CityofWhartonSchool&CommunityConnectivit
0913-09-133 · let Jul 2, 2025 · Wharton, Yoakum · Pedestrian, Sidewalks & Curb Ramps
$2,973,237Low bid: TI-ZACK CONCRETE, LLC-17.5% vs estimate $3,601,994
$138,050Left on the table4.6% gap to the second bid
8BiddersSpread 33% low to high
82Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TI-ZACK CONCRETE, LLC | $2,973,237 | -17.5% | $138,050 | 1+$21,730 | 4-$717,247 | |
| 2 | 3LW CIVIL LLC | $3,111,287 | +4.6% | -13.6% | $87,594 | 5+$251,608 | 5-$703,296 |
| 3 | TALBERT COMPANIES LLC | $3,198,881 | +7.6% | -11.2% | $162,113 | 6+$192,191 | 2-$169,004 |
| 4 | STX CIVIL | $3,360,994 | +13.0% | -6.7% | $230,178 | 4+$142,935 | 3-$182,794 |
| 5 | ENCINO LANDSCAPE, INC. | $3,591,172 | +20.8% | -0.3% | $142,608 | 5+$232,233 | 2-$263,372 |
| 6 | E-Z BEL CONSTRUCTION, LLC | $3,733,780 | +25.6% | 3.7% | $209,401 | ||
| 7 | C. E. BARKER, LTD. | $3,943,181 | +32.6% | 9.5% | $5,169 | ||
| 8 | RAGLE CONSTRUCTION, INC. | $3,948,350 | +32.8% | 9.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TI-ZACK CONCRETE, LLC vs 3LW CIVIL LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 531-7003 CONC SIDEWALKS (6") | 8,820 SY | $118.81 | $110.00 | $88.84 | -$77,704 |
| 100-7002 PREPARING ROW | 47 STA | $400.00 | $1,750.00 | $6,072.92 | $63,450 |
| 530-7006 DRIVEWAYS (CONC) | 2,471 SY | $128.68 | $106.49 | $109.20 | -$54,831 |
| 104-7018 REMOV CONC (CURB OR CURB & GUTTER) | 4,926 LF | $9.16 | $18.50 | $11.27 | $46,009 |
| 505-7001 TMA (STATIONARY) | 20 DAY | $0.0100 | $2,000.00 | $217.57 | $40,000 |
| 529-7016 CONC CURB (TY C1) | 391 LF | $150.99 | $53.11 | $121.20 | -$38,271 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 553 SY | $95.00 | $162.00 | $60.19 | $37,051 |
| 500-7001 MOBILIZATION | 1 LS | $238,075.31 | $203,000.00 | $523,850.32 | -$35,075 |
| 529-7017 CONC CURB (TY F1) | 257 LF | $211.39 | $130.74 | $168.53 | -$20,727 |
| 529-7009 CONC CURB & GUTTER (TY II) | 3,721 LF | $54.66 | $60.00 | $32.57 | $19,870 |
| 480-7001 CLEAN EXIST CULVERTS | 6 EA | $500.00 | $3,750.00 | $1,712.97 | $19,500 |
| 531-7020 CURB RAMPS (TY 7) | 326 SY | $135.52 | $195.00 | $201.04 | $19,390 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 1,224 SY | $24.59 | $40.00 | $6.84 | $18,862 |
| 529-7015 CONC CURB (TY F2) | 442 LF | $176.16 | $139.38 | $154.71 | -$16,257 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,616.00 | $2,588.57 | $11,585.04 | $13,616 |
| 479-7001 ADJUSTING MANHOLES | 5 EA | $300.96 | $3,000.00 | $1,510.21 | $13,495 |
| 529-7022 CONC CURB (TY F3) | 130 LF | $264.24 | $168.72 | $179.62 | -$12,418 |
| 479-7003 ADJUSTING MANHOLES & INLETS | 3 EA | $501.60 | $4,500.00 | $1,535.11 | $11,995 |
| 531-7021 CURB RAMPS (TY 10) | 236 SY | $135.52 | $184.46 | $266.68 | $11,550 |
| 677-7008 ELIM EXT PM & MRKS (24") | 1,297 LF | $4.40 | $13.20 | $2.87 | $11,414 |
Positive: the low bidder was cheaper on that item. These 20 items account for $70,918 of the $138,050 gap.
TI-ZACK CONCRETE, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 1,224 SY | $24.59 | $6.84 | 3.60x | $21,730 |
| 500-7001 MOBILIZATION | 1 LS | $238,075.31 | $523,850.32 | 0.45x | -$285,775 |
| 100-7002 PREPARING ROW | 47 STA | $400.00 | $6,072.92 | 0.07x | -$266,627 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,616.00 | $11,585.04 | 0.14x | -$139,567 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 1 EA | $9,667.06 | $34,944.96 | 0.28x | -$25,278 |
3LW CIVIL LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7009 CONC CURB & GUTTER (TY II) | 3,721 LF | $60.00 | $32.57 | 1.84x | $102,074 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 553 SY | $162.00 | $60.19 | 2.69x | $56,300 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 1,224 SY | $40.00 | $6.84 | 5.85x | $40,591 |
| 505-7001 TMA (STATIONARY) | 20 DAY | $2,000.00 | $217.57 | 9.19x | $35,649 |
| 531-7025 CONC SIDEWALKS (SPECIAL) | 15 SY | $1,250.00 | $117.04 | 10.68x | $16,994 |
| 500-7001 MOBILIZATION | 1 LS | $203,000.00 | $523,850.32 | 0.39x | -$320,850 |
| 100-7002 PREPARING ROW | 47 STA | $1,750.00 | $6,072.92 | 0.29x | -$203,177 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $2,588.57 | $11,585.04 | 0.22x | -$125,951 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 1 EA | $8,250.00 | $34,944.96 | 0.24x | -$26,695 |
| 529-7016 CONC CURB (TY C1) | 391 LF | $53.11 | $121.20 | 0.44x | -$26,623 |
TALBERT COMPANIES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7015 CONC CURB (TY F2) | 442 LF | $297.55 | $154.71 | 1.92x | $63,136 |
| 529-7016 CONC CURB (TY C1) | 391 LF | $217.05 | $121.20 | 1.79x | $37,478 |
| 464-7003 RC PIPE (CL III)(18 IN) | 28 LF | $1,375.00 | $83.08 | 16.55x | $36,174 |
| 480-7001 CLEAN EXIST CULVERTS | 6 EA | $4,950.00 | $1,712.97 | 2.89x | $19,422 |
| 465-7126 INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) | 2 EA | $16,335.00 | $7,339.80 | 2.23x | $17,990 |
| 529-7022 CONC CURB (TY F3) | 130 LF | $318.01 | $179.62 | 1.77x | $17,990 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $1,318.89 | $11,585.04 | 0.11x | -$143,726 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 1 EA | $9,667.06 | $34,944.96 | 0.28x | -$25,278 |
STX CIVIL: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7002 SPOT TREE TRIMMING / BRUSH REMOVAL | 370 LF | $150.00 | $1.20 | 125.11x | $55,056 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 553 SY | $125.00 | $60.19 | 2.08x | $35,839 |
| 6099-7001 PEDESTRAIN ILLUMINATION ASSEMBLY | 6 EA | $11,959.71 | $6,293.48 | 1.90x | $33,997 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 848 LF | $35.00 | $13.72 | 2.55x | $18,042 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $3,500.00 | $11,585.04 | 0.30x | -$113,191 |
| 104-7018 REMOV CONC (CURB OR CURB & GUTTER) | 4,926 LF | $3.00 | $11.27 | 0.27x | -$40,720 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 1 EA | $6,061.33 | $34,944.96 | 0.17x | -$28,884 |
ENCINO LANDSCAPE, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 553 SY | $200.00 | $60.19 | 3.32x | $77,314 |
| 529-7015 CONC CURB (TY F2) | 442 LF | $300.00 | $154.71 | 1.94x | $64,219 |
| 529-7016 CONC CURB (TY C1) | 391 LF | $250.00 | $121.20 | 2.06x | $50,361 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 848 LF | $40.00 | $13.72 | 2.91x | $22,282 |
| 752-7002 SPOT TREE TRIMMING / BRUSH REMOVAL | 370 LF | $50.00 | $1.20 | 41.70x | $18,056 |
| 100-7002 PREPARING ROW | 47 STA | $1,000.00 | $6,072.92 | 0.16x | -$238,427 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 1 EA | $10,000.00 | $34,944.96 | 0.29x | -$24,945 |