CR 315 BRIDGE REPLACEMENT 2609
0913-21-054 · let Sep 5, 2025 · Matagorda, Yoakum · Bridge Replacement
$1,833,937Low bid: E-Z BEL CONSTRUCTION, LLC+13.9% vs estimate $1,610,026
$284,591Left on the table15.5% gap to the second bid
4BiddersSpread 30% low to high
82Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | E-Z BEL CONSTRUCTION, LLC | $1,833,937 | 13.9% | $284,591 | 7+$222,797 | 2-$464,701 | |
| 2 | TREVWAY, INC. | $2,118,528 | +15.5% | 31.6% | $63,741 | 10+$360,866 | 1-$100,850 |
| 3 | STX CIVIL | $2,182,269 | +19.0% | 35.5% | $196,621 | 10+$685,541 | 2-$454,701 |
| 4 | RAGLE CONSTRUCTION, INC. | $2,378,890 | +29.7% | 47.8% | 6+$723,751 | 1-$298,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
E-Z BEL CONSTRUCTION, LLC vs TREVWAY, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $300,000.00 | $523,850.32 | $175,000 |
| 420-7015 CL C CONC (ABUT)(HPC)(SRC) | 38 CY | $1,700.00 | $3,500.00 | $1,700.00 | $68,400 |
| 247-7196 FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS) | 487.3 CY | $110.00 | $222.00 | $88.48 | $54,578 |
| 416-7004 DRILL SHAFT (24 IN) | 468 LF | $290.00 | $400.00 | $234.98 | $51,480 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 1,031 CY | $70.00 | $22.00 | $18.71 | -$49,488 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $27,000.00 | $45,000.00 | $28,021.15 | $36,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $5,000.00 | $1,500.00 | $11,585.04 | -$35,000 |
| 416-7006 DRILL SHAFT (36 IN) | 384 LF | $360.00 | $450.00 | $280.58 | $34,560 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,320 SF | $30.00 | $55.00 | $28.47 | $33,000 |
| 425-7017 PRESTR CONC SLAB BEAM (5SB12) | 442.5 LF | $350.00 | $300.00 | $242.93 | -$22,125 |
| 422-7002 REINF CONC SLAB (HPC) | 1,950 SF | $45.00 | $35.00 | $26.91 | -$19,500 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 2,340 SF | $29.00 | $22.00 | $23.90 | -$16,380 |
| 100-7002 PREPARING ROW | 9.2 STA | $6,500.00 | $5,000.00 | $6,072.92 | -$13,800 |
| 316-7016 ASPH (RC-250) | 430 GAL | $19.00 | $50.00 | $5.28 | $13,330 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 298 LF | $410.00 | $450.00 | $217.69 | $11,920 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 463 CY | $305.00 | $280.00 | $190.61 | -$11,575 |
| 400-7010 CEM STABIL BKFL | 121 CY | $320.00 | $250.00 | $138.14 | -$8,470 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 18.4 CY | $1,060.00 | $1,500.00 | $111.76 | $8,096 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 320 CY | $300.00 | $275.00 | $184.74 | -$8,000 |
| 450-7008 RAIL (TY T223) | 204 LF | $260.00 | $222.00 | $141.07 | -$7,752 |
Positive: the low bidder was cheaper on that item. These 20 items account for $294,274 of the $284,591 gap.
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 425-7001 PRESTR CONC GIRDER (TX28) | 298 LF | $410.00 | $217.69 | 1.88x | $57,307 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 1,031 CY | $70.00 | $18.71 | 3.74x | $52,877 |
| 450-7009 RAIL (TY T223)(HPC) | 198 LF | $316.00 | $152.11 | 2.08x | $32,450 |
| 450-7008 RAIL (TY T223) | 204 LF | $260.00 | $141.07 | 1.84x | $24,263 |
| 400-7010 CEM STABIL BKFL | 121 CY | $320.00 | $138.14 | 2.32x | $22,005 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 18.4 CY | $1,060.00 | $111.76 | 9.48x | $17,448 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 17.9 CY | $1,075.00 | $156.13 | 6.89x | $16,448 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $523,850.32 | 0.24x | -$398,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $5,000.00 | $11,585.04 | 0.43x | -$65,850 |
TREVWAY, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 425-7001 PRESTR CONC GIRDER (TX28) | 298 LF | $450.00 | $217.69 | 2.07x | $69,227 |
| 420-7015 CL C CONC (ABUT)(HPC)(SRC) | 38 CY | $3,500.00 | $1,700.00 | 2.06x | $68,400 |
| 247-7196 FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS) | 487.3 CY | $222.00 | $88.48 | 2.51x | $65,067 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,320 SF | $55.00 | $28.47 | 1.93x | $35,019 |
| 450-7009 RAIL (TY T223)(HPC) | 198 LF | $300.00 | $152.11 | 1.97x | $29,282 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 18.4 CY | $1,500.00 | $111.76 | 13.42x | $25,544 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 17.9 CY | $1,500.00 | $156.13 | 9.61x | $24,055 |
| 316-7016 ASPH (RC-250) | 430 GAL | $50.00 | $5.28 | 9.48x | $19,231 |
| 400-7010 CEM STABIL BKFL | 121 CY | $250.00 | $138.14 | 1.81x | $13,535 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 727 GAL | $20.00 | $4.17 | 4.79x | $11,507 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $1,500.00 | $11,585.04 | 0.13x | -$100,850 |
STX CIVIL: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7004 DRILL SHAFT (24 IN) | 468 LF | $630.00 | $234.98 | 2.68x | $184,871 |
| 416-7006 DRILL SHAFT (36 IN) | 384 LF | $675.00 | $280.58 | 2.41x | $151,457 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 298 LF | $475.00 | $217.69 | 2.18x | $76,677 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,320 SF | $80.00 | $28.47 | 2.81x | $68,019 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $60,000.00 | $28,021.15 | 2.14x | $63,958 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 1,031 CY | $60.00 | $18.71 | 3.21x | $42,567 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 18.4 CY | $2,000.00 | $111.76 | 17.90x | $34,744 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 17.9 CY | $2,000.00 | $156.13 | 12.81x | $33,005 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 727 GAL | $25.00 | $4.17 | 5.99x | $15,142 |
| 110-7002 EXCAV (CHANNEL) | 648 CY | $40.00 | $16.69 | 2.40x | $15,102 |
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $523,850.32 | 0.32x | -$353,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $1,500.00 | $11,585.04 | 0.13x | -$100,850 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 1,320 SF | $298.50 | $28.47 | 10.48x | $356,439 |
| 100-7002 PREPARING ROW | 9.2 STA | $27,000.00 | $6,072.92 | 4.45x | $192,529 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $75,000.00 | $28,021.15 | 2.68x | $93,958 |
| 110-7001 EXCAV (ROADWAY) | 384 CY | $150.00 | $11.68 | 12.84x | $53,114 |
| 110-7002 EXCAV (CHANNEL) | 648 CY | $40.00 | $16.69 | 2.40x | $15,102 |
| 420-7038 CL C CONC (COLUMN) | 5.6 CY | $3,800.00 | $1,548.37 | 2.45x | $12,609 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |