6485-19-001 ASPPM
6485-19-001 · let Jun 10, 2025 · Pecos, Odessa · Material Maintenance Project
$98,560Low bid: SOUTHERN SOURCING SOLUTIONS, LLC-6.1% vs estimate $105,000
$12,040Left on the table12.2% gap to the second bid
2BiddersSpread 12% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SOUTHERN SOURCING SOLUTIONS, LLC | $98,560 | -6.1% | $12,040 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $110,600 | +12.2% | 5.3% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
SOUTHERN SOURCING SOLUTIONS, LLC vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8012-7042 ASPH CONC PATCH MAT (DEL)(ST3) | 100 TON | $198.21 | $244.00 | $195.54 | $4,579 |
| 8012-7044 ASPH CONC PATCH MAT (DEL)(ST5) | 100 TON | $209.10 | $242.00 | $197.24 | $3,290 |
| 8012-7040 ASPH CONC PATCH MAT (DEL)(ST1) | 100 TON | $185.37 | $215.00 | $158.39 | $2,963 |
| 8012-7043 ASPH CONC PATCH MAT (DEL)(ST4) | 100 TON | $198.02 | $210.00 | $197.37 | $1,198 |
| 8012-7041 ASPH CONC PATCH MAT (DEL)(ST2) | 100 TON | $194.90 | $195.00 | $175.27 | $10 |
Positive: the low bidder was cheaper on that item. These 5 items account for $12,040 of the $12,040 gap.