FY26 MBGF & Cable Barrier Repair
6479-91-001 · let Jun 4, 2025 · Jefferson, Beaumont · Routine Maintenance Project - Sealed
$622,654Low bid: ROSS SA ENTERPRISE LLC-41.6% vs estimate $1,065,545
$236,974Left on the table38.1% gap to the second bid
4BiddersSpread 77% low to high
76Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ROSS SA ENTERPRISE LLC | $622,654 | -41.6% | $236,974 | 7+$121,371 | 17-$277,981 | |
| 2 | RHINO EQUITY, LLC | $859,628 | +38.1% | -19.3% | $131,073 | 15+$356,879 | 9-$287,496 |
| 3 | T&L CLEANING SERVICES LLC | $990,701 | +59.1% | -7.0% | $113,092 | 6+$201,864 | 6-$99,389 |
| 4 | ISI CONTRACTING, INC. | $1,103,793 | +77.3% | 3.6% | 16+$427,817 | 2-$140,433 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
ROSS SA ENTERPRISE LLC vs RHINO EQUITY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 50 EA | $3,000.00 | $300.00 | $2,869.78 | -$135,000 |
| 774-7038 REPAIR (TAU-M BAY) NARROW | 10 EA | $500.00 | $10,000.00 | $500.00 | $95,000 |
| 774-7011 REPLACE (QUAD - ELITE) WIDE | 2 EA | $100.00 | $25,000.00 | $4,285.00 | $49,800 |
| 545-7010 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) | 1 EA | $5,000.00 | $54,000.00 | $25,783.02 | $49,000 |
| 774-7006 REPAIR (SMTC) WIDE | 40 LF | $100.00 | $1,000.00 | $172.25 | $36,000 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 30 EA | $1,000.00 | $1.00 | $67.25 | -$29,970 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 750 LF | $1.00 | $40.00 | $31.82 | $29,250 |
| 774-7012 REPAIR (QUAD - ELITE) WIDE | 60 LF | $50.00 | $500.00 | $105.18 | $27,000 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $1.00 | $200.00 | $217.57 | $25,870 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 130 EA | $1.00 | $200.00 | $67.59 | $25,870 |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 20 EA | $800.00 | $2,000.00 | $975.38 | $24,000 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 75 EA | $500.00 | $300.00 | $89.82 | -$15,000 |
| 774-7073 REPAIR (QUAD)(N)(M) | 60 LF | $250.00 | $500.00 | $234.62 | $15,000 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 15 EA | $1,000.00 | $50.00 | $1,019.22 | -$14,250 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 10 EA | $1.00 | $1,280.00 | $65.99 | $12,790 |
| 774-7037 REPAIR (TAU-M) NARROW | 30 LF | $100.00 | $500.00 | $350.57 | $12,000 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 200 EA | $1.00 | $60.00 | $144.70 | $11,800 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 3,750 LF | $27.00 | $30.00 | $22.03 | $11,250 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $7,870.00 | $6,000.00 | $87.82 | -$9,350 |
| 770-7021 REPLACE SGT OBJECT MARKER | 15 EA | $1.00 | $450.00 | $34.21 | $6,735 |
Positive: the low bidder was cheaper on that item. These 20 items account for $227,795 of the $236,974 gap.
ROSS SA ENTERPRISE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $7,870.00 | $87.82 | 89.62x | $38,911 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 75 EA | $500.00 | $89.82 | 5.57x | $30,763 |
| 771-7018 CHECK / RE-TENSION CABLE (TL-4) | 30 EA | $1,000.00 | $67.25 | 14.87x | $27,982 |
| 770-7018 REPLACE BLOCKOUT | 150 EA | $100.00 | $44.95 | 2.22x | $8,257 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 40 EA | $250.00 | $94.21 | 2.65x | $6,232 |
| 771-7016 REPLACE CABLE (TL-4) | 100 LF | $50.00 | $2.15 | 23.26x | $4,785 |
| 5010-7002 PEDESTRIAN BARRIER (REMOVE & REINSTALL) | 100 LF | $50.00 | $5.59 | 8.95x | $4,441 |
| 500-7002 MOBILIZATION (CALLOUT) | 75 EA | $1.00 | $600.85 | 0.00x | -$44,989 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 100 LF | $50.00 | $380.94 | 0.13x | -$33,094 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 200 EA | $1.00 | $144.70 | 0.01x | -$28,739 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $1.00 | $217.57 | 0.00x | -$28,154 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 750 LF | $1.00 | $31.82 | 0.03x | -$23,113 |
| 771-7005 REPLACE POSTS (TL-4)(GIBRALTAR) | 200 EA | $50.00 | $159.54 | 0.31x | -$21,907 |
| 545-7010 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) | 1 EA | $5,000.00 | $25,783.02 | 0.19x | -$20,783 |
| 771-7006 REPLACE POSTS (TL-4)(NU-CABLE) | 200 EA | $1.00 | $75.00 | 0.01x | -$14,799 |
| 770-7010 REALIGN POSTS | 500 EA | $0.2500 | $24.32 | 0.01x | -$12,037 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 50 LF | $25.00 | $228.58 | 0.11x | -$10,179 |
RHINO EQUITY, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 774-7038 REPAIR (TAU-M BAY) NARROW | 10 EA | $10,000.00 | $500.00 | 20.00x | $95,000 |
| 774-7011 REPLACE (QUAD - ELITE) WIDE | 2 EA | $25,000.00 | $4,285.00 | 5.83x | $41,430 |
| 774-7006 REPAIR (SMTC) WIDE | 40 LF | $1,000.00 | $172.25 | 5.81x | $33,110 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $6,000.00 | $87.82 | 68.32x | $29,561 |
| 545-7010 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) | 1 EA | $54,000.00 | $25,783.02 | 2.09x | $28,217 |
| 774-7012 REPAIR (QUAD - ELITE) WIDE | 60 LF | $500.00 | $105.18 | 4.75x | $23,689 |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 20 EA | $2,000.00 | $975.38 | 2.05x | $20,492 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 130 EA | $200.00 | $67.59 | 2.96x | $17,213 |
| 774-7073 REPAIR (QUAD)(N)(M) | 60 LF | $500.00 | $234.62 | 2.13x | $15,923 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 75 EA | $300.00 | $89.82 | 3.34x | $15,763 |
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 50 EA | $300.00 | $2,869.78 | 0.10x | -$128,489 |
| 500-7002 MOBILIZATION (CALLOUT) | 75 EA | $1.00 | $600.85 | 0.00x | -$44,989 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 100 LF | $50.00 | $380.94 | 0.13x | -$33,094 |
| 771-7005 REPLACE POSTS (TL-4)(GIBRALTAR) | 200 EA | $60.00 | $159.54 | 0.38x | -$19,907 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 200 EA | $60.00 | $144.70 | 0.41x | -$16,939 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 15 EA | $50.00 | $1,019.22 | 0.05x | -$14,538 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 50 LF | $1.00 | $228.58 | 0.00x | -$11,379 |
| 771-7006 REPLACE POSTS (TL-4)(NU-CABLE) | 200 EA | $20.00 | $75.00 | 0.27x | -$10,999 |
| 770-7010 REALIGN POSTS | 500 EA | $10.00 | $24.32 | 0.41x | -$7,162 |
T&L CLEANING SERVICES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 774-7011 REPLACE (QUAD - ELITE) WIDE | 2 EA | $50,000.00 | $4,285.00 | 11.67x | $91,430 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 750 LF | $100.00 | $31.82 | 3.14x | $51,137 |
| 5010-7002 PEDESTRIAN BARRIER (REMOVE & REINSTALL) | 100 LF | $250.00 | $5.59 | 44.75x | $24,441 |
| 5010-7001 PEDESTRIAN BARRIER (FURN & INSTALL) | 100 LF | $250.00 | $38.33 | 6.52x | $21,167 |
| 774-7012 REPAIR (QUAD - ELITE) WIDE | 60 LF | $250.00 | $105.18 | 2.38x | $8,689 |
| 774-7038 REPAIR (TAU-M BAY) NARROW | 10 EA | $1,000.00 | $500.00 | 2.00x | $5,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 75 EA | $1.00 | $600.85 | 0.00x | -$44,989 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $100.00 | $217.57 | 0.46x | -$15,284 |
| 771-7006 REPLACE POSTS (TL-4)(NU-CABLE) | 200 EA | $1.00 | $75.00 | 0.01x | -$14,799 |
| 770-7010 REALIGN POSTS | 500 EA | $1.00 | $24.32 | 0.04x | -$11,662 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 75 EA | $1.00 | $89.82 | 0.01x | -$6,662 |
| 770-7018 REPLACE BLOCKOUT | 150 EA | $5.00 | $44.95 | 0.11x | -$5,993 |
ISI CONTRACTING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 774-7011 REPLACE (QUAD - ELITE) WIDE | 2 EA | $43,127.00 | $4,285.00 | 10.06x | $77,684 |
| 771-7014 REPR OR REPLC CABLE BARR TERM SEC(TL-4) | 15 EA | $4,695.00 | $1,019.22 | 4.61x | $55,137 |
| 774-7074 REPLACE (QUAD)(N)(M) | 2 EA | $43,127.00 | $17,375.00 | 2.48x | $51,504 |
| 771-7006 REPLACE POSTS (TL-4)(NU-CABLE) | 200 EA | $293.00 | $75.00 | 3.91x | $43,601 |
| 505-7001 TMA (STATIONARY) | 130 DAY | $500.00 | $217.57 | 2.30x | $36,716 |
| 774-7036 REPLACE (TAU-M) NARROW | 1 EA | $43,127.00 | $8,494.67 | 5.08x | $34,632 |
| 771-7007 REPLACE POSTS (TL-4)(TRINITY) | 200 EA | $293.00 | $144.70 | 2.02x | $29,661 |
| 771-7005 REPLACE POSTS (TL-4)(GIBRALTAR) | 200 EA | $293.00 | $159.54 | 1.84x | $26,693 |
| 451-7049 RETROFIT RAIL (TY T131RC) | 50 LF | $551.00 | $228.58 | 2.41x | $16,121 |
| 5010-7002 PEDESTRIAN BARRIER (REMOVE & REINSTALL) | 100 LF | $117.00 | $5.59 | 20.94x | $11,141 |
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 50 EA | $471.00 | $2,869.78 | 0.16x | -$119,939 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 100 LF | $176.00 | $380.94 | 0.46x | -$20,494 |