0077-06-107 US 67 ACP Overlay
0077-06-107 · let Sep 4, 2025 · Tom Green, San Angelo · Overlay
$20,466,166Low bid: REECE ALBERT, INC.-34.7% vs estimate $31,358,149
$1,175,506Left on the table5.7% gap to the second bid
3BiddersSpread 17% low to high
295Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | REECE ALBERT, INC. | $20,466,166 | -34.7% | $1,175,506 | 0 | 1-$266,817 | |
| 2 | RK HALL, LLC | $21,641,672 | +5.7% | -31.0% | $2,341,343 | 3+$1,407,052 | 0 |
| 3 | RAGLE CONSTRUCTION, INC. | $23,983,016 | +17.2% | -23.5% | 3+$3,358,160 | 1-$326,786 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
REECE ALBERT, INC. vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $603,302.25 | $1,234,191.53 | $523,850.32 | $630,889 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $11,950.62 | $42,000.00 | $11,585.04 | $390,642 |
| 451-7006 RETROFIT RAIL (TY T222) | 4,285 LF | $218.14 | $294.80 | $217.20 | $328,488 |
| 110-7002 EXCAV (CHANNEL) | 20,822.47 CY | $3.88 | $17.14 | $16.69 | $276,106 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 16,590.61 SY | $79.00 | $64.46 | $60.19 | -$241,227 |
| 344-7077 TACK COAT | 170,048.11 GAL | $2.41 | $3.56 | $3.25 | $195,555 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 35,538.44 TON | $139.19 | $134.00 | $137.95 | -$184,445 |
| 105-7015 RMV (15"-19") TRT/UNTRT BASE & ASPH PAV | 9,922 SY | $27.90 | $10.47 | $17.92 | -$172,940 |
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) | 8,413.11 CY | $58.57 | $73.28 | $88.59 | $123,757 |
| 354-7052 PLANE ASPH CONC PAV(3") | 148,439.55 SY | $4.30 | $3.48 | $2.92 | -$121,720 |
| 310-7004 PRIME COAT (MC-30) | 59,109.61 GAL | $4.85 | $6.60 | $5.35 | $103,442 |
| 347-7001 TOM-C PG76-22 SAC-A | 33,849.75 TON | $178.21 | $175.55 | $169.86 | -$90,040 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 1,834.19 CY | $65.02 | $16.85 | $16.96 | -$88,353 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 2,552.92 CY | $222.20 | $251.12 | $133.09 | $73,830 |
| 354-7085 PLANE ASPH CONC PAV (0" TO 0.75") | 58,264.67 SY | $1.98 | $1.08 | $1.45 | -$52,438 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 37,220.99 SY | $3.72 | $2.39 | $3.11 | -$49,504 |
| 354-7053 PLANE ASPH CONC PAV(4") | 24,039.44 SY | $5.54 | $7.27 | $3.14 | $41,588 |
| 134-7004 BACKFILL (TY A OR B) | 1,008 STA | $271.36 | $233.22 | $211.21 | -$38,445 |
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 103,441.81 GAL | $4.56 | $4.93 | $3.44 | $38,273 |
| 432-7003 RIPRAP (CONC)(6 IN) | 153 CY | $878.83 | $1,100.00 | $580.25 | $33,839 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,197,297 of the $1,175,506 gap.
REECE ALBERT, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7002 EXCAV (CHANNEL) | 20,822.47 CY | $3.88 | $16.69 | 0.23x | -$266,817 |
RK HALL, LLC: unbalanced items
Placed 2RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,390,000.00 | $523,850.32 | 4.56x | $1,866,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $106,800.00 | $11,585.04 | 9.22x | $1,237,794 |
| 512-7013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) | 3,000 LF | $100.00 | $15.26 | 6.55x | $254,216 |
| 110-7002 EXCAV (CHANNEL) | 20,822.47 CY | $1.00 | $16.69 | 0.06x | -$326,786 |