FY26 NE TxDOT Region Road and Brine Salt
6485-89-001 · let Aug 7, 2025 · Titus, Maintenance Division · Material Maintenance Project
$1,244,298Low bid: NSG LOGISTICS, LLC-2.6% vs estimate $1,277,000
$655,703Left on the table52.7% gap to the second bid
2BiddersSpread 53% low to high
20Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | NSG LOGISTICS, LLC | $1,244,298 | -2.6% | $655,703 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $1,900,000 | +52.7% | 48.8% | 3+$103,541 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
NSG LOGISTICS, LLC vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8014-7344 CAT 8A-R ROAD SALT (DEL)(SITE 1) | 750 TON | $96.61 | $190.00 | $121.17 | $70,043 |
| 8014-7345 CAT 8A-R ROAD SALT (DEL)(SITE 2) | 750 TON | $96.82 | $190.00 | $111.18 | $69,885 |
| 8014-7348 CAT 8A-R ROAD SALT (DEL)(SITE 5) | 750 TON | $101.92 | $190.00 | $108.50 | $66,060 |
| 8014-7346 CAT 8A-R ROAD SALT (DEL)(SITE 3) | 750 TON | $105.32 | $190.00 | $119.18 | $63,510 |
| 8014-7347 CAT 8A-R ROAD SALT (DEL)(SITE 4) | 750 TON | $118.71 | $190.00 | $115.22 | $53,468 |
| 8014-7458 CAT 8C-B BRINE SALT (DEL)(SITE 1) | 750 TON | $135.40 | $190.00 | $157.34 | $40,950 |
| 8014-7459 CAT 8C-B BRINE SALT (DEL)(SITE 2) | 750 TON | $135.61 | $190.00 | $159.18 | $40,793 |
| 8014-7462 CAT 8C-B BRINE SALT (DEL)(SITE 5) | 750 TON | $140.71 | $190.00 | $146.14 | $36,968 |
| 8014-7460 CAT 8C-B BRINE SALT (DEL)(SITE 3) | 750 TON | $144.11 | $190.00 | $143.06 | $34,418 |
| 8014-7461 CAT 8C-B BRINE SALT (DEL)(SITE 4) | 750 TON | $157.50 | $190.00 | $151.85 | $24,375 |
| 8014-7363 CAT 8A-R ROAD SALT (DEL)(SITE 1)(EXP) | 250 TON | $99.75 | $190.00 | $115.69 | $22,563 |
| 8014-7364 CAT 8A-R ROAD SALT (DEL)(SITE 2)(EXP) | 250 TON | $99.96 | $190.00 | $103.55 | $22,510 |
| 8014-7367 CAT 8A-R ROAD SALT (DEL)(SITE 5)(EXP) | 250 TON | $105.06 | $190.00 | $106.79 | $21,235 |
| 8014-7365 CAT 8A-R ROAD SALT (DEL)(SITE 3)(EXP) | 250 TON | $108.46 | $190.00 | $119.31 | $20,385 |
| 8014-7366 CAT 8A-R ROAD SALT (DEL)(SITE 4)(EXP) | 250 TON | $121.85 | $190.00 | $127.41 | $17,038 |
| 8014-7477 CAT 8C-B BRINE SALT (DEL)(SITE 1)(EXP) | 250 TON | $141.53 | $190.00 | $172.25 | $12,118 |
| 8014-7478 CAT 8C-B BRINE SALT (DEL)(SITE 2)(EXP) | 250 TON | $141.74 | $190.00 | $164.57 | $12,065 |
| 8014-7481 CAT 8C-B BRINE SALT (DEL)(SITE 5)(EXP) | 250 TON | $146.84 | $190.00 | $194.02 | $10,790 |
| 8014-7479 CAT 8C-B BRINE SALT (DEL)(SITE 3)(EXP) | 250 TON | $150.24 | $190.00 | $171.31 | $9,940 |
| 8014-7480 CAT 8C-B BRINE SALT (DEL)(SITE 4)(EXP) | 250 TON | $163.63 | $190.00 | $179.79 | $6,593 |
Positive: the low bidder was cheaper on that item. These 20 items account for $655,703 of the $655,703 gap.