Specialty Markings Handwork 07 0825
6482-05-001 · let Aug 13, 2025 · Collin, Dallas · Routine Maintenance Project - Sealed
$378,983Low bid: STRIPING TECHNOLOGY, L.P.-34.3% vs estimate $576,426
$14,558Left on the table3.8% gap to the second bid
4BiddersSpread 37% low to high
36Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPING TECHNOLOGY, L.P. | $378,983 | -34.3% | $14,558 | 5+$35,861 | 5-$562,159 | |
| 2 | TRAFFIC HIGHWAY MAINTENANCE, LLC | $393,541 | +3.8% | -31.7% | $5,490 | 4+$22,410 | 5-$542,360 |
| 3 | TRP INFRASTRUCTURE SERVICES, LLC | $399,031 | +5.3% | -30.8% | $119,096 | 1+$2,754 | 3-$582,948 |
| 4 | RHINO EQUITY, LLC | $518,127 | +36.7% | -10.1% | 7+$185,458 | 9-$590,457 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
STRIPING TECHNOLOGY, L.P. vs TRAFFIC HIGHWAY MAINTENANCE, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 100 DAY | $350.00 | $0.1000 | $217.57 | -$34,990 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 12,151 LF | $5.70 | $7.75 | $7.19 | $24,910 |
| 677-7008 ELIM EXT PM & MRKS (24") | 10,585 LF | $2.00 | $4.00 | $2.87 | $21,170 |
| 666-7352 PAVEMENT SLER 24" | 12,151 LF | $2.50 | $1.74 | $1.84 | -$9,235 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $6,500.00 | $11,585.04 | $9,000 |
| 666-7354 PAVEMENT SLER (WORD) | 190 EA | $100.00 | $65.00 | $35.94 | -$6,650 |
| 666-7066 REFL PAV MRK TY I (W)(WORD)(100MIL) | 190 EA | $160.50 | $175.00 | $184.78 | $2,755 |
| 666-7012 REFL PAV MRK TY I (W)6"(LNDP)(100MIL) | 3,908 LF | $2.00 | $2.65 | $1.42 | $2,540 |
| 677-7006 ELIM EXT PM & MRKS (12") | 4,222 LF | $1.50 | $2.00 | $1.27 | $2,111 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $22,000.00 | $523,850.32 | $2,000 |
| 666-7042 REFL PAV MRK TY I (W)(ARROW)(100MIL) | 207 EA | $140.50 | $150.00 | $156.95 | $1,967 |
| 666-7347 PAVEMENT SLER 6" | 3,908 LF | $1.00 | $0.5000 | $0.1841 | -$1,954 |
| 677-7015 ELIM EXT PM & MRKS (WORD) | 190 EA | $100.00 | $90.00 | $53.95 | -$1,900 |
| 677-7001 ELIM EXT PM & MRKS (4") | 3,908 LF | $0.6500 | $1.00 | $0.2643 | $1,368 |
| 666-7087 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) | 63 EA | $75.00 | $60.00 | $34.28 | -$945 |
| 666-7348 PAVEMENT SLER 8" | 850 LF | $2.00 | $1.00 | $0.3318 | -$850 |
| 677-7004 ELIM EXT PM & MRKS (8") | 850 LF | $1.00 | $2.00 | $0.6468 | $850 |
| 677-7012 ELIM EXT PM & MRKS (UTURN ARROW) | 11 EA | $100.00 | $175.00 | $49.92 | $825 |
| 677-7023 ELIM EXT PM & MRKS (18")(YLD TRI) | 63 EA | $25.00 | $37.00 | $23.57 | $756 |
| 666-7045 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) | 12 EA | $222.25 | $275.00 | $240.06 | $633 |
Positive: the low bidder was cheaper on that item. These 20 items account for $14,360 of the $14,558 gap.
STRIPING TECHNOLOGY, L.P.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7354 PAVEMENT SLER (WORD) | 190 EA | $100.00 | $35.94 | 2.78x | $12,172 |
| 666-7353 PAVEMENT SLER (ARROW) | 207 EA | $75.00 | $30.62 | 2.45x | $9,186 |
| 677-7015 ELIM EXT PM & MRKS (WORD) | 190 EA | $100.00 | $53.95 | 1.85x | $8,749 |
| 666-7347 PAVEMENT SLER 6" | 3,908 LF | $1.00 | $0.1841 | 5.43x | $3,189 |
| 666-7087 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) | 63 EA | $75.00 | $34.28 | 2.19x | $2,565 |
| 500-7001 MOBILIZATION | 1 LS | $20,000.00 | $523,850.32 | 0.04x | -$503,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |
| 678-7008 PAV SURF PREP FOR MRK (24") | 12,151 LF | $0.0100 | $0.9416 | 0.01x | -$11,320 |
| 678-7016 PAV SURF PREP FOR MRK (WORD) | 190 EA | $0.0100 | $21.20 | 0.00x | -$4,026 |
| 678-7009 PAV SURF PREP FOR MRK (ARROW) | 207 EA | $0.0100 | $16.69 | 0.00x | -$3,452 |
TRAFFIC HIGHWAY MAINTENANCE, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7353 PAVEMENT SLER (ARROW) | 207 EA | $75.00 | $30.62 | 2.45x | $9,186 |
| 666-7354 PAVEMENT SLER (WORD) | 190 EA | $65.00 | $35.94 | 1.81x | $5,522 |
| 666-7012 REFL PAV MRK TY I (W)6"(LNDP)(100MIL) | 3,908 LF | $2.65 | $1.42 | 1.87x | $4,826 |
| 677-7001 ELIM EXT PM & MRKS (4") | 3,908 LF | $1.00 | $0.2643 | 3.78x | $2,875 |
| 500-7001 MOBILIZATION | 1 LS | $22,000.00 | $523,850.32 | 0.04x | -$501,850 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $0.1000 | $217.57 | 0.00x | -$21,747 |
| 678-7008 PAV SURF PREP FOR MRK (24") | 12,151 LF | $0.0100 | $0.9416 | 0.01x | -$11,320 |
| 678-7016 PAV SURF PREP FOR MRK (WORD) | 190 EA | $0.1000 | $21.20 | 0.00x | -$4,009 |
| 678-7009 PAV SURF PREP FOR MRK (ARROW) | 207 EA | $0.1000 | $16.69 | 0.01x | -$3,434 |
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7087 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) | 63 EA | $78.00 | $34.28 | 2.28x | $2,754 |
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,845.00 | $11,585.04 | 0.25x | -$52,440 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
RHINO EQUITY, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 677-7006 ELIM EXT PM & MRKS (12") | 4,222 LF | $20.00 | $1.27 | 15.70x | $79,061 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $500.00 | $217.57 | 2.30x | $28,243 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 850 LF | $25.00 | $0.9489 | 26.35x | $20,443 |
| 666-7012 REFL PAV MRK TY I (W)6"(LNDP)(100MIL) | 3,908 LF | $6.00 | $1.42 | 4.24x | $17,918 |
| 677-7004 ELIM EXT PM & MRKS (8") | 850 LF | $20.00 | $0.6468 | 30.92x | $16,450 |
| 678-7004 PAV SURF PREP FOR MRK (8") | 850 LF | $15.00 | $0.1162 | 129.09x | $12,651 |
| 677-7001 ELIM EXT PM & MRKS (4") | 3,908 LF | $3.00 | $0.2643 | 11.35x | $10,691 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 666-7352 PAVEMENT SLER 24" | 12,151 LF | $0.4500 | $1.84 | 0.24x | -$16,852 |
| 666-7354 PAVEMENT SLER (WORD) | 190 EA | $1.75 | $35.94 | 0.05x | -$6,495 |
| 666-7353 PAVEMENT SLER (ARROW) | 207 EA | $1.25 | $30.62 | 0.04x | -$6,080 |
| 677-7015 ELIM EXT PM & MRKS (WORD) | 190 EA | $25.00 | $53.95 | 0.46x | -$5,501 |
| 677-7009 ELIM EXT PM & MRKS (ARROW) | 207 EA | $25.00 | $50.50 | 0.50x | -$5,278 |
| 678-7016 PAV SURF PREP FOR MRK (WORD) | 190 EA | $2.00 | $21.20 | 0.09x | -$3,648 |
| 678-7009 PAV SURF PREP FOR MRK (ARROW) | 207 EA | $1.00 | $16.69 | 0.06x | -$3,248 |