FY 26 North Crack Seal
6483-20-001 · let Sep 16, 2025 · Gregg, Tyler · Routine Maintenance Project - Sealed
$283,388Low bid: SCOUT 5 CONSTRUCTION LLC-34.2% vs estimate $430,395
$266,809Left on the table94.1% gap to the second bid
2BiddersSpread 94% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOUT 5 CONSTRUCTION LLC | $283,388 | -34.2% | $266,809 | 0 | 2-$533,136 | |
| 2 | D & M CONTRACTORS, LLC | $550,197 | +94.1% | 27.8% | 0 | 2-$507,296 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
SCOUT 5 CONSTRUCTION LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 396.86 LMI | $625.00 | $1,200.00 | $868.20 | $228,195 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $35,000.00 | $523,850.32 | $25,000 |
| 712-7005 JT / CRCK ROUT / SEAL(RUBBER - ASPHALT | 25.35 LMI | $1,000.00 | $1,500.00 | $1,000.00 | $12,675 |
| 505-7003 TMA (MOBILE OPERATION) | 84 DAY | $0.0100 | $10.00 | $229.60 | $839 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 10 DAY | $0.0100 | $10.00 | $117.34 | $100 |
Positive: the low bidder was cheaper on that item. These 5 items account for $266,809 of the $266,809 gap.