Bid Tab X-ray: 6483-20-001

Sep 16, 2025 · Gregg Sign up free
Set your company to personalize scores

FY 26 North Crack Seal

6483-20-001 · let Sep 16, 2025 · Gregg, Tyler · Routine Maintenance Project - Sealed

$283,388Low bid: SCOUT 5 CONSTRUCTION LLC-34.2% vs estimate $430,395
$266,809Left on the table94.1% gap to the second bid
2BiddersSpread 94% low to high
5Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1SCOUT 5 CONSTRUCTION LLC $283,388-34.2% $266,809 0 2-$533,136
2D & M CONTRACTORS, LLC $550,197+94.1%27.8% 0 2-$507,296

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

SCOUT 5 CONSTRUCTION LLC vs D & M CONTRACTORS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
712-7001 JT / CRCK SEAL (RUBBER - ASPHALT)396.86 LMI $625.00$1,200.00$868.20 $228,195
500-7001 MOBILIZATION1 LS $10,000.00$35,000.00$523,850.32 $25,000
712-7005 JT / CRCK ROUT / SEAL(RUBBER - ASPHALT25.35 LMI $1,000.00$1,500.00$1,000.00 $12,675
505-7003 TMA (MOBILE OPERATION)84 DAY $0.0100$10.00$229.60 $839
7010-7002 MAINTENANCE SPEED LIMIT SIGNING10 DAY $0.0100$10.00$117.34 $100

Positive: the low bidder was cheaper on that item. These 5 items account for $266,809 of the $266,809 gap.

SCOUT 5 CONSTRUCTION LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $10,000.00$523,850.320.02x-$513,850
505-7003 TMA (MOBILE OPERATION)84 DAY $0.0100$229.600.00x-$19,285

D & M CONTRACTORS, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $35,000.00$523,850.320.07x-$488,850
505-7003 TMA (MOBILE OPERATION)84 DAY $10.00$229.600.04x-$18,446