25.56 | $36,131 |
| 530-7006 DRIVEWAYS (CONC) | 1,166 SY | $61.00 | $90.00 | $109.20 | $33,814 |
| 7003-7002 WELDED STL CASING PIPE (OPEN CUT)(30") | 458 LF | $225.00 | $296.00 | $291.23 | $32,518 |
| 275-7008 CEMENT TRT (EXIST MATL & NEW BASE)(10") | 103,824 SY | $1.75 | $2.00 | $2.05 | $25,956 |
Positive: the low bidder was cheaper on that item. These 20 items account for $366,888 of the $398,990 gap.
REIM CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,300,000.00 | $523,850.32 | 2.48x | $776,150 |
| 100-7002 PREPARING ROW | 111 STA | $2,700.00 | $6,072.92 | 0.44x | -$374,394 |
| 508-7001 CONSTRUCTING DETOURS | 6,943 SY | $41.50 | $83.58 | 0.50x | -$292,195 |
| 110-7001 EXCAV (ROADWAY) | 44,651 CY | $5.30 | $11.68 | 0.45x | -$284,972 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 20 MO | $2,380.00 | $11,585.04 | 0.21x | -$184,101 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $11,300.00 | $62,461.14 | 0.18x | -$153,483 |
| 505-7001 TMA (STATIONARY) | 720 DAY | $28.00 | $217.57 | 0.13x | -$136,492 |
| 512-7089 PCTB (FUR&INST)(F-SHAPE OR SNGL SLP)TY1 | 3,720 LF | $8.65 | $32.87 | 0.26x | -$90,082 |
| 505-7003 TMA (MOBILE OPERATION) | 480 DAY | $56.00 | $229.60 | 0.24x | -$83,327 |
TEXAS CORDIA CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7005 STRUCT EXCAV (SPECIAL) | 2,983 CY | $100.00 | $42.59 | 2.35x | $171,245 |
| 400-7010 CEM STABIL BKFL | 7,186 CY | $60.00 | $138.14 | 0.43x | -$561,541 |
| 100-7002 PREPARING ROW | 111 STA | $2,500.00 | $6,072.92 | 0.41x | -$396,594 |
| 508-7001 CONSTRUCTING DETOURS | 6,943 SY | $38.00 | $83.58 | 0.45x | -$316,496 |
| 450-7016 RAIL (TY T551) | 2,047 LF | $50.00 | $164.46 | 0.30x | -$234,290 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 20 MO | $500.00 | $11,585.04 | 0.04x | -$221,701 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $11,600.00 | $62,461.14 | 0.19x | -$152,583 |
| 505-7001 TMA (STATIONARY) | 720 DAY | $15.00 | $217.57 | 0.07x | -$145,852 |
| 505-7003 TMA (MOBILE OPERATION) | 480 DAY | $25.00 | $229.60 | 0.11x | -$98,207 |
FOREMOST PAVING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,750,000.00 | $523,850.32 | 3.34x | $1,226,150 |
| 1004-7002 IRRIGATION WELL (60") | 9 EA | $81,000.00 | $24,800.00 | 3.27x | $505,800 |
| 529-7022 CONC CURB (TY F3) | 865 LF | $420.00 | $179.62 | 2.34x | $207,926 |
| 1004-7001 IRRIGATION WELL (48") | 4 EA | $65,000.00 | $23,400.00 | 2.78x | $166,400 |
| 464-7003 RC PIPE (CL III)(18 IN) | 2,223 LF | $150.00 | $83.08 | 1.81x | $148,760 |
| 7003-7002 WELDED STL CASING PIPE (OPEN CUT)(30") | 458 LF | $580.00 | $291.23 | 1.99x | $132,259 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 329 EA | $400.00 | $60.77 | 6.58x | $111,605 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 177 EA | $725.00 | $100.44 | 7.22x | $110,547 |
| 681-7001 TEMP TRAF SIGNALS | 3 EA | $10,250.00 | $62,461.14 | 0.16x | -$156,633 |
| 505-7001 TMA (STATIONARY) | 720 DAY | $40.00 | $217.57 | 0.18x | -$127,852 |
| 505-7003 TMA (MOBILE OPERATION) | 480 DAY | $0.0100 | $229.60 | 0.00x | -$110,202 |