Bid Tab X-ray: 6488-95-001

Sep 18, 2025 · Hopkins Sign up free
Set your company to personalize scores

Crack Seal-SSAO FY26

6488-95-001 · let Sep 18, 2025 · Hopkins, Paris · Routine Maintenance Project - Sealed

$163,397Low bid: SCOUT 5 CONSTRUCTION LLC+13.2% vs estimate $144,388
$126,428Left on the table77.4% gap to the second bid
4BiddersSpread 163% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1SCOUT 5 CONSTRUCTION LLC $163,39713.2% $126,428 0 3-$528,011
2D & M CONTRACTORS, LLC $289,825+77.4%100.7% $25,863 0 2-$495,077
3GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY $315,688+93.2%118.6% $113,812 0 2-$526,047
4ICOS MANAGEMENT, LLC $429,500+162.9%197.5% 0 3-$482,952

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

SCOUT 5 CONSTRUCTION LLC vs D & M CONTRACTORS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
712-7003 JT / CRCK SEAL (HOT - POURED RUBBER)252.96 LMI $626.17$1,005.00$936.68 $95,829
500-7001 MOBILIZATION1 LS $5,000.00$35,000.00$523,850.32 $30,000
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN30 DAY $0.0100$10.00$87.82 $300
505-7001 TMA (STATIONARY)30 DAY $0.0100$10.00$217.57 $300

Positive: the low bidder was cheaper on that item. These 4 items account for $126,428 of the $126,428 gap.

SCOUT 5 CONSTRUCTION LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $5,000.00$523,850.320.01x-$518,850
505-7001 TMA (STATIONARY)30 DAY $0.0100$217.570.00x-$6,527
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN30 DAY $0.0100$87.820.00x-$2,634

D & M CONTRACTORS, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $35,000.00$523,850.320.07x-$488,850
505-7001 TMA (STATIONARY)30 DAY $10.00$217.570.05x-$6,227

GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $4,300.00$523,850.320.01x-$519,550
505-7001 TMA (STATIONARY)30 DAY $1.00$217.570.00x-$6,497

ICOS MANAGEMENT, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $50,000.00$523,850.320.10x-$473,850
505-7001 TMA (STATIONARY)30 DAY $1.00$217.570.00x-$6,497
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN30 DAY $1.00$87.820.01x-$2,605