IH20,FM2087-SABINERVR,EBLDECK
0495-07-081 · let Sep 5, 2025 · Gregg, Tyler · Bridge Replacement
$36,971,035Low bid: LONGVIEW BRIDGE AND ROAD, LTD.-8.1% vs estimate $40,248,856
$560,617Left on the table1.5% gap to the second bid
10BiddersSpread 31% low to high
139Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONGVIEW BRIDGE AND ROAD, LTD. | $36,971,035 | -8.1% | $560,617 | 4+$6,429,898 | 1-$228,522 | |
| 2 | EAST TEXAS BRIDGE, INC. | $37,531,651 | +1.5% | -6.8% | $1,153,603 | 4+$6,510,005 | 1-$217,306 |
| 3 | TRUE ROADS CONSTRUCTION LLC | $38,685,254 | +4.6% | -3.9% | $1,084,856 | 4+$6,715,789 | 1-$217,306 |
| 4 | INDUS ROAD & BRIDGE, INC. | $39,770,109 | +7.6% | -1.2% | $1,765,395 | 5+$8,534,085 | 0 |
| 5 | HIGHWAY 19 CONSTRUCTION LLC | $41,535,504 | +12.3% | 3.2% | $1,978,165 | 7+$11,016,776 | 1-$217,306 |
| 6 | PULICE CONSTRUCTION, INC. | $43,513,669 | +17.7% | 8.1% | $554,352 | ||
| 7 | HARPER BROTHERS CONSTRUCTION LLC | $44,068,021 | +19.2% | 9.5% | $455,456 | ||
| 8 | JAMES CONSTRUCTION GROUP, LLC | $44,523,477 | +20.4% | 10.6% | $3,030,954 | ||
| 9 | ALTUS CONSTRUCTION LLC | $47,554,431 | +28.6% | 18.2% | $1,002,123 | ||
| 10 | COPASA INC | $48,556,554 | +31.3% | 20.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONGVIEW BRIDGE AND ROAD, LTD. vs EAST TEXAS BRIDGE, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,500,000.00 | $2,700,000.00 | $523,850.32 | -$800,000 |
| 508-7001 CONSTRUCTING DETOURS | 18,111 SY | $208.00 | $245.00 | $83.58 | $670,107 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 135,817 CY | $11.00 | $15.75 | $13.19 | $645,131 |
| 110-7001 EXCAV (ROADWAY) | 104,314 CY | $8.00 | $13.00 | $11.68 | $521,570 |
| 360-7008 CONC PVMT (CRCP) (14") | 30,369 SY | $155.00 | $140.00 | $95.74 | -$455,535 |
| 100-7001 PREPARING ROW | 70 AC | $15,000.00 | $18,000.00 | $3,995.94 | $210,000 |
| 422-7001 REINF CONC SLAB | 89,900 SF | $27.00 | $25.00 | $24.45 | -$179,800 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 14,940 LF | $87.00 | $75.00 | $52.29 | -$179,280 |
| 344-7001 SP MIXES SP-B PG64-22 | 16,302 TON | $170.00 | $178.00 | $124.45 | $130,416 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 203,380 SY | $2.50 | $2.00 | $1.43 | -$101,690 |
| 432-7001 RIPRAP (CONC)(4 IN) | 1,128 CY | $550.00 | $640.00 | $573.24 | $101,520 |
| 450-7024 RAIL (TY SSTR) | 9,500 LF | $65.00 | $75.00 | $69.92 | $95,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $7,500.00 | $5,000.00 | $11,585.04 | -$82,500 |
| 420-7052 CL C CONC (RAIL FOUNDATION) | 97 CY | $750.00 | $1,500.00 | $552.17 | $72,750 |
| 168-7001 VEGETATIVE WATERING | 6,712 TGL | $14.50 | $5.00 | $8.43 | -$63,764 |
| 416-7008 DRILL SHAFT (48 IN) | 1,440 LF | $445.00 | $480.00 | $400.14 | $50,400 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $150,000.00 | $200,000.00 | $378,521.97 | $50,000 |
| 420-7038 CL C CONC (COLUMN) | 517.9 CY | $1,000.00 | $1,075.00 | $1,548.37 | $38,843 |
| 400-7010 CEM STABIL BKFL | 775.2 CY | $228.00 | $185.00 | $138.14 | -$33,334 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 1,664 CY | $190.00 | $210.00 | $190.61 | $33,280 |
Positive: the low bidder was cheaper on that item. These 20 items account for $723,114 of the $560,617 gap.
LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,500,000.00 | $523,850.32 | 6.68x | $2,976,150 |
| 508-7001 CONSTRUCTING DETOURS | 18,111 SY | $208.00 | $83.58 | 2.49x | $2,253,282 |
| 100-7001 PREPARING ROW | 70 AC | $15,000.00 | $3,995.94 | 3.75x | $770,284 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 22,057 SY | $38.00 | $18.50 | 2.05x | $430,182 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $150,000.00 | $378,521.97 | 0.40x | -$228,522 |
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 18,111 SY | $245.00 | $83.58 | 2.93x | $2,923,389 |
| 500-7001 MOBILIZATION | 1 LS | $2,700,000.00 | $523,850.32 | 5.15x | $2,176,150 |
| 100-7001 PREPARING ROW | 70 AC | $18,000.00 | $3,995.94 | 4.50x | $980,284 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 22,057 SY | $38.00 | $18.50 | 2.05x | $430,182 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $5,000.00 | $11,585.04 | 0.43x | -$217,306 |
TRUE ROADS CONSTRUCTION LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,650,000.00 | $523,850.32 | 6.97x | $3,126,150 |
| 508-7001 CONSTRUCTING DETOURS | 18,111 SY | $215.00 | $83.58 | 2.57x | $2,380,059 |
| 100-7001 PREPARING ROW | 70 AC | $14,500.00 | $3,995.94 | 3.63x | $735,284 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 22,057 SY | $40.00 | $18.50 | 2.16x | $474,296 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $5,000.00 | $11,585.04 | 0.43x | -$217,306 |
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,970,000.00 | $523,850.32 | 7.58x | $3,446,150 |
| 508-7001 CONSTRUCTING DETOURS | 18,111 SY | $210.00 | $83.58 | 2.51x | $2,289,504 |
| 344-7001 SP MIXES SP-B PG64-22 | 16,302 TON | $234.00 | $124.45 | 1.88x | $1,785,922 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 22,057 SY | $45.00 | $18.50 | 2.43x | $584,581 |
| 100-7001 PREPARING ROW | 70 AC | $10,109.21 | $3,995.94 | 2.53x | $427,929 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $4,000,000.00 | $523,850.32 | 7.64x | $3,476,150 |
| 508-7001 CONSTRUCTING DETOURS | 18,111 SY | $248.00 | $83.58 | 2.97x | $2,977,722 |
| 360-7008 CONC PVMT (CRCP) (14") | 30,369 SY | $178.00 | $95.74 | 1.86x | $2,498,011 |
| 450-7024 RAIL (TY SSTR) | 9,500 LF | $180.00 | $69.92 | 2.57x | $1,045,738 |
| 100-7001 PREPARING ROW | 70 AC | $10,450.00 | $3,995.94 | 2.62x | $451,784 |
| 514-7005 PERM CTB (SGL SLOPE) (TY 1) (48 ) | 4,107 LF | $180.00 | $95.40 | 1.89x | $347,472 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 19,180 LF | $19.00 | $7.54 | 2.52x | $219,899 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 33 MO | $5,000.00 | $11,585.04 | 0.43x | -$217,306 |