6488-32-001 Callout Bridge Repair
6488-32-001 · let Aug 12, 2025 · Reeves, Odessa · Routine Maintenance Project - Sealed
$520,679Low bid: PREMIER CONTRACTORS LLC-24.2% vs estimate $686,750
$139,196Left on the table26.7% gap to the second bid
2BiddersSpread 27% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PREMIER CONTRACTORS LLC | $520,679 | -24.2% | $139,196 | 4+$234,979 | 2-$28,168 | |
| 2 | SCR CIVIL CONSTRUCTION, LLC | $659,875 | +26.7% | -3.9% | 9+$357,912 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
PREMIER CONTRACTORS LLC vs SCR CIVIL CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 5 EA | $10,000.00 | $22,000.00 | $6,492.05 | $60,000 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 750 SF | $350.00 | $300.00 | $150.68 | -$37,500 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $250.00 | $217.57 | $24,900 |
| 788-7001 CONCRETE BEAM REPAIR | 5 EA | $5,000.00 | $9,500.00 | $4,623.25 | $22,500 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 3 EA | $5,000.00 | $12,000.00 | $5,892.50 | $21,000 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 3 EA | $18,000.00 | $23,000.00 | $10,082.27 | $15,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $1.00 | $3,000.00 | $600.85 | $11,996 |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 150 LF | $60.00 | $130.00 | $46.07 | $10,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 75 DAY | $1.00 | $105.00 | $87.82 | $7,800 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 150 SF | $300.00 | $320.00 | $95.74 | $3,000 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 150 SF | $400.00 | $400.00 | $192.68 | $0 |
Positive: the low bidder was cheaper on that item. These 11 items account for $139,196 of the $139,196 gap.
PREMIER CONTRACTORS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 750 SF | $350.00 | $150.68 | 2.32x | $149,490 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 150 SF | $400.00 | $192.68 | 2.08x | $31,098 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 150 SF | $300.00 | $95.74 | 3.13x | $30,639 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 3 EA | $18,000.00 | $10,082.27 | 1.79x | $23,753 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 75 DAY | $1.00 | $87.82 | 0.01x | -$6,511 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 750 SF | $300.00 | $150.68 | 1.99x | $111,990 |
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 5 EA | $22,000.00 | $6,492.05 | 3.39x | $77,540 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 3 EA | $23,000.00 | $10,082.27 | 2.28x | $38,753 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 150 SF | $320.00 | $95.74 | 3.34x | $33,639 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 150 SF | $400.00 | $192.68 | 2.08x | $31,098 |
| 788-7001 CONCRETE BEAM REPAIR | 5 EA | $9,500.00 | $4,623.25 | 2.05x | $24,384 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 3 EA | $12,000.00 | $5,892.50 | 2.04x | $18,323 |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 150 LF | $130.00 | $46.07 | 2.82x | $12,590 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $3,000.00 | $600.85 | 4.99x | $9,597 |