FY26 BAO FDCR
6481-99-001 · let Jul 1, 2025 · Jefferson, Beaumont · Routine Maintenance Project - Sealed
$879,310Low bid: O. TREVINO CONSTRUCTION, LLC-24.8% vs estimate $1,169,487
$86,376Left on the table9.8% gap to the second bid
4BiddersSpread 53% low to high
12Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | O. TREVINO CONSTRUCTION, LLC | $879,310 | -24.8% | $86,376 | 2+$69,321 | 1-$438,850 | |
| 2 | ISI CONTRACTING, INC. | $965,686 | +9.8% | -17.4% | $33,229 | 2+$642,215 | 6-$687,726 |
| 3 | WINDING ROAD CONSTRUCTION, INC. | $998,915 | +13.6% | -14.6% | $346,355 | 2+$69,047 | 2-$460,449 |
| 4 | GREY SKY CONSTRUCTION LLC | $1,345,270 | +53.0% | 15.0% | 3+$293,997 | 1-$393,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
O. TREVINO CONSTRUCTION, LLC vs ISI CONTRACTING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 86 DAY | $205.00 | $6,500.00 | $217.57 | $541,370 |
| 361-7046 FULL-DEPTH REPAIR CPJR (VAR DEPTH) | 276 CY | $1,400.00 | $800.00 | $1,415.64 | -$165,600 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 148 LF | $750.00 | $55.00 | $380.94 | -$102,860 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 35 DAY | $180.00 | $3,000.00 | $87.82 | $98,700 |
| 500-7001 MOBILIZATION | 1 LS | $85,000.00 | $1.00 | $523,850.32 | -$84,999 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $15,000.00 | $1,500.00 | $11,585.04 | -$67,500 |
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 51 CY | $1,650.00 | $785.00 | $1,211.78 | -$44,115 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 3,754 LF | $15.00 | $5.00 | $15.92 | -$37,540 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 264 GAL | $105.00 | $10.00 | $72.23 | -$25,080 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 50 CF | $500.00 | $50.00 | $206.00 | -$22,500 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 200 EA | $12.00 | $3.25 | $1.03 | -$1,750 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 200 EA | $12.00 | $3.25 | $0.5715 | -$1,750 |
Positive: the low bidder was cheaper on that item. These 12 items account for $86,376 of the $86,376 gap.
O. TREVINO CONSTRUCTION, LLC: unbalanced items
Placed 1ISI CONTRACTING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 86 DAY | $6,500.00 | $217.57 | 29.88x | $540,289 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 35 DAY | $3,000.00 | $87.82 | 34.16x | $101,926 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $523,850.32 | 0.00x | -$523,849 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 MO | $1,500.00 | $11,585.04 | 0.13x | -$50,425 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 148 LF | $55.00 | $380.94 | 0.14x | -$48,239 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 3,754 LF | $5.00 | $15.92 | 0.31x | -$40,984 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 264 GAL | $10.00 | $72.23 | 0.14x | -$16,429 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 50 CF | $50.00 | $206.00 | 0.24x | -$7,800 |
WINDING ROAD CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 148 LF | $750.00 | $380.94 | 1.97x | $54,621 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 35 DAY | $500.00 | $87.82 | 5.69x | $14,426 |
| 500-7001 MOBILIZATION | 1 LS | $95,000.00 | $523,850.32 | 0.18x | -$428,850 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 3,754 LF | $7.50 | $15.92 | 0.47x | -$31,599 |
GREY SKY CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 3,754 LF | $80.00 | $15.92 | 5.03x | $240,566 |
| 720-7003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 264 GAL | $200.00 | $72.23 | 2.77x | $33,731 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 50 CF | $600.00 | $206.00 | 2.91x | $19,700 |
| 500-7001 MOBILIZATION | 1 LS | $130,000.00 | $523,850.32 | 0.25x | -$393,850 |