US 90 (@ HILLEBRANDT BAYOU)BRIDGE REHAB
0028-07-059 · let Jul 1, 2025 · Jefferson, Beaumont · Bridge Maintenance
$5,167,740Low bid: RAGLE CONSTRUCTION, INC.-30.7% vs estimate $7,462,308
$808,988Left on the table15.7% gap to the second bid
9BiddersSpread 98% low to high
233Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RAGLE CONSTRUCTION, INC. | $5,167,740 | -30.7% | $808,988 | 2+$364,187 | 3-$1,433,161 | |
| 2 | STRUCTURAL INTEGRITY GROUP LLC | $5,976,728 | +15.7% | -19.9% | $22,012 | 6+$366,888 | 2-$275,276 |
| 3 | GIBSON & ASSOCIATES, INC. | $5,998,740 | +16.1% | -19.6% | $587,942 | 3+$373,208 | 0 |
| 4 | FORDE CONSTRUCTION COMPANY, INC. | $6,586,682 | +27.5% | -11.7% | $783,876 | 5+$903,894 | 0 |
| 5 | MB WESTERN INDUSTRIAL CONTRACTING CO. | $7,370,558 | +42.6% | -1.2% | $526,426 | 7+$1,083,585 | 0 |
| 6 | ICOS MANAGEMENT, LLC | $7,896,984 | +52.8% | 5.8% | $590,909 | ||
| 7 | SOUTHERN ROAD & BRIDGE, LLC | $8,487,893 | +64.2% | 13.7% | $1,178,356 | ||
| 8 | GREY SKY CONSTRUCTION LLC | $9,666,249 | +87.0% | 29.5% | $575,657 | ||
| 9 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $10,241,906 | +98.2% | 37.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RAGLE CONSTRUCTION, INC. vs STRUCTURAL INTEGRITY GROUP LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 18,450 LF | $1.00 | $41.50 | $40.65 | $747,225 |
| 439-7015 POLYESTER POLYMER CONC OVERLAY (3/4") | 13,200 SY | $170.00 | $119.00 | $106.74 | -$673,200 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 103,979 SY | $4.35 | $9.00 | $10.07 | $483,502 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $33,850.00 | $17,250.00 | $11,585.04 | -$232,400 |
| 500-7001 MOBILIZATION | 1 LS | $510,000.00 | $611,000.00 | $523,850.32 | $101,000 |
| 341-7044 D-GR HMA TY-D SAC-A PG64-22 | 210 TON | $400.00 | $835.00 | $257.23 | $91,350 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 18,450 LF | $8.50 | $4.00 | $13.39 | -$83,025 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 1,912 SY | $12.00 | $51.50 | $1.62 | $75,524 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 455 SF | $125.00 | $260.00 | $150.68 | $61,425 |
| 505-7003 TMA (MOBILE OPERATION) | 46 DAY | $150.00 | $1,200.00 | $229.60 | $48,300 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $18,000.00 | $10,000.00 | $9,253.78 | -$48,000 |
| 432-7038 RIPRAP (STONE COMMON)(GROUT)(12 IN) | 177 CY | $250.00 | $475.00 | $270.40 | $39,825 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 50 LF | $350.00 | $1,140.00 | $435.92 | $39,500 |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD) | 75,243 LF | $1.25 | $0.7500 | $0.8015 | -$37,622 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 51 LF | $325.00 | $1,050.00 | $380.94 | $36,975 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 73,432 LF | $1.25 | $0.7500 | $0.8371 | -$36,716 |
| 505-7001 TMA (STATIONARY) | 214 DAY | $100.00 | $250.00 | $217.57 | $32,100 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 4 EA | $7,250.00 | $15,000.00 | $8,780.51 | $31,000 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 663 SF | $50.00 | $91.00 | $95.74 | $27,183 |
| 400-7010 CEM STABIL BKFL | 178 CY | $100.00 | $235.00 | $138.14 | $24,030 |
Positive: the low bidder was cheaper on that item. These 20 items account for $727,977 of the $808,988 gap.
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $33,850.00 | $11,585.04 | 2.92x | $311,709 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $18,000.00 | $9,253.78 | 1.95x | $52,477 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 18,450 LF | $1.00 | $40.65 | 0.02x | -$731,498 |
| 428-7001 PENETRATING CONCRETE SURFACE TREATMENT | 103,979 SY | $4.35 | $10.07 | 0.43x | -$595,020 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 18,420 LF | $3.25 | $9.04 | 0.36x | -$106,643 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7044 D-GR HMA TY-D SAC-A PG64-22 | 210 TON | $835.00 | $257.23 | 3.25x | $121,333 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 1,912 SY | $51.50 | $1.62 | 31.84x | $95,376 |
| 505-7003 TMA (MOBILE OPERATION) | 46 DAY | $1,200.00 | $229.60 | 5.23x | $44,639 |
| 432-7038 RIPRAP (STONE COMMON)(GROUT)(12 IN) | 177 CY | $475.00 | $270.40 | 1.76x | $36,215 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 50 LF | $1,140.00 | $435.92 | 2.62x | $35,204 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 51 LF | $1,050.00 | $380.94 | 2.76x | $34,122 |
| 512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) | 18,450 LF | $4.00 | $13.39 | 0.30x | -$173,238 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 18,420 LF | $3.50 | $9.04 | 0.39x | -$102,038 |
GIBSON & ASSOCIATES, INC.: unbalanced items
Placed 3FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 18,450 LF | $72.00 | $40.65 | 1.77x | $578,452 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 663 SF | $338.00 | $95.74 | 3.53x | $160,616 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 455 SF | $315.00 | $150.68 | 2.09x | $74,766 |
| 7001-7002 BENT CAP/ABUTMENT CAP CLEANING | 15 EA | $4,200.00 | $475.41 | 8.83x | $55,869 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 1,912 SY | $19.50 | $1.62 | 12.06x | $34,192 |
MB WESTERN INDUSTRIAL CONTRACTING CO.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 18,450 LF | $76.00 | $40.65 | 1.87x | $652,252 |
| 341-7044 D-GR HMA TY-D SAC-A PG64-22 | 210 TON | $980.00 | $257.23 | 3.81x | $151,783 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 1,912 SY | $58.20 | $1.62 | 35.99x | $108,186 |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 50 LF | $1,500.00 | $435.92 | 3.44x | $53,204 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 764 LF | $75.00 | $19.19 | 3.91x | $42,637 |
| 780-7001 CNC CRACK REPAIR (DISCRETE)(GRAVITY) | 694 LF | $80.00 | $25.51 | 3.14x | $37,813 |
| 400-7010 CEM STABIL BKFL | 178 CY | $350.00 | $138.14 | 2.53x | $37,710 |