SH 71 - TRAVIS C/L to E. of TUCKER HILL
0265-03-043 · let Jun 4, 2025 · Bastrop, Austin · Interchange (New or Reconstructed)
$58,558,559Low bid: JORDAN FOSTER CONSTRUCTION, LLC-12.9% vs estimate $67,216,535
$841,304Left on the table1.4% gap to the second bid
9BiddersSpread 17% low to high
522Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JORDAN FOSTER CONSTRUCTION, LLC | $58,558,559 | -12.9% | $841,304 | 4+$8,499,681 | 1-$301,645 | |
| 2 | INDUS ROAD & BRIDGE, INC. | $59,399,863 | +1.4% | -11.6% | $2,139,764 | 3+$7,550,939 | 1-$309,985 |
| 3 | SER CONSTRUCTION PARTNERS, LLC | $61,539,627 | +5.1% | -8.4% | $2,119,527 | 5+$9,300,672 | 0 |
| 4 | HARPER BROTHERS CONSTRUCTION LLC | $63,659,154 | +8.7% | -5.3% | $715,284 | 4+$8,373,593 | 1-$2,290,664 |
| 5 | PULICE CONSTRUCTION, INC. | $64,374,438 | +9.9% | -4.2% | $465,586 | 10+$19,232,161 | 3-$2,982,021 |
| 6 | JAMES CONSTRUCTION GROUP, LLC | $64,840,024 | +10.7% | -3.5% | $2,764,529 | ||
| 7 | WEBBER, LLC | $67,604,553 | +15.4% | 0.6% | $436,237 | ||
| 8 | POSILLICO CIVIL, INC. | $68,040,790 | +16.2% | 1.2% | $607,910 | ||
| 9 | ZACHRY CONSTRUCTION CORPORATION | $68,648,699 | +17.2% | 2.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JORDAN FOSTER CONSTRUCTION, LLC vs INDUS ROAD & BRIDGE, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 24,679 SY | $82.00 | $132.00 | $83.58 | $1,233,950 |
| 100-7002 PREPARING ROW | 89.68 STA | $32,000.00 | $24,328.05 | $6,072.92 | -$688,020 |
| 276-7100 CM TRT(PT MX)(CL N)(TY A)(GR 5)(FN POS) | 11,563 CY | $150.00 | $98.00 | $137.95 | -$601,276 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 15,690 LF | $32.00 | $70.00 | $38.28 | $596,220 |
| 341-7001 D-GR HMA TY-B PG64-22 | 13,480 TON | $100.00 | $129.00 | $97.82 | $390,920 |
| 512-7093 PORT CTB (FURN & INST)(TL-3 LPCB) | 3,870 LF | $27.00 | $100.00 | $67.00 | $282,510 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 4,360 LF | $16.85 | $77.00 | $43.56 | $262,254 |
| 105-7123 REMOVE STAB BASE AND ASPH PAV (6"-20") | 68,059 SY | $7.35 | $11.00 | $9.85 | $248,415 |
| 416-7006 DRILL SHAFT (36 IN) | 3,216 LF | $205.00 | $280.00 | $280.58 | $241,200 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 26,250 LF | $9.00 | $18.00 | $9.41 | $236,250 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 MO | $29,000.00 | $21,000.00 | $11,585.04 | -$232,000 |
| 247-7191 FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS) | 9,136 CY | $82.00 | $57.00 | $62.11 | -$228,400 |
| 422-7001 REINF CONC SLAB | 45,120 SF | $28.00 | $23.00 | $24.45 | -$225,600 |
| 403-7001 TEMPORARY SPL SHORING | 2,547 SF | $180.00 | $103.00 | $25.56 | -$196,119 |
| 529-7009 CONC CURB & GUTTER (TY II) | 16,982 LF | $33.00 | $22.00 | $32.57 | -$186,802 |
| 432-7002 RIPRAP (CONC)(5 IN) | 645.4 CY | $715.00 | $450.00 | $585.15 | -$171,031 |
| 530-7010 DRIVEWAYS (ACP) | 4,770 SY | $70.00 | $105.00 | $54.96 | $166,950 |
| 500-7001 MOBILIZATION | 1 LS | $5,800,000.00 | $5,940,000.00 | $523,850.32 | $140,000 |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) | 6,216 SY | $18.00 | $40.00 | $30.47 | $136,752 |
| 341-7056 D-GR HMA TY-D PG76-22 | 4,730 TON | $135.00 | $160.00 | $123.11 | $118,250 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,524,423 of the $841,304 gap.
JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,800,000.00 | $523,850.32 | 11.07x | $5,276,150 |
| 100-7002 PREPARING ROW | 89.68 STA | $32,000.00 | $6,072.92 | 5.27x | $2,325,140 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 MO | $29,000.00 | $11,585.04 | 2.50x | $505,034 |
| 403-7001 TEMPORARY SPL SHORING | 2,547 SF | $180.00 | $25.56 | 7.04x | $393,357 |
| 168-7001 VEGETATIVE WATERING | 41,700 TGL | $1.20 | $8.43 | 0.14x | -$301,645 |
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,940,000.00 | $523,850.32 | 11.34x | $5,416,150 |
| 100-7002 PREPARING ROW | 89.68 STA | $24,328.05 | $6,072.92 | 4.01x | $1,637,120 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 15,690 LF | $70.00 | $38.28 | 1.83x | $497,670 |
| 168-7001 VEGETATIVE WATERING | 41,700 TGL | $1.00 | $8.43 | 0.12x | -$309,985 |
SER CONSTRUCTION PARTNERS, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,100,000.00 | $523,850.32 | 11.64x | $5,576,150 |
| 100-7002 PREPARING ROW | 89.68 STA | $23,500.00 | $6,072.92 | 3.87x | $1,562,860 |
| 168-7001 VEGETATIVE WATERING | 41,700 TGL | $31.80 | $8.43 | 3.77x | $974,375 |
| 450-7024 RAIL (TY SSTR) | 6,231 LF | $188.30 | $69.92 | 2.69x | $737,611 |
| 467-7233 SET (TY I)(S= 10 FT)(HW= 6 FT)(6:1)(P) | 12 EA | $71,973.00 | $34,500.00 | 2.09x | $449,676 |
HARPER BROTHERS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 423-7001 RETAINING WALL (MSE) | 69,802 SF | $135.00 | $74.07 | 1.82x | $4,252,910 |
| 500-7001 MOBILIZATION | 1 LS | $3,125,000.00 | $523,850.32 | 5.97x | $2,601,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 29 MO | $50,000.00 | $11,585.04 | 4.32x | $1,114,034 |
| 450-7024 RAIL (TY SSTR) | 6,231 LF | $135.00 | $69.92 | 1.93x | $405,499 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 213,815 CY | $6.25 | $16.96 | 0.37x | -$2,290,664 |
PULICE CONSTRUCTION, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $6,398,687.01 | $523,850.32 | 12.21x | $5,874,837 |
| 100-7002 PREPARING ROW | 89.68 STA | $71,364.00 | $6,072.92 | 11.75x | $5,855,304 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 188,972 SY | $12.53 | $1.43 | 8.77x | $2,097,721 |
| 168-7001 VEGETATIVE WATERING | 41,700 TGL | $55.61 | $8.43 | 6.59x | $1,967,252 |
| 529-7009 CONC CURB & GUTTER (TY II) | 16,982 LF | $100.24 | $32.57 | 3.08x | $1,149,203 |
| 416-7006 DRILL SHAFT (36 IN) | 3,216 LF | $494.34 | $280.58 | 1.76x | $687,453 |
| 531-7002 CONC SIDEWALKS (5") | 4,934 SY | $179.02 | $68.80 | 2.60x | $543,815 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 24,467 CY | $33.26 | $18.71 | 1.78x | $355,921 |
| 529-7008 CONC CURB & GUTTER (TY I) | 4,813 LF | $98.94 | $25.20 | 3.93x | $354,904 |
| 530-7010 DRIVEWAYS (ACP) | 4,770 SY | $127.44 | $54.96 | 2.32x | $345,751 |
| 276-7100 CM TRT(PT MX)(CL N)(TY A)(GR 5)(FN POS) | 11,563 CY | $31.28 | $137.95 | 0.23x | -$1,233,381 |
| 508-7001 CONSTRUCTING DETOURS | 24,679 SY | $37.04 | $83.58 | 0.44x | -$1,148,682 |
| 110-7001 EXCAV (ROADWAY) | 90,598 CY | $5.06 | $11.68 | 0.43x | -$599,958 |