Bid Tab X-ray: 6475-25-001

Jun 4, 2025 · Jasper Sign up free
Set your company to personalize scores

2026 ORANGE AREA MBGF

6475-25-001 · let Jun 4, 2025 · Jasper, Beaumont · Routine Maintenance Project - Sealed

$671,470Low bid: ROSS SA ENTERPRISE LLC-52.6% vs estimate $1,415,278
$109,341Left on the table16.3% gap to the second bid
4BiddersSpread 33% low to high
73Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1ROSS SA ENTERPRISE LLC $671,470-52.6% $109,341 6+$420,541 9-$209,928
2ISI CONTRACTING, INC. $780,811+16.3%-44.8% $15,659 5+$400,767 6-$58,758
3T&L CLEANING SERVICES LLC $796,470+18.6%-43.7% $99,326 10+$297,134 7-$101,437
4ACE CONTRACTORS, INC. $895,796+33.4%-36.7% 12+$375,280 5-$77,927

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

ROSS SA ENTERPRISE LLC vs ISI CONTRACTING, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
770-7013 REM OBSOLETE GET & REPL W/ SGT15 EA $7,468.00$2,371.00$2,869.78 -$76,455
451-7049 RETROFIT RAIL (TY T131RC)150 LF $40.00$276.00$228.58 $35,400
774-7005 REPLACE (SMTC) WIDE1 EA $5,000.00$37,677.00$25,508.81 $32,677
770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD30 EA $1.00$1,049.00$975.38 $31,440
500-7002 MOBILIZATION (CALLOUT)60 EA $1.00$355.00$600.85 $21,240
770-7018 REPLACE BLOCKOUT200 EA $50.00$150.00$44.95 $20,000
770-7001 REPLACE RAIL ELEMENT (W-BEAM)5,000 LF $8.00$12.00$22.03 $20,000
770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL1,000 LF $25.00$7.00$31.82 -$18,000
774-7020 REPLACE (TAU II-R) NARROW1 EA $25,000.00$37,677.00$8,529.41 $12,677
774-7026 REPLACE (NARROW QUAD)1 EA $25,000.00$37,677.00$9,579.42 $12,677
774-7002 REPLACE (SMTC) NARROW1 EA $25,000.00$31,354.00$24,419.83 $6,354
505-7001 TMA (STATIONARY)62 DAY $5,000.00$5,100.00$217.57 $6,200
774-7029 REPAIR (NARROW QUAD BAY)5 EA $1,500.00$527.00$1,490.11 -$4,865
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN1 DAY $4,800.00$211.00$87.82 -$4,589
540-7041 TERMINAL ANCHOR SECTION5 EA $1.00$896.00$630.09 $4,475
432-7013 RIPRAP (MOW STRIP)(4 IN)10 CY $100.00$533.00$616.83 $4,330
770-7023 REPLACE SGT CABLE ASSEMBLY30 EA $1.00$117.00$98.88 $3,480
770-7017 REPLACE SINGLE GDRAIL TERMINAL POST175 EA $50.00$31.00$67.59 -$3,325
770-7019 REPAIR STEEL POST WITH BASE PLATE10 EA $50.00$376.00$137.68 $3,260
500-7033 MOBILIZATION (EMERGENCY)12 EA $500.00$709.00$844.81 $2,508

Positive: the low bidder was cheaper on that item. These 20 items account for $109,484 of the $109,341 gap.

ROSS SA ENTERPRISE LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)62 DAY $5,000.00$217.5722.98x$296,511
770-7013 REM OBSOLETE GET & REPL W/ SGT15 EA $7,468.00$2,869.782.60x$68,973
774-7008 REPLACE (QUAD - ELITE) NARROW1 EA $25,000.00$6,545.913.82x$18,454
774-7020 REPLACE (TAU II-R) NARROW1 EA $25,000.00$8,529.412.93x$16,471
774-7026 REPLACE (NARROW QUAD)1 EA $25,000.00$9,579.422.61x$15,421
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN1 DAY $4,800.00$87.8254.66x$4,712
770-7001 REPLACE RAIL ELEMENT (W-BEAM)5,000 LF $8.00$22.030.36x-$70,138
500-7002 MOBILIZATION (CALLOUT)60 EA $1.00$600.850.00x-$35,991
770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD30 EA $1.00$975.380.00x-$29,232
451-7049 RETROFIT RAIL (TY T131RC)150 LF $40.00$228.580.17x-$28,287
774-7005 REPLACE (SMTC) WIDE1 EA $5,000.00$25,508.810.20x-$20,509
774-7021 REPAIR (TAU II-R) NARROW50 LF $100.00$272.670.37x-$8,633
770-7004 REPLACE SHORT RADIUS SYS (TL-2)25 EA $1.00$339.200.00x-$8,455
432-7013 RIPRAP (MOW STRIP)(4 IN)10 CY $100.00$616.830.16x-$5,168
774-7007 REMOVE (QUAD - ELITE) NARROW10 EA $25.00$376.570.07x-$3,516

ISI CONTRACTING, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)62 DAY $5,100.00$217.5723.44x$302,711
774-7020 REPLACE (TAU II-R) NARROW1 EA $37,677.00$8,529.414.42x$29,148
774-7026 REPLACE (NARROW QUAD)1 EA $37,677.00$9,579.423.93x$28,098
770-7018 REPLACE BLOCKOUT200 EA $150.00$44.953.34x$21,009
774-7008 REPLACE (QUAD - ELITE) NARROW1 EA $26,348.00$6,545.914.03x$19,802
770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL1,000 LF $7.00$31.820.22x-$24,818
774-7021 REPAIR (TAU II-R) NARROW50 LF $105.00$272.670.39x-$8,383
770-7004 REPLACE SHORT RADIUS SYS (TL-2)25 EA $21.00$339.200.06x-$7,955
770-7017 REPLACE SINGLE GDRAIL TERMINAL POST175 EA $31.00$67.590.46x-$6,404
770-7006 REPLACE TIMBER POST W/O CONC FND100 EA $26.00$89.820.29x-$6,382
774-7029 REPAIR (NARROW QUAD BAY)5 EA $527.00$1,490.110.35x-$4,816

T&L CLEANING SERVICES LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
770-7004 REPLACE SHORT RADIUS SYS (TL-2)25 EA $5,000.00$339.2014.74x$116,520
770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL1,000 LF $100.00$31.823.14x$68,182
774-7005 REPLACE (SMTC) WIDE1 EA $51,000.00$25,508.812.00x$25,491
774-7008 REPLACE (QUAD - ELITE) NARROW1 EA $30,000.00$6,545.914.58x$23,454
774-7026 REPLACE (NARROW QUAD)1 EA $26,000.00$9,579.422.71x$16,421
540-7003 MTL THRIE-BEAM GD FEN (TIM POST)10 LF $1,500.00$25.7958.16x$14,742
774-7020 REPLACE (TAU II-R) NARROW1 EA $20,000.00$8,529.412.34x$11,471
545-7001 CRASH CUSH ATTEN (DES SOURCE)1 EA $10,000.00$1,747.215.72x$8,253
429-7009 CONC STR REPAIR (STANDARD)18 SF $500.00$146.353.42x$6,366
774-7007 REMOVE (QUAD - ELITE) NARROW10 EA $1,000.00$376.572.66x$6,234
500-7002 MOBILIZATION (CALLOUT)60 EA $1.00$600.850.00x-$35,991
451-7049 RETROFIT RAIL (TY T131RC)150 LF $100.00$228.580.44x-$19,287
505-7001 TMA (STATIONARY)62 DAY $1.00$217.570.00x-$13,427
500-7033 MOBILIZATION (EMERGENCY)12 EA $1.00$844.810.00x-$10,126
774-7021 REPAIR (TAU II-R) NARROW50 LF $100.00$272.670.37x-$8,633
770-7018 REPLACE BLOCKOUT200 EA $10.00$44.950.22x-$6,991
770-7006 REPLACE TIMBER POST W/O CONC FND100 EA $20.00$89.820.22x-$6,982

ACE CONTRACTORS, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)62 DAY $3,000.00$217.5713.79x$172,511
774-7020 REPLACE (TAU II-R) NARROW1 EA $35,000.00$8,529.414.10x$26,471
770-7017 REPLACE SINGLE GDRAIL TERMINAL POST175 EA $200.00$67.592.96x$23,171
774-7003 REPAIR (SMTC) NARROW10 LF $2,500.00$202.8012.33x$22,972
774-7005 REPLACE (SMTC) WIDE1 EA $47,500.00$25,508.811.86x$21,991
774-7009 REPAIR (QUAD - ELITE) NARROW10 LF $2,000.00$136.6514.64x$18,634
774-7027 REPAIR (NARROW QUAD)10 LF $2,000.00$153.6913.01x$18,463
774-7008 REPLACE (QUAD - ELITE) NARROW1 EA $25,000.00$6,545.913.82x$18,454
774-7006 REPAIR (SMTC) WIDE10 LF $2,000.00$172.2511.61x$18,278
774-7026 REPLACE (NARROW QUAD)1 EA $25,000.00$9,579.422.61x$15,421
500-7002 MOBILIZATION (CALLOUT)60 EA $1.00$600.850.00x-$35,991
451-7049 RETROFIT RAIL (TY T131RC)150 LF $100.00$228.580.44x-$19,287
500-7033 MOBILIZATION (EMERGENCY)12 EA $1.00$844.810.00x-$10,126
770-7004 REPLACE SHORT RADIUS SYS (TL-2)25 EA $25.00$339.200.07x-$7,855
432-7013 RIPRAP (MOW STRIP)(4 IN)10 CY $150.00$616.830.24x-$4,668