Crack Seal FY 26
6478-78-001 · let Jun 12, 2025 · Lavaca, Yoakum · Routine Maintenance Project - Sealed
$1,172,845Low bid: CRACKSEAL OF TEXAS, LLC+17.8% vs estimate $995,670
$285,314Left on the table24.3% gap to the second bid
4BiddersSpread 40% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CRACKSEAL OF TEXAS, LLC | $1,172,845 | 17.8% | $285,314 | 0 | 2-$541,909 | |
| 2 | FYL ENTERPRISES, LLC | $1,458,159 | +24.3% | 46.4% | $40,364 | 0 | 2-$491,826 |
| 3 | ICOS MANAGEMENT, LLC | $1,498,523 | +27.8% | 50.5% | $139,104 | 0 | 2-$391,826 |
| 4 | D & M CONTRACTORS, LLC | $1,637,627 | +39.6% | 64.5% | 0 | 2-$524,017 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
CRACKSEAL OF TEXAS, LLC vs FYL ENTERPRISES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 1,656.56 LMI | $708.00 | $850.00 | $868.20 | $235,232 |
| 500-7001 MOBILIZATION | 1 LS | $0.0100 | $50,000.00 | $523,850.32 | $50,000 |
| 505-7001 TMA (STATIONARY) | 83 DAY | $0.0010 | $1.00 | $217.57 | $83 |
Positive: the low bidder was cheaper on that item. These 3 items account for $285,314 of the $285,314 gap.