Crack Seal 01 0825
6481-63-001 · let Aug 13, 2025 · Navarro, Dallas · Routine Maintenance Project - Sealed
$147,118Low bid: D & M CONTRACTORS, LLC-10.8% vs estimate $164,841
$28,401Left on the table19.3% gap to the second bid
3BiddersSpread 65% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | D & M CONTRACTORS, LLC | $147,118 | -10.8% | $28,401 | 0 | 3-$542,148 | |
| 2 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $175,519 | +19.3% | 6.5% | $66,787 | 0 | 3-$549,482 |
| 3 | ICOS MANAGEMENT, LLC | $242,306 | +64.7% | 47.0% | 0 | 3-$514,384 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
D & M CONTRACTORS, LLC vs GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 168.56 LMI | $800.00 | $1,012.00 | $868.20 | $35,735 |
| 500-7001 MOBILIZATION | 1 LS | $12,000.00 | $4,900.00 | $523,850.32 | -$7,100 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $5.00 | $1.00 | $217.57 | -$136 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $50.00 | $1.00 | $11,585.04 | -$98 |
Positive: the low bidder was cheaper on that item. These 4 items account for $28,401 of the $28,401 gap.