FM 730; SH 114 TO TARRANT CL
0312-04-034 · let Jul 1, 2025 · Wise, Fort Worth · Overlay
$15,286,842Low bid: FOUTSCO PAVING COMPANY, LLC-9.0% vs estimate $16,798,752
$317,693Left on the table2.1% gap to the second bid
4BiddersSpread 17% low to high
520Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FOUTSCO PAVING COMPANY, LLC | $15,286,842 | -9.0% | $317,693 | 6+$2,166,974 | 5-$990,608 | |
| 2 | JAGOE-PUBLIC COMPANY | $15,604,535 | +2.1% | -7.1% | $1,348,751 | 11+$3,327,542 | 3-$495,071 |
| 3 | JAY MILLS CONTRACTING, INCORPORATED | $16,953,287 | +10.9% | 0.9% | $914,099 | 9+$3,069,006 | 2-$566,285 |
| 4 | GREY SKY CONSTRUCTION LLC | $17,867,386 | +16.9% | 6.4% | 12+$3,976,826 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
FOUTSCO PAVING COMPANY, LLC vs JAGOE-PUBLIC COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 20,560 TON | $195.00 | $115.00 | $156.36 | -$1,644,800 |
| 341-7002 D-GR HMA TY-B SAC-B PG64-22 | 6,542 TON | $180.00 | $100.00 | $109.80 | -$523,360 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $40,000.00 | $24,000.00 | $11,585.04 | -$416,000 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 1,454 CY | $190.00 | $450.00 | $190.61 | $378,040 |
| 432-7014 RIPRAP (MOW STRIP)(5 IN) | 516 CY | $550.00 | $1,200.00 | $480.77 | $335,400 |
| 500-7001 MOBILIZATION | 1 LS | $1,400,000.00 | $1,715,000.00 | $523,850.32 | $315,000 |
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) | 5,674 CY | $65.00 | $110.00 | $88.59 | $255,330 |
| 100-7002 PREPARING ROW | 96 STA | $500.00 | $3,000.00 | $6,072.92 | $240,000 |
| 480-7001 CLEAN EXIST CULVERTS | 124 EA | $750.00 | $2,100.00 | $1,712.97 | $167,400 |
| 530-7018 TURNOUTS (ACP) | 405 SY | $500.00 | $100.00 | $82.59 | -$162,000 |
| 354-7051 PLANE ASPH CONC PAV(2") | 155,617 SY | $2.00 | $3.00 | $1.86 | $155,617 |
| 110-7001 EXCAV (ROADWAY) | 11,293 CY | $17.50 | $30.00 | $11.68 | $141,163 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 26,824 SY | $7.00 | $12.00 | $3.04 | $134,120 |
| 466-7178 WINGWALL (PW - 1) (HW=8 FT) | 3 EA | $45,000.00 | $88,000.00 | $42,198.45 | $129,000 |
| 432-7002 RIPRAP (CONC)(5 IN) | 495 CY | $600.00 | $850.00 | $585.15 | $123,750 |
| 530-7010 DRIVEWAYS (ACP) | 11,829 SY | $90.00 | $80.00 | $54.96 | -$118,290 |
| 168-7001 VEGETATIVE WATERING | 1,857 TGL | $1.00 | $60.00 | $8.43 | $109,563 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 706 CY | $189.00 | $310.00 | $179.97 | $85,426 |
| 403-7001 TEMPORARY SPL SHORING | 2,823 SF | $20.00 | $48.00 | $25.56 | $79,044 |
| 134-7009 BACKFILL (TY A OR B)(VEH) | 4,000 CY | $20.00 | $2.00 | $29.93 | -$72,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$287,598 of the $317,693 gap.
FOUTSCO PAVING COMPANY, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,400,000.00 | $523,850.32 | 2.67x | $876,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $40,000.00 | $11,585.04 | 3.45x | $738,789 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 3 EA | $100,000.00 | $34,944.96 | 2.86x | $195,165 |
| 530-7018 TURNOUTS (ACP) | 405 SY | $500.00 | $82.59 | 6.05x | $169,049 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 26,824 SY | $7.00 | $3.04 | 2.30x | $106,258 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,200 CY | $50.00 | $12.93 | 3.87x | $81,563 |
| 100-7002 PREPARING ROW | 96 STA | $500.00 | $6,072.92 | 0.08x | -$535,000 |
| 344-7077 TACK COAT | 39,312 GAL | $0.1000 | $3.25 | 0.03x | -$123,746 |
| 480-7001 CLEAN EXIST CULVERTS | 124 EA | $750.00 | $1,712.97 | 0.44x | -$119,409 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 1,352 DAY | $1.00 | $87.82 | 0.01x | -$117,377 |
| 505-7001 TMA (STATIONARY) | 439 DAY | $1.00 | $217.57 | 0.00x | -$95,075 |
JAGOE-PUBLIC COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,715,000.00 | $523,850.32 | 3.27x | $1,191,150 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 1,454 CY | $450.00 | $190.61 | 2.36x | $377,150 |
| 432-7014 RIPRAP (MOW STRIP)(5 IN) | 516 CY | $1,200.00 | $480.77 | 2.50x | $371,120 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $24,000.00 | $11,585.04 | 2.07x | $322,789 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 26,824 SY | $12.00 | $3.04 | 3.95x | $240,378 |
| 110-7001 EXCAV (ROADWAY) | 11,293 CY | $30.00 | $11.68 | 2.57x | $206,863 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 3 EA | $100,000.00 | $34,944.96 | 2.86x | $195,165 |
| 466-7178 WINGWALL (PW - 1) (HW=8 FT) | 3 EA | $88,000.00 | $42,198.45 | 2.09x | $137,405 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,200 CY | $60.00 | $12.93 | 4.64x | $103,563 |
| 168-7001 VEGETATIVE WATERING | 1,857 TGL | $60.00 | $8.43 | 7.11x | $95,759 |
| 100-7002 PREPARING ROW | 96 STA | $3,000.00 | $6,072.92 | 0.49x | -$295,000 |
| 134-7009 BACKFILL (TY A OR B)(VEH) | 4,000 CY | $2.00 | $29.93 | 0.07x | -$111,705 |
| 344-7077 TACK COAT | 39,312 GAL | $1.00 | $3.25 | 0.31x | -$88,366 |
JAY MILLS CONTRACTING, INCORPORATED: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,600,000.00 | $523,850.32 | 3.05x | $1,076,150 |
| 530-7010 DRIVEWAYS (ACP) | 11,829 SY | $102.00 | $54.96 | 1.86x | $556,489 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $30,000.00 | $11,585.04 | 2.59x | $478,789 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 52,700 SY | $7.95 | $1.95 | 4.08x | $316,369 |
| 110-7001 EXCAV (ROADWAY) | 11,293 CY | $25.00 | $11.68 | 2.14x | $150,398 |
| 680-7002 INSTALL HWY TRF SIG (ISOLATED) | 3 EA | $84,700.00 | $34,944.96 | 2.42x | $149,265 |
| 403-7001 TEMPORARY SPL SHORING | 2,823 SF | $77.00 | $25.56 | 3.01x | $145,213 |
| 530-7018 TURNOUTS (ACP) | 405 SY | $335.00 | $82.59 | 4.06x | $102,224 |
| 760-7001 DITCH CLEANING AND RESHAPING (FOOT) | 5,075 LF | $20.50 | $1.96 | 10.48x | $94,109 |
| 100-7002 PREPARING ROW | 96 STA | $1,500.00 | $6,072.92 | 0.25x | -$439,000 |
| 344-7077 TACK COAT | 39,312 GAL | $0.0100 | $3.25 | 0.00x | -$127,284 |
GREY SKY CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,600,000.00 | $523,850.32 | 3.05x | $1,076,150 |
| 100-7002 PREPARING ROW | 96 STA | $16,600.00 | $6,072.92 | 2.73x | $1,010,600 |
| 354-7051 PLANE ASPH CONC PAV(2") | 155,617 SY | $5.00 | $1.86 | 2.69x | $489,104 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 52,700 SY | $10.00 | $1.95 | 5.14x | $424,404 |
| 403-7001 TEMPORARY SPL SHORING | 2,823 SF | $85.00 | $25.56 | 3.33x | $167,797 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 26,824 SY | $8.00 | $3.04 | 2.63x | $133,082 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 6 EA | $30,000.00 | $8,780.51 | 3.42x | $127,317 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 2,200 CY | $65.00 | $12.93 | 5.03x | $114,563 |
| 105-7036 RMV (16") TRT/UNTRT BASE & ASPH PAV | 3,909 SY | $35.00 | $6.03 | 5.80x | $113,246 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 22 EA | $6,500.00 | $1,471.00 | 4.42x | $110,638 |