FM 855, US 69-US 175, SFTY
1161-02-014 · let Aug 8, 2025 · Cherokee, Tyler · Safety Improvement Projects
$4,101,439Low bid: 3LW CIVIL LLC-25.6% vs estimate $5,515,548
$583,693Left on the table14.2% gap to the second bid
13BiddersSpread 104% low to high
91Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | 3LW CIVIL LLC | $4,101,439 | -25.6% | $583,693 | 2+$163,543 | 4-$3,699,523 | |
| 2 | SKYLINE BRIDGE LLC | $4,685,132 | +14.2% | -15.1% | $105,034 | 5+$260,754 | 2-$3,434,870 |
| 3 | THK CONSTRUCTION LLC | $4,790,166 | +16.8% | -13.2% | $196,378 | 1+$98,743 | 2-$2,937,359 |
| 4 | L. S. EQUIPMENT CO., INC. | $4,986,544 | +21.6% | -9.6% | $91,017 | 4+$384,552 | 4-$2,801,121 |
| 5 | BAKER & COMPANY CONSTRUCTION, LLC | $5,077,561 | +23.8% | -7.9% | $151,867 | 2+$112,043 | 3-$2,841,147 |
| 6 | HIGHWAY 19 CONSTRUCTION LLC | $5,229,428 | +27.5% | -5.2% | $225,656 | ||
| 7 | TRUE ROADS CONSTRUCTION LLC | $5,455,084 | +33.0% | -1.1% | $136,353 | ||
| 8 | LONGVIEW BRIDGE AND ROAD, LTD. | $5,591,437 | +36.3% | 1.4% | $98,298 | ||
| 9 | GARRET SHIELDS INFRASTRUCTURE | $5,689,734 | +38.7% | 3.2% | $75,714 | ||
| 10 | EAST TEXAS BRIDGE, INC. | $5,765,449 | +40.6% | 4.5% | $784,100 | ||
| 11 | LAKEY, INC. | $6,549,548 | +59.7% | 18.7% | $637,650 | ||
| 12 | ALTUS CONSTRUCTION LLC | $7,187,199 | +75.2% | 30.3% | $1,190,222 | ||
| 13 | REYNOLDS & KAY, LTD. | $8,377,420 | +104.3% | 51.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
3LW CIVIL LLC vs SKYLINE BRIDGE LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 611 STA | $150.00 | $625.00 | $6,072.92 | $290,225 |
| 132-7017 EMBANK (VEH)(OC)(TY C) | 11,869 CY | $38.33 | $26.00 | $37.09 | -$146,345 |
| 150-7001 BLADING | 126 STA | $1.00 | $600.00 | $152.64 | $75,474 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 47,686 SY | $4.25 | $3.00 | $1.43 | -$59,608 |
| 462-7084 CONC BOX CULV (9 FT X 7 FT)(EXTEND) | 40 LF | $1,529.40 | $2,800.00 | $1,529.40 | $50,824 |
| 466-7192 WINGWALL (PW - 2) (HW=8 FT) | 12 EA | $37,276.17 | $41,000.00 | $33,376.42 | $44,686 |
| 496-7037 REMOV STR (PIPE) | 46 EA | $1,220.33 | $300.00 | $740.62 | -$42,335 |
| 530-7010 DRIVEWAYS (ACP) | 2,623 SY | $55.00 | $70.00 | $54.96 | $39,345 |
| 500-7001 MOBILIZATION | 1 LS | $363,250.00 | $400,000.00 | $523,850.32 | $36,750 |
| 164-7076 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 47,686 SY | $0.0100 | $0.7500 | $0.5910 | $35,288 |
| 505-7001 TMA (STATIONARY) | 203 DAY | $85.00 | $250.00 | $217.57 | $33,495 |
| 464-7003 RC PIPE (CL III)(18 IN) | 1,921 LF | $63.56 | $80.00 | $83.08 | $31,581 |
| 462-7069 CONC BOX CULV (6 FT X 6 FT)(EXTEND) | 92 LF | $1,060.68 | $1,400.00 | $921.45 | $31,217 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 147 EA | $516.45 | $725.00 | $696.14 | $30,657 |
| 403-7001 TEMPORARY SPL SHORING | 8,532 SF | $27.50 | $24.00 | $25.56 | -$29,862 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $6,074.97 | $4,000.00 | $11,585.04 | -$29,050 |
| 462-7078 CONC BOX CULV (8 FT X 6 FT)(EXTEND) | 44 LF | $1,403.04 | $2,000.00 | $1,303.30 | $26,266 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 1,760 LF | $19.80 | $5.00 | $12.47 | -$26,048 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 128 EA | $1,093.30 | $900.00 | $1,176.76 | -$24,742 |
| 530-7018 TURNOUTS (ACP) | 1,551 SY | $55.00 | $70.00 | $82.59 | $23,265 |
Positive: the low bidder was cheaper on that item. These 20 items account for $391,084 of the $583,693 gap.
3LW CIVIL LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 47,686 SY | $4.25 | $1.43 | 2.97x | $134,508 |
| 400-7008 CUT & RESTORE ASPH PAVING | 149 SY | $335.00 | $140.13 | 2.39x | $29,036 |
| 100-7002 PREPARING ROW | 611 STA | $150.00 | $6,072.92 | 0.02x | -$3,618,905 |
| 164-7076 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 47,686 SY | $0.0100 | $0.5910 | 0.02x | -$27,706 |
| 505-7001 TMA (STATIONARY) | 203 DAY | $85.00 | $217.57 | 0.39x | -$26,912 |
| 480-7001 CLEAN EXIST CULVERTS | 27 EA | $750.00 | $1,712.97 | 0.44x | -$26,000 |
SKYLINE BRIDGE LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 47,686 SY | $3.00 | $1.43 | 2.10x | $74,900 |
| 150-7001 BLADING | 126 STA | $600.00 | $152.64 | 3.93x | $56,368 |
| 462-7084 CONC BOX CULV (9 FT X 7 FT)(EXTEND) | 40 LF | $2,800.00 | $1,529.40 | 1.83x | $50,824 |
| 400-7008 CUT & RESTORE ASPH PAVING | 149 SY | $450.00 | $140.13 | 3.21x | $46,171 |
| 432-7014 RIPRAP (MOW STRIP)(5 IN) | 88 CY | $850.00 | $480.77 | 1.77x | $32,492 |
| 100-7002 PREPARING ROW | 611 STA | $625.00 | $6,072.92 | 0.10x | -$3,328,680 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,000.00 | $11,585.04 | 0.35x | -$106,191 |
THK CONSTRUCTION LLC: unbalanced items
Placed 3L. S. EQUIPMENT CO., INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 8,532 SF | $45.00 | $25.56 | 1.76x | $165,857 |
| 462-7084 CONC BOX CULV (9 FT X 7 FT)(EXTEND) | 40 LF | $4,500.00 | $1,529.40 | 2.94x | $118,824 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 47,686 SY | $2.75 | $1.43 | 1.92x | $62,979 |
| 432-7014 RIPRAP (MOW STRIP)(5 IN) | 88 CY | $900.00 | $480.77 | 1.87x | $36,892 |
| 100-7002 PREPARING ROW | 611 STA | $1,750.00 | $6,072.92 | 0.29x | -$2,641,305 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $5,000.00 | $11,585.04 | 0.43x | -$92,191 |
| 505-7001 TMA (STATIONARY) | 203 DAY | $50.00 | $217.57 | 0.23x | -$34,017 |
| 496-7037 REMOV STR (PIPE) | 46 EA | $10.00 | $740.62 | 0.01x | -$33,609 |
BAKER & COMPANY CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 28 DAY | $2,488.00 | $229.60 | 10.84x | $63,235 |
| 150-7001 BLADING | 126 STA | $540.00 | $152.64 | 3.54x | $48,808 |
| 100-7002 PREPARING ROW | 611 STA | $2,065.00 | $6,072.92 | 0.34x | -$2,448,840 |
| 500-7001 MOBILIZATION | 1 LS | $239,050.00 | $523,850.32 | 0.46x | -$284,800 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $3,906.00 | $11,585.04 | 0.34x | -$107,507 |