ELP_US0067_2-SYS
0104-09-034 · let Jun 5, 2025 · Presidio, El Paso · Safety Improvement Projects
$3,181,974Low bid: DAN WILLIAMS COMPANY+6.1% vs estimate $2,999,399
$1,373,718Left on the table43.2% gap to the second bid
2BiddersSpread 43% low to high
78Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DAN WILLIAMS COMPANY | $3,181,974 | 6.1% | $1,373,718 | 13+$1,259,641 | 0 | |
| 2 | CK NEWBERRY, LLC | $4,555,692 | +43.2% | 51.9% | 17+$2,295,126 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
DAN WILLIAMS COMPANY vs CK NEWBERRY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7002 EMBANK (FNL)(DC)(TY A) | 7,422 CY | $45.00 | $125.00 | $15.82 | $593,760 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 2,509 TON | $275.00 | $350.00 | $137.95 | $188,175 |
| 500-7001 MOBILIZATION | 1 LS | $300,000.00 | $450,000.00 | $523,850.32 | $150,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $42,500.00 | $25,000.00 | $11,585.04 | -$87,500 |
| 496-7004 REMOV STR (SET) | 8 EA | $600.00 | $10,000.00 | $514.07 | $75,200 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 500 LF | $45.00 | $150.00 | $25.60 | $52,500 |
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 500 TON | $300.00 | $400.00 | $152.88 | $50,000 |
| 354-7051 PLANE ASPH CONC PAV(2") | 17,970 SY | $4.00 | $6.00 | $1.86 | $35,940 |
| 467-7436 SET (TY II) (DES 4) (CMP) (4: 1) (C) | 2 EA | $2,500.00 | $20,000.00 | $2,600.00 | $35,000 |
| 530-7006 DRIVEWAYS (CONC) | 449 SY | $155.00 | $225.00 | $109.20 | $31,430 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 531 CY | $250.00 | $300.00 | $179.97 | $26,550 |
| 467-7362 SET (TY II) (36 IN) (CMP) (4: 1) (C) | 2 EA | $3,000.00 | $15,000.00 | $4,296.67 | $24,000 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 570 SY | $100.00 | $60.00 | $34.56 | -$22,800 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 4,310 LF | $5.00 | $10.00 | $3.92 | $21,550 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 587 SY | $165.00 | $200.00 | $49.06 | $20,545 |
| 354-7044 PLANE ASPH CONC PAV(0" TO 0.5" MICRO) | 1,000 SY | $20.00 | $40.00 | $0.7773 | $20,000 |
| 467-7342 SET (TY II) (30 IN) (CMP) (4: 1) (C) | 2 EA | $2,500.00 | $12,000.00 | $2,185.40 | $19,000 |
| 260-7024 LIME TRT(SUBGRADE)(6") | 6,338 SY | $8.90 | $6.00 | $4.59 | -$18,380 |
| 542-7004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) | 2 EA | $450.00 | $8,000.00 | $284.77 | $15,100 |
| 505-7001 TMA (STATIONARY) | 75 DAY | $300.00 | $500.00 | $217.57 | $15,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,245,070 of the $1,373,718 gap.
DAN WILLIAMS COMPANY: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 2,509 TON | $275.00 | $137.95 | 1.99x | $343,868 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 7,422 CY | $45.00 | $15.82 | 2.84x | $216,564 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 6,338 SY | $50.00 | $21.46 | 2.33x | $180,888 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $42,500.00 | $11,585.04 | 3.67x | $154,575 |
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 500 TON | $300.00 | $152.88 | 1.96x | $73,561 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 587 SY | $165.00 | $49.06 | 3.36x | $68,054 |
| 112-7004 SUBGR WIDEN (DC) | 6,338 SY | $12.00 | $4.13 | 2.91x | $49,888 |
| 354-7051 PLANE ASPH CONC PAV(2") | 17,970 SY | $4.00 | $1.86 | 2.15x | $38,510 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 570 SY | $100.00 | $34.56 | 2.89x | $37,303 |
| 260-7024 LIME TRT(SUBGRADE)(6") | 6,338 SY | $8.90 | $4.59 | 1.94x | $27,336 |
CK NEWBERRY, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7002 EMBANK (FNL)(DC)(TY A) | 7,422 CY | $125.00 | $15.82 | 7.90x | $810,324 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 2,509 TON | $350.00 | $137.95 | 2.54x | $532,043 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 6,338 SY | $50.00 | $21.46 | 2.33x | $180,888 |
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 500 TON | $400.00 | $152.88 | 2.62x | $123,561 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 587 SY | $200.00 | $49.06 | 4.08x | $88,599 |
| 496-7004 REMOV STR (SET) | 8 EA | $10,000.00 | $514.07 | 19.45x | $75,887 |
| 354-7051 PLANE ASPH CONC PAV(2") | 17,970 SY | $6.00 | $1.86 | 3.23x | $74,450 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $25,000.00 | $11,585.04 | 2.16x | $67,075 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 500 LF | $150.00 | $25.60 | 5.86x | $62,199 |
| 530-7006 DRIVEWAYS (CONC) | 449 SY | $225.00 | $109.20 | 2.06x | $51,995 |